HomeMy WebLinkAboutBakersfield BTP Ch 7 ImplementationImplementation Alta Planning + Design| 7-1 7. Implementation This chapter provides a strategy for implementing the capital project recommendations in this Plan. This implementation strategy and sequence is guided by a criteria-based ranking consistent with the goals of this plan as well as the goals of other City plans and the Metro General Plan. Phased implementation of the recommended projects and programs presented in Chapter 4 and Chapter 5 will take a significant amount of time, subject to a large number of variables. The most important of these variables include availability of funding for non-motorized transportation, the City of Bakersfield’s success in obtaining competitive grant funding, and local community and political support. In the near-term, it is critically important to focus on a group of achievable, high priority projects. These high priority projects are drawn directly from the results of the criteria-based ranking process presented in Table 7-1. The high priority projects identified in Table 7-5 of this chapter represent roughly $2.1 million dollars in capital improvements and site-specific technical traffic studies to support near-term project refinement and development. These projects are intended for near-term implementation in the next one to five years. While this is a significant jump in expenditure for the City of Bakersfield, current trends indicate that Bakersfield is poised to make this jump. The city’s commitment to implementing the goals of the Metro General Plan, to continued investment in Downtown, and commitment to the preparation of the Bicycle Transportation Plan, will certainly attract the wide variety of transportation funding and generate other financing required to complete this high priority project list. 7.1. Bikeway Project Prioritization The intent of prioritizing projects is to create a prioritized list of bicycle projects for implementation. As projects are implemented, lower ranked projects move up the list. The project list and individual projects outlined in this Plan are flexible concepts that serve as a guideline. The high-priority Tier 1 project list, and perhaps the overall system and segments themselves, may change over time as a result of changing bicycling patterns, land use patterns, implementation constraints and opportunities and the development of other transportation system facilities. Projects may be implemented out of scoring order as opportunities or challenges arise. Opportunities may include grant availability, new development projects, or roadway repaving. The City of Bakersfield should review the project list and project ranking at regular intervals to ensure it reflects the most current priorities, needs, and opportunities for implementing the bicycle network in a logical and efficient manner. City of Bakersfield | Bicycle Transportation Plan 7-2 | Alta Planning + Design 7.1.1 Prioritization Criteria The plan’s vision and goals inform the ranking criteria, which were developed with input from the City of Bakersfield and the Bicycle Transportation Plan Steering Committee. These criteria are described in Table 7-1 and outlined below. The criteria include:  Safety  Gap Closure  Community Connections  Employment Connections  School Connections  Public Input Based on the nature of the criterion, the projects were scored:  Score / No Score  Full Score / Half Score / Zero Score  Scaled range from zero to 20 For example, projects evaluated for network connectivity will receive either a zero score or a full score. The project either extends the existing network/overcomes a freeway barrier or does not. By contrast, projects that connect to community destinations can receive a full, half or no score depending on whether it directly connects, indirectly connects or does not connect to a community destination. The maximum potential score for each project is the sum of the maximum potential scores of all project criteria (100). Implementation Alta Planning + Design| 7-3 Table 7-1: Project Ranking Criteria Criteria Description Maximum Score Safety This ranking is based on available collision data identifying corridors with high incidents of bicycle related collisions within a quarter mile buffer of the proposed improvement. Projects are scored on a scaled ranking from zero to 20 with locations with the most collisions receiving the maximum score. 20 Gap Closure Projects that close identified gaps receive 20 points. 