HomeMy WebLinkAboutTract 6921Thanks Blaine.
It would be greatly appreciated.
Don
From: Blaine Neptune [mailto:BNeptune@mcintoshassoc.com]
Sent: Tuesday, January 28, 2014 3:16 PM
To: Don Richardson
Cc: Jim Holladay; Manpreet Behl; Roger McIntosh; Matt Wade
(mwade@landstonecompanies.com); Mark Windes
(mwindes@landstonecompanies.com); Ryan Joyce
(rjoyce@landstonecompanies.com); Larry Burns (LarryBurns@krazan.com)
Subject: RE: Tract 6921
Thank you for the quick reply,
I am sure the contractor will be able to clear the weeds, Matt please
confirm.
Thanks,
Blaine Neptune, RCE
McIntosh & Associates
2001 Wheelan Ct.
Bakersfield, CA 93309
661-834-4814
bneptune@mcintoshassoc.com
From: Don Richardson [mailto:drichard@bakersfieldcity.us]
Sent: Tuesday, January 28, 2014 3:09 PM
To: Blaine Neptune
Cc: Jim Holladay; Manpreet Behl; Roger McIntosh; Matt Wade
(mwade@landstonecompanies.com); Mark Windes
(mwindes@landstonecompanies.com); Ryan Joyce
(rjoyce@landstonecompanies.com); Larry Burns (LarryBurns@krazan.com)
Subject: RE: Tract 6921
I have no issue with lowering this basin. I would ask that the road pad
around the perimeter be cleaned of weeds, during the lowering process.
Thanks
Don Richardson
Superintendent
Water