20 Community Center Connections Projects that directly connect to community destinations including retail districts, libraries, community centers, and parks, receive 15 points. Projects located within a half mile of these destinations that connect to a bikeway directly connected to the destination receive 7 points Projects that do not connect to a community center receive zero points. 15 Employment Connections Projects that directly connect to any of the ten largest employers or the highest employment census blocks in the City receive 15 points. Projects that connect to a bikeway that connects directly to one of these employers or areas of moderate employment density receive 7 points. Projects that do not connect to major employers, high or moderate employment density areas receive zero points. 15 School Connections Projects that directly connect to schools receive 15 points. Projects that connect to a bikeway that directly connect to a school receive 7 points. Projects that do not connect to schools receive zero points. 15 Public Input Projects that were identified by the community receive 15 points. Projects that were not identified by the community receive zero points. 15 Maximum Total Score100 Bikeway projects were then placed into three phasing groups: Tier 1, Tier 2, and Tier 3.  Tier 1 (>50 points): Tier 1 projects have the highest potential for addressing the City’s goals for bicycle transportation and are intended for near-term project implementation within one to five years.  Tier 2 (30-50 points): Tier 2 projects are intended for development within 6 to 10 years.  Tier 3 (<30 points): Tier 3 projects are not currently ready for implementation but are included as long-term potential bicycle-specific projects over the next 11 to 20 years. Table 7-3 lists the projects and their scores, organized into the three Tiers. City of Bakersfield | Bicycle Transportation Plan 7-4 | Alta Planning + Design 7.1.2 Cost Estimate Assumptions This section presents typical planning level unit costs for constructing bikeways in California’s Central Valley Area, shown in Table 7-2. The cost estimates for each of the recommended bikeway projects is included in Table 7-3. Unit costs presented here are planning-level cost estimates based on typical or average costs experienced by California cities and counties when constructing similar project. While these costs also reflect the suburban nature of the City of Bakersfield, they do not consider project-specific factors such as intensive grading, landscaping, intersection modifications, and right-of-way acquisition that may increase actual construction costs. For some segments project costs may be significantly greater. Table 7-2: Estimated Bikeway Unit Costs Item Quantity Units Unit Cost Total Class III Bike Route – Urban – Per Mile Bike Route Sign/Wayfinding1 10 EA $ 300 $ 3,000 Shared Lane Marking2 20 EA $ 250 $ 5,000 Total Cost Per Mile $ 8,000 Class II Bike Lanes – Urban – Per Mile Bike Lane Sign/Wayfinding 10 EA $ 300 $ 3,000 Striping Removal 10,560 LF $ 1.25 $ 13,200 Striping and Stenciling 10,560 LF $ 2.50 $ 26,400 Total Cost Per Mile $ 42,600 Class I Shared Use Path - 10' paved, 2' shoulders – Per Mile Wayfinding 4 EA $ 300 $ 1,200 Clear and Grub 73,920 SF $ 1.00 $ 73,920 Asphalt Concrete Pavement 52,800 SF $ 8.00 $ 422,400 Decomposed Granite Shoulders 21,120 SF $ 5.00 $ 105,600 Striping4 15,840 LF $ 2.50 $ 39,600 Total Cost Per Mile $ 642,720 1 Assumes five signs per mile in each direction. 2 Assumes shared lane marking are placed every 265 feet. 3 Assumes two signs per mile in each direction. 4 Includes center stripe and striping along path edges. The construction of recommended facilities will also require additional field work to verify conditions. These include but are not limited to: roadway width, travel lanes, actual motor vehicle speeds, motor vehicle volumes, bicycle and motor vehicle travel patterns and conflicts, and pavement conditions. Final bikeway treatments should be selected based on verified conditions. Implementation Alta Planning + Design | 7-5 Table 7-3: Prioritized Bikeway Projects by Tier Class Location Start End Distance (Miles) Study Needed? Family Friendly / Confident Commuter Safety Gap Closure Community Center Connections Employment Connections School Connections Public Input Total Score Tier Cost Estimate II Baker Street Bernard Street California Avenue 1.57 Confident Commuter 11 20 15 15 7 15 83 1 $66,900 II Potomac Avenue S. King Street Monticello Avenue 0.82 Confident Commuter 4 20 15 0 15 15 69 1 $34,900 I River Bike Trail Connection Kern River Parkway Elm Street 0.26 Yes Family Friendly 20 20 15 7 7 0 69 1 $167,100 III Baker Street California Avenue S. King Street 0.35 Confident Commuter 4 20 15 7 7 15 68 1 $2,800 III E. Pacheco Road Hughes Lane Cottonwood Road 2.52 Family Friendly 3 20 15 0 15 15 68 1 $20,200 II Belle Terrace Stine Road Madison Street 3.04 Confident Commuter 4 20 15 7 7 15 68 1 $129,500 III Pin Oak Boulevard Bear Creek Road District Boulevard 1.14 Family Friendly 1 20 15 0 15 15 66 1 $9,100 III Ewoldsen Class III Route Oak Grove Street N. Half Moon Drive 1.43 Family Friendly 1 20 15 0 15 15 66 1 $11,400 III Harris Road Ashe Road Akers Road 1.51 Family Friendly 2 20 15 7 7 15 66 1 $12,100 II Harris Road Ashe Road Wible Road 0.50 Family Friendly 1 20 15 0 15 15 66 1 $21,300 II Hughes Lane Ming Ave E. Pacheco Road 1.50 Confident Commuter 2 20 15 7 7 15 66 1 $63,900 II Harris Road S. Allen Road Ashe Road 4.08 Family Friendly 2 20 15 7 7 15 66 1 $173,800 II Haley Street Panorama Drive Columbus Street 0.87 Confident Commuter 1 20 7 7 15 15 65 1 $37,100 II E. Pacheco Road Gasoline Alley Monitor Street 1.33 Family Friendly 1 20 15 7 7 15 65 1 $56,700 II Akers Road Wilson Rd McKee 3.99 Confident Commuter 1 20 15 7 7 15 65 1 $170,000 I Arvin-Edison Canal Path Stockdale Highway Cottonwood Road 9.54 Yes Family Friendly 1 20 15 7 7 15 65 1 $6,131,500 III 17th Street A Street Truxtun Avenue 1.26 Confident Commuter 4 0 15 15 15 15 64 1 $10,100 II M Street 30th Street 17th Street 0.85 Confident Commuter 4 0 15 15 15 15 64 1 $36,200 City of Bakersfield | Bicycle Transportation Plan 7-6 | Alta Planning + Design Class Location Start End Distance (Miles) Study Needed? Family Friendly / Confident Commuter Safety Gap Closure Community Center Connections Employment Connections School Connections Public Input Total Score Tier Cost Estimate II Sillect Avenue Buck Owens Boulevard Kern River Parkway 1.33 Confident Commuter 20 0 15 7 7 15 64 1 $56,700 I H Street Canal Path Railroad Bridge Highway 99 7.97 Yes Family Friendly 4 0 15 15 15 15 64 1 $5,122,500 I Friant-Kern Canal Seventh Standard Road Kern River 6.10 Yes Family Friendly 1 0 15 15 15 15 61 1 $3,920,600 II Beale Avenue Grace Street 21st Street 1.00 Confident Commuter 11 20 15 7 7 0 60 1 $42,600 II Q Street Columbus Street Highway 178 1.12 Confident Commuter 3 20 15 15 7 0 60 1 $47,700 III Haggin Oaks Blvd Camino Media Limoges Way 0.74 Family Friendly 1 20 7 0 15 15 58 1 $5,900 II Kentucky Street Alta Vista Drive Mt. Vernon Avenue 1.81 Confident Commuter 11 0 15 7 7 15 55 1 $77,100 III Flower Street Alta Vista Drive Owens Street 0.64 Confident Commuter 2 0 15 15 7 15 54 1 $5,100 III S, King Street California Avenue Brundage Lane 1.00 Confident Commuter 4 20 15 0 15 0 54 1 $8,000 III 4th Street Union Avenue City Limits 1.25 Confident Commuter 4 20 15 0 0 15 54 1 $10,000 III Watts Drive Cottonwood Road Madison Street 0.50 Confident Commuter 4 20 15 7 7 0 53 1 $4,000 III Brundage Lane Union Avenue Oswell Street 5.08 Confident Commuter 4 20 15 7 7 0 53 1 $40,600 II Niles Street Alta Vista Drive Virginia Street 1.28 Confident Commuter 1 0 15 15 7 15 53 1 $54,500 II Bernard Street Chester Avenue Mt. Vernon Avenue 2.95 Confident Commuter 4 20 15 7 7 0 53 1 $125,700 III Berkshire Road Stine Road Santana Sun Drive 1.50 Family Friendly 2 20 15 0 15 0 52 1 $12,000 II 21st Street King Street Washington Street 0.89 Confident Commuter 11 20 7 7 7 0 52 1 $37,900 I 178 Overcrossing Height Street Mirador Drive 0.10 Yes Family Friendly 2 20 15 0 15 0 52 1 $64,300 III Laurelglen Boulevard Pin Oak Park Boulevard Gosford Road 0.48 Confident Commuter 1 20 15 0 0 15 51 1 $3,800 Implementation Alta Planning + Design | 7-7 Class Location Start End Distance (Miles) Study Needed? Family Friendly / Confident Commuter Safety Gap Closure Community Center Connections Employment Connections School Connections Public Input Total Score Tier Cost Estimate III Mountain Oak - McInnes Rt Park Path McInnes - Westwold Path 0.59 Family Friendly 1 20 15 0 15 0 51 1 $4,700 III 22nd Street Elm Street F Street 0.72 Confident Commuter 6 0 15 15 0 15 51 1 $5,800 III Christmas Tree Lane Mt Vernon Avenue Panorama Drive 1.65 Confident Commuter 1 20 15 0 15 0 51 1 $13,200 II Madison Street Belle Terrace White Ln 1.00 Confident Commuter 1 20 15 0 15 0 51 1 $42,600 I Park Path Mountain Oak Road Broad Oak Avenue 0.19 Yes Family Friendly 1 20 15 0 15 0 51 1 $122,100 II Wible Road Planz Road Taft Highway 4.00 Confident Commuter 2 20 15 7 7 0 51 1 $170,400 III Pacific Street Union Avenue Alta Vista Drive 0.36 Confident Commuter 1 20 15 7 7 0 50 2 $2,900 III Chinon - Limoges Route McInnes Boulevard Haggin Oaks Boulevard 0.37 Family Friendly 0 20 15 0 15 0 50 2 $3,000 III Maywood - Charger Route Oswell Street Piper Way 1.85 Family Friendly 0 20 15 0 15 0 50 2 $14,800 I McInnes - Westwold Path McInnes Boulevard Westwold Drive 0.08 Yes Family Friendly 0 20 15 0 15 0 50 2 $51,400 II Riverlakes Drive Olive Drive Coffee Road 1.57 Confident Commuter 1 20 15 7 7 0 50 2 $66,900 II Stine Road Panama Lane Taft Highway 2.00 Confident Commuter 0 20 15 0 15 0 50 2 $85,200 II Noriega Road Renfro Rd Calloway Drive 2.01 Confident Commuter 0 20 15 0 15 0 50 2 $85,600 III Marella Class III Garnsey Avenue Montclair Street 0.55 Confident Commuter 5 0 15 7 7 15 49 2 $4,400 III Marella Way California Avenue Montclair Street 1.00 Confident Commuter 5 0 15 7 7 15 49 2 $8,000 II Hosking Avenue Wible Rd Cottonwood Road 3.03 Yes Confident Commuter 0 20 15 7 7 0 49 2 $129,100 II P Street Brundage Lane Belle Terrace 0.50 Confident Commuter 3 0 15 7 7 15 47 2 $21,300 City of Bakersfield | Bicycle Transportation Plan 7-8 | Alta Planning + Design Class Location Start End Distance (Miles) Study Needed? Family Friendly / Confident Commuter Safety Gap Closure Community Center Connections Employment Connections School Connections Public Input Total Score Tier Cost Estimate III Sundale Avenue La Puente Drive New Stine Road 0.91 Family Friendly 1 0 15 15 15 0 46 2 $7,300 III Palm Street Real Road P Street 1.79 Confident Commuter 2 0 15 7 7 15 46 2 $14,300 II Verdugo Lane Olive Drive Hagaman Road 1.22 Confident Commuter 1 0 15 0 15 15 46 2 $52,000 II A St/Hughes Ln California Ave Terrace Way 1.26 Yes Confident Commuter 2 0 15 7 7 15 46 2 $53,700 III Raider Drive Planz Road Merrimac Avenue 0.25 Confident Commuter 15 0 15 0 15 0 45 2 $2,000 III University Avenue Haley Street River Boulevard 0.58 Confident Commuter 1 0 7 7 15 15 45 2 $4,600 III Quailwood - Quailridge Truxtun Avenue Stockdale Highway 1.02 Confident Commuter 1 0 15 7 7 15 45 2 $8,200 III School House Road Ming Ave Ashe Road 1.33 Family Friendly 1 0 15 7 7 15 45 2 $10,600 III 18th St - 19th St Route 21st Street 17th Street 1.01 Confident Commuter 0 0 15 7 7 15 44 2 $8,100 II Calloway Drive Snow Road Norris Road 0.50 Confident Commuter 8 20 15 0 0 0 43 2 $21,300 II Panama Lane H Street Cottonwood Road 2.03 Confident Commuter 2 20 7 7 7 0 43 2 $86,500 III Broad Oak - Oak Grove Rt Park Path Westwold Drive 0.20 Confident Commuter 0 20 7 0 15 0 42 2 $1,600 III Ridge Oak Drive Rose Petal Street Mountain Oak Road 0.42 Family Friendly 1 20 7 7 7 0 42 2 $3,400 III Harris Rd-Gasoline Alley Wible Road Pacheco Road 0.70 Family Friendly 0 20 7 0 0 15 42 2 $5,600 III White Lane Dovewood Street Hughes Lane 1.22 Confident Commuter 1 20 7 7 7 0 42 2 $9,800 II Morning Drive Auburn Street Willis Avenue 1.38 Confident Commuter 0 20 7 0 15 0 42 2 $58,800 II Snow Road Allen Road Verdugo Lane 1.50 Confident Commuter 1 20 7 7 7 0 42 2 $63,900 Implementation Alta Planning + Design | 7-9 Class Location Start End Distance (Miles) Study Needed? Family Friendly / Confident Commuter Safety Gap Closure Community Center Connections Employment Connections School Connections Public Input Total Score Tier Cost Estimate II Clay Patrick Farr Way Hageman Road Granite Falls Dr 0.83 Confident Commuter 0 20 7 7 7 0 41 2 $35,400 I Buena Vista Canal Path Ming Ave Taft Hwy 8.29 Yes Family Friendly 1 0 7 15 15 0 38 2 $5,328,100 III Merrimac Avenue Raider Drive Monitor Street 0.06 Confident Commuter 15 0 7 0 15 0 37 2 $500 III Monitor Street Merrimac Avenue White Lane 0.25 Confident Commuter 15 0 7 0 15 0 37 2 $2,000 III Spring Creek Loop Wilderness Drive Reliance Drive 1.03 Confident Commuter 1 0 7 7 7 15 37 2 $8,200 III Mountain Vista Drive Grand Lakes Avenue Berkshire Road 2.73 Family Friendly 1 0 7 7 7 15 37 2 $21,800 II Half Moon Drive Ashe Rd Ashe Rd 1.15 Family Friendly 1 0 7 7 7 15 37 2 $49,000 I Bakersfield Commons Conn. Coffee Road Friant-Kern Canal 0.44 Yes Family Friendly 1 0 7 7 7 15 37 2 $282,800 III Madison Street Brundage Lane Belle Terrace 0.49 Confident Commuter 1 20 15 0 0 0 36 2 $3,900 III Jewetta Avenue Palm Avenue Brimhall Road 0.50 Confident Commuter 1 20 15 0 0 0 36 2 $4,000 II University Avenue Columbus Street Panorama Drive 0.68 Confident Commuter 1 20 15 0 0 0 36 2 $29,000 I Coffee Road Path Widening Truxtun Avenue Kern River Parkway 0.06 Yes Family Friendly 1 20 15 0 0 0 36 2 $38,600 II Gosford Road Harris Road Taft Highway 2.50 Confident Commuter 1 20 15 0 0 0 36 2 $106,500 III Comanche Drive City Limit Highway 178 0.16 Confident Commuter 0 20 15 0 0 0 35 2 $1,300 III Campus Park Buena Vista Road Old River Road 1.06 Confident Commuter 1 20 0 7 7 0 35 2 $8,500 II Patton Way Weldon Avenue Hageman Road 0.28 Confident Commuter 8 20 7 0 0 0 35 2 $11,900 II Morning Drive Paladino Drive Morningstar Avenue 0.80 Confident Commuter 0 20 15 0 0 0 35 2 $34,100 City of Bakersfield | Bicycle Transportation Plan 7-10 | Alta Planning + Design Class Location Start End Distance (Miles) Study Needed? Family Friendly / Confident Commuter Safety Gap Closure Community Center Connections Employment Connections School Connections Public Input Total Score Tier Cost Estimate II Auburn Street Morning Drive Fairfax Road 0.92 Confident Commuter 0 20 15 0 0 0 35 2 $39,200 III Highway 178 City Limits Masterson Street 6.60 Confident Commuter 0 20 15 0 0 0 35 2 $52,800 II Allen Road Ming Avenue White Lane 1.52 Confident Commuter 0 20 15 0 0 0 35 2 $64,800 II Olive Drive Santa Fe Way Allen Road 1.52 Confident Commuter 0 20 15 0 0 0 35 2 $64,800 I Claymore Extension Eissler Street Piper Way 0.11 Yes Family Friendly 0 20 0 0 15 0 35 2 $70,700 II Paladino Drive Rivani Drive Grand Canyon Drive 1.87 Confident Commuter 0 20 15 0 0 0 35 2 $79,700 II Kern Canyon Road Masterson Street Morning Drive 2.66 Confident Commuter 0 20 15 0 0 0 35 2 $113,300 I North Rosedale Park Path Campfire Drive Jewetta Avenue 0.18 Yes Family Friendly 0 20 15 0 0 0 35 2 $115,700 III Jewette Avenue Bernard Street 30th Street 0.27 Confident Commuter 4 0 15 7 7 0 33 2 $2,200 III Jewetta Avenue Columbus Street Bernard Street 0.52 Family Friendly 4 0 15 7 7 0 33 2 $4,200 III 36th Street Chester Avenue San Dimas Path 0.59 Family Friendly 4 0 15 7 7 0 33 2 $4,700 III La France Drive Castro Lane El Toro Drive 1.03 Family Friendly 4 0 15 7 7 0 33 2 $8,200 III Park/Blanch/11th/10th Route Oak Street Union Ave 1.08 Family Friendly 4 0 15 7 7 0 33 2 $8,600 III Bank Street 2nd Street Ro Oak Street S. P Street 1.59 Family Friendly 4 0 15 7 7 0 33 2 $12,700 II White Lane Union Street Cottonwood Road 0.99 Yes Confident Commuter 6 20 7 0 0 0 33 2 $42,200 II Ming Avenue Oak Street Union Avenue 2.03 Yes Confident Commuter 4 0 15 7 7 0 33 2 $86,500 II McKee Rd Ashe Rd SH 99 2.76 Confident Commuter 2 0 15 0 15 0 32 2 $117,600 III Polo Drive Dapple Avenue Meadow Creek Street 0.26 Confident Commuter 1 0 15 0 15 0 31 2 $2,100 Implementation Alta Planning + Design | 7-11 Class Location Start End Distance (Miles) Study Needed? Family Friendly / Confident Commuter Safety Gap Closure Community Center Connections Employment Connections School Connections Public Input Total Score Tier Cost Estimate III Wilderness Drive Harris Road Reliance Drive 0.54 Confident Commuter 1 0 15 0 0 15 31 2 $4,300 III Garnsey Avenue Garnsey Lane Stockdale Highway 0.57 Confident Commuter 2 0 15 7 7 0 31 2 $4,600 III Height Street River Boulevard 178 Overcrossing 0.75 Family Friendly 1 0 15 0 15 0 31 2 $6,000 III W. Jeffrey Street Overcrossing River Boulevard 1.10 Family Friendly 2 0 15 7 7 0 31 2 $8,800 III Grand Lakes Avenue Rossilyn Lane Brandy Rose Street 1.83 Family Friendly 1 0 0 0 15 15 31 2 $14,600 I Almondale Pk Shared Path Meadow Creek Street Verdugo Lane 0.14 Yes Family Friendly 1 0 15 0 15 0 31 2 $90,000 I San Dimas Path 36th Street Jeffrey Street 0.43 Yes Family Friendly 2 0 15 7 7 0 31 2 $276,400 III China Grade Loop City Limit Panorama Drive 0.11 Confident Commuter 1 0 7 7 15 0 30 2 $900 III Half Moon Drive Ashe Road Ashe Road 0.96 Family Friendly 1 0 0 7 7 15 30 2 $7,700 III Hughes Lane E Pacheco Rd Fairview Road 1.00 Confident Commuter 3 20 7 0 0 0 30 2 $8,000 III Coventry - Benton Route Ming Avenue Oak Street 1.40 Family Friendly 0 0 15 0 15 0 30 2 $11,200 III Noble Avenue Route River Boulevard Columbus Street 2.30 Family Friendly 0 0 15 0 15 0 30 2 $18,400 II Old Farm Road Snow Road Hageman Road 2.00 Confident Commuter 0 0 15 0 15 0 30 2 $85,200 II Buena Vista Road Panama Lane Highway 119 2.00 Confident Commuter 0 0 15 0 15 0 30 2 $85,200 II Mt. Vernon Avenue Panorama Drive Flower Street 2.19 Confident Commuter 1 0 15 7 7 0 30 2 $93,300 II Old River Road Harris Road Taft Highway 2.50 Confident Commuter 1 0 15 7 7 0 30 2 $106,500 I Emerald Cove Park Path Vaquero Avenue Hageman Road 0.23 Yes Family Friendly 0 0 15 0 15 0 30 2 $147,800 I Polo Park Shared Path Old Farm Road Grazing Avenue 0.37 Yes Family Friendly 0 0 15 0 15 0 30 2 $237,800 City of Bakersfield | Bicycle Transportation Plan 7-12 | Alta Planning + Design Class Location Start End Distance (Miles) Study Needed? Family Friendly / Confident Commuter Safety Gap Closure Community Center Connections Employment Connections School Connections Public Input Total Score Tier Cost Estimate II 21st St Oak St Westwind Dr 0.13 Confident Commuter 0 0 15 7 7 0 29 3 $5,500 II Panama Lane Dennen Street Colony Street 0.33 Confident Commuter 2 20 7 0 0 0 29 3 $14,100 III Berkshire Road Colony Street Madison Street 1.81 Family Friendly 0 0 15 7 7 0 29 3 $14,500 III Fairview Road Hughes Lane Cottonwood Road 2.53 Confident Commuter 0 0 15 7 7 0 29 3 $20,200 I 21st St Westwind Dr Kern River Bike Path 0.06 Yes Family Friendly 0 0 15 7 7 0 29 3 $38,600 II Hosking Avenue Wible Rd Gosford Rd 2.99 Confident Commuter 2 20 7 0 0 0 29 3 $127,400 II Verdugo Lane Seventh Standard Road Snow Road 1.00 Confident Commuter 1 20 7 0 0 0 28 3 $42,600 III Edison Road Highway 178 End of Street 1.15 Confident Commuter 0 20 7 0 0 0 27 3 $9,200 II Patton Way Weldon Avenue Hageman Road 0.28 Confident Commuter 0 20 7 0 0 0 27 3 $11,900 III Rudd Avenue Seventh Standard Road Santa Fe Way 1.50 Confident Commuter 0 20 7 0 0 0 27 3 $12,000 III Alfred Harrell Highway Morning Drive Bike Path Highway 178 3.32 Confident Commuter 0 20 7 0 0 0 27 3 $26,600 II Oswell Street Columbus Street City Limits 0.66 Confident Commuter 0 20 7 0 0 0 27 3 $28,100 II Masterson Street Highway 178 Alfred Harrell Highway 1.43 Confident Commuter 0 20 7 0 0 0 27 3 $60,900 I NE Bakersfield Path Paladino Drive Morning Drive Path 2.70 Yes Family Friendly 0 20 7 0 0 0 27 3 $1,735,300 I Columbus Path Kern River Parkway Columbus Street 0.37 Yes Family Friendly 4 0 7 7 7 0 25 3 $237,800 III Real Road Garnsey Lane Palm Street 0.08 Confident Commuter 2 0 7 0 0 15 24 3 $600 III Ridge Road Camino Real Mt. Vernon Avenue 0.16 Family Friendly 3 0 7 7 7 0 24 3 $1,300 Implementation Alta Planning + Design | 7-13 Class Location Start End Distance (Miles) Study Needed? Family Friendly / Confident Commuter Safety Gap Closure Community Center Connections Employment Connections School Connections Public Input Total Score Tier Cost Estimate III Chippewa - Yorkshire Jewetta Avenue Verdugo Lane 0.88 Family Friendly 1 0 7 0 15 0 23 3 $7,000 III Chamber Boulevard S. Allen Road Grand Lakes Avenue 1.45 Family Friendly 1 0 7 0 0 15 23 3 $11,600 III Laurel Park - Wrangler Bay Meadows Lane Calloway Drive 1.83 Family Friendly 1 0 7 0 15 0 23 3 $14,600 III Iron Creek Goose Creek CT Allen Road Coffee Road 3.66 Family Friendly 1 0 7 0 15 0 23 3 $29,300 II Wenatchee Avenue Panorama Drive Columbus Street 1.02 Confident Commuter 1 0 7 0 0 15 23 3 $43,500 II Ashe Road Panama Lane Taft Highway 2.00 Confident Commuter 2 0 7 7 7 0 23 3 $85,200 III Alfred Harrell Highway City Limit Panorama Drive 0.10 Confident Commuter 0 0 7 0 15 0 22 3 $800 III Toluca Drive Route Renfro Road Allen Road 1.48 Family Friendly 0 0 7 0 15 0 22 3 $11,800 II Panama Lane Mountain Vista Road Gosford Road 1.50 Confident Commuter 0 0 7 0 15 0 22 3 $63,900 I Overcrossing Willow Drive Rio Mirada 0.17 Yes Family Friendly 0 0 7 0 0 15 22 3 $109,300 II Allen Road Pensinger Road Highway 119 2.75 Confident Commuter 1 0 7 7 7 0 22 3 $117,200 II Mohawk Street Hageman Road Rosedale Highway 1.26 Confident Commuter 0 0 7 7 7 0 21 3 $53,700 II Panama Lane Interstate 5 Gosford Road 2.02 Confident Commuter 0 0 7 7 7 0 21 3 $86,100 III Camino Grande Alfred Harrell NE Bakersfield Path 1.29 Confident Commuter 0 20 0 0 0 0 20 3 $10,300 I Patton Way Shared Path Weldon Avenue Hageman Road 0.27 Yes Family Friendly 0 20 0 0 0 0 20 3 $173,500 III Appletree - Hahn Route Wilson Road Wible Road 1.80 Family Friendly 4 0 7 0 7 0 18 3 $14,400 III Cottonwood Road Casa Loma Drive E. Panama Lane 3.00 Confident Commuter 3 0 15 0 0 0 18 3 $24,000 City of Bakersfield | Bicycle Transportation Plan 7-14 | Alta Planning + Design Class Location Start End Distance (Miles) Study Needed? Family Friendly / Confident Commuter Safety Gap Closure Community Center Connections Employment Connections School Connections Public Input Total Score Tier Cost Estimate III S. H Street Panama Lane Taft Highway 2.00 Confident Commuter 2 0 15 0 0 0 17 3 $16,000 III Greenwich - Balvanera Verdugo Lane Calloway Road 0.55 Family Friendly 1 0 15 0 0 0 16 3 $4,400 I Arvin-Edison Canal Path Cottonwood Road Fairfax Road 3.77 Yes Family Friendly 1 0 0 0 0 15 16 3 $2,423,100 III Sage Drive Half Moon Bay Drive Wilson Road 0.20 Family Friendly 0 0 0 0 0 15 15 3 $1,600 III Stellar Avenue Old Farm Road Campfire Drive 0.34 Family Friendly 0 0 15 0 0 0 15 3 $2,700 III Westholme Boulevard Ming Avenue Wilson Road 0.40 Confident Commuter 1 0 7 0 7 0 15 3 $3,200 III El Capitan Bike Route Noriega Road Polo Park Path 0.44 Family Friendly 0 0 15 0 0 0 15 3 $3,500 III Allegheny Court Old Walker Pass Road Rivers Edge Park 0.44 Confident Commuter 0 0 15 0 0 0 15 3 $3,500 III Olympia Drive S. Laurel Glen Boulevard Half Moon Bay Drive 0.49 Confident Commuter 0 0 0 0 0 15 15 3 $3,900 III Old Walker Pass Road Comanche Drive Rancheria Road 1.46 Confident Commuter 0 0 15 0 0 0 15 3 $11,700 II Knudsen Drive Olive Drive Hageman Road 0.47 Confident Commuter 0 0 15 0 0 0 15 3 $20,000 II Brimhall Road Renfro Road Allen Road 1.01 Confident Commuter 0 0 15 0 0 0 15 3 $43,000 II Santa Fe Way 7th Stnard Road Hageman Road 4.14 Confident Commuter 0 0 15 0 0 0 15 3 $176,400 I Rail ROW Path 7th Standard Road E. Norris Road 2.23 Yes Family Friendly 0 0 15 0 0 0 15 3 $1,433,300 III Kahala - Constitution Rou Hawaii Lane Jewetta Avenue 1.34 Family Friendly 1 0 7 0 0 0 8 3 $10,700 III Mezzadro/Alderbrk/Lavina Allen Road Allen Road 3.63 Family Friendly 1 0 7 0 0 0 8 3 $29,000 I Panorama Class I Connecti Kern River Parkway Panorama Drive 0.06 Yes Family Friendly 1 0 7 0 0 0 8 3 $38,600 Implementation Alta Planning + Design | 7-15 Class Location Start End Distance (Miles) Study Needed? Family Friendly / Confident Commuter Safety Gap Closure Community Center Connections Employment Connections School Connections Public Input Total Score Tier Cost Estimate II Mountain Ridge Rd Panama Ln Taft Hwy 2.00 Confident Commuter 1 0 7 0 0 0 8 3 $85,200 II Reina Road Renfro Road Verdugo Lane 2.04 Confident Commuter 1 0 7 0 0 0 8 3 $86,900 I Calloway Shared Path Balvanera Drive Noriega Road 0.28 Yes Family Friendly 1 0 7 0 0 0 8 3 $180,000 III Yarnell Bike Route Paul Avenue Calloway Drive 0.31 Family Friendly 0 0 7 0 0 0 7 3 $2,500 III Hawaii - Wailea Allen Road Noriega Road 0.38 Family Friendly 0 0 7 0 0 0 7 3 $3,000 II Allen Road Snow Road Hageman Road 1.89 Confident Commuter 0 0 7 0 0 0 7 3 $80,500 III Mountain Park Dr Kern River Parkway River Run Boulevard 0.18 Confident Commuter 1 0 0 0 0 0 1 3 $1,400 III Rose Petal Street Brandy Rose Street Ridge Oak Drive 0.20 Confident Commuter 1 0 0 0 0 0 1 3 $1,600 III River Run Boulevard Ming Avenue Buena Vista Road 0.93 Confident Commuter 1 0 0 0 0 0 1 3 $7,400 I Truxtun Shared Path link Coffee Road Quailridge Road 0.15 Yes Family Friendly 1 0 0 0 0 0 1 3 $96,400 II Panama Lane Interstate 5 Gosford Road 2.02 Confident Commuter 0 0 0 0 0 0 0 3 $86,100 City of Bakersfield | Bicycle Transportation Plan 7-16 | Alta Planning + Design 7.2. Bikeway Cost by Class and Tier Table 7-5 presents a summary of bikeway miles and cost estimates by bikeway class. The total estimate for all the bikeway projects in this Plan is $34.2 million. A significant amount of this cost estimate is due to the cost of the Class I bike paths. The cost estimate for the recommended Class II and Class III projects is approximately $5.6 million. Table 7-5: Summary of Costs by Class and Miles Facility Type Cost Estimate Miles I $28,633,300 44.55 II $4,732,200 111.07 III $831,900 104.03 Total $34,217,400 259.65 Table 7-6 presents a summary of bikeway projects by implementation tier. Tier 1, intended for implementation within the next five years, is estimated to cost $17.1 million. This includes the Arvin-Edison Canal, H Street Canal, and the Friant-Kern Canal paths which will require a feasibility study and will take considerable time to study and implement. The cost to implement the Tier 1 projects without the paths is approximately $2 million. Table 7-6: Summary of Costs by Tier and Miles Tier Cost Estimate Miles 1 $17,152,400 80.45 2 $8,946,600 98.87 3 $8,098,400 80.33 Total $34,217,400 259.65 Table 7-5 at the end of this chapter outlines the high priority projects that include the Tier 1 bikeway infrastructure projects and priority programs. Implementation Alta Planning + Design |7-17 7.3. Maintenance Cost Estimates Bikeways require regular maintenance and repair. On-street bikeways are maintained as part of the normal roadway maintenance program and extra emphasis should be placed on keeping bike lanes and roadway shoulders clear of debris and keeping vegetation overgrowth from blocking visibility. The high cost of maintaining Class I facilities may be shared among various agencies or departments. The typical maintenance costs for the existing and proposed bikeway network are shown in Table 7-4. Table 7-4: Bikeway Maintenance Cost Estimates (Existing and Proposed) Facility Type Unit Cost Description Length (Miles) Annual Cost Notes Class I $8,500 Miles/Year 72.45 $615,800 Lighting and removal of debris and vegetation overgrowth Class II $2,000 Miles/Year 225.45 $450,900 Repainting lane stripes and stencils, sign replacement as needed Class III $1,000 Miles/Year 104.76 $104,800 Sign replacement as needed Annual Cost $1,171,500 City of Bakersfield | Bicycle Transportation Plan 7-18 | Alta Planning + Design 7.4. High Priority Projects and Programs The high priority projects are comprised of the following:  Tier 1 bikeway infrastructure projects;  Spot improvement studies; and  Selected programs including a bike parking plan; Safe Routes to School Plan, and a citywide youth bicycle saftey education program. Table 7-5 below presents the high priority projects and cost estimates. This list may change to reflect the City’s most current priorities, needs, and opportunities for implementing the bicycle network in a logical and efficient manner. A number of projects will require a feasibility study before implementation and those study costs have been included rather than implementation costs. The cost estimates for all projects are high level and detailed scoping should be completed before implementation. The total cost estimate for the high priority projects is approximately $3.3 million. Table 7-5: High Priority Projects Class Project/Location Start End Distance (Miles) Family Friendly / Confident Commuter Cost Estimate II Baker Street Bernard Street California Avenue 1.57 Confident Commuter $66,900 II Potomac Avenue S. King Street Monticello Avenue 0.82 Confident Commuter $34,900 I River Bike Trail Connection Kern River Parkway Elm Street 0.26 Family Friendly $167,100 III Baker Street California Avenue S. King Street 0.35 Confident Commuter $2,800 III E. Pacheco Road Hughes Lane Cottonwood Road 2.52 Family Friendly $20,200 II Belle Terrace Stine Road Madison Street 3.04 Confident Commuter $129,500 III Pin Oak Boulevard Bear Creek Road District Boulevard 1.14 Family Friendly $9,100 III Ewoldsen Class III Route Oak Grove Street N. Half Moon Drive 1.43 Family Friendly $11,400 III Harris Road Ashe Road Akers Road 1.51 Family Friendly $12,100 II Harris Road Ashe Road Wible Road 0.50 Family Friendly $21,300 II Hughes Lane Ming Ave E. Pacheco Road 1.50 Confident Commuter $63,900 II Harris Road S. Allen Road Ashe Road 4.08 Family Friendly $173,800 II Haley Street Panorama Drive Columbus Street 0.87 Confident Commuter $37,100 II E. Pacheco Road Gasoline Alley Monitor Street 1.33 Family Friendly $56,700 II Akers Road Wilson Rd Taft Hwy 4.47 Confident Commuter $190,400 I Arvin-Edison Canal Path Stockdale Highway Cottonwood Road 9.54 Family Friendly Study III 17th Street A Street Truxtun Avenue 1.26 Confident Commuter $10,100 II M Street 30th Street 17th Street 0.85 Confident Commuter $36,200 II Sillect Avenue Buck Owens Boulevard Kern River Parkway 1.33 Confident Commuter $56,700 I H Street Canal Path Railroad Bridge Highway 99 7.97 Family Friendly Study I Friant-Kern Canal Seventh Standard Road Kern River 6.10 Family Friendly Study Implementation Alta Planning + Design |7-19 Class Project/Location Start End Distance (Miles) Family Friendly / Confident Commuter Cost Estimate II Beale Avenue Grace Street 21st Street 1.00 Confident Commuter $42,600 II Q Street Columbus Street Highway 178 1.12 Confident Commuter $47,700 III Haggin Oaks Blvd Camino Media Limoges Way 0.74 Family Friendly $5,900 II Kentucky Street Alta Vista Drive Mt. Vernon Avenue 1.81 Confident Commuter $77,100 III Flower Street Alta Vista Drive Owens Street 0.64 Confident Commuter $5,100 III S, King Street California Avenue Brundage Lane 1.00 Confident Commuter $8,000 III 4th Street Union Avenue City Limits 1.25 Confident Commuter $10,000 III Watts Drive Cottonwood Road Madison Street 0.50 Confident Commuter $4,000 III Brundage Lane Union Avenue Oswell Street 5.08 Confident Commuter $40,600 II Niles Street Alta Vista Drive Virginia Street 1.28 Confident Commuter $54,500 II Bernard Street Chester Avenue Mt. Vernon Avenue 2.95 Confident Commuter $125,700 III Berkshire Road Stine Road Santana Sun Drive 1.50 Family Friendly $12,000 II 21st Street King Street Washington Street 0.89 Confident Commuter $37,900 I 178 Overcrossing Height Street Mirador Drive 0.10 Family Friendly Study III Laurelglen Boulevard Pin Oak Park Boulevard Gosford Road 0.48 Confident Commuter $3,800 III Mountain Oak - McInnes Rt Park Path McInnes - Westwold Path 0.59 Family Friendly $4,700 III 22nd Street Elm Street F Street 0.72 Confident Commuter $5,800 III Christmas Tree Lane Mt Vernon Avenue Panorama Drive 1.65 Confident Commuter $13,200 II Madison Street Belle Terrace White Ln 1.00 Confident Commuter $42,600 I Park Path Mountain Oak Road Broad Oak Avenue 0.19 Family Friendly $122,100 II Wible Road Planz Road Taft Highway 4.00 Confident Commuter $170,400 Arvin-Edison Canal Path Feasibility Study $200,000 H Street Canal Path Feasibility Study $200,000 Friant-Kern Canal Feasibility Study $200,000 178 Overcrossing Feasibility Study $100,000 River Bike Trail Connection Feasibility Study $75,000 Spot Improvement Studies $100,000 Bike Parking Plan $75,000 Safe Routes to School Plan $350,000 Youth Bicycle Safety Education Program $50,000 Total $3,283,900 City of Bakersfield | Bicycle Transportation Plan 7-20 | Alta Planning + Design This page intentionally left blank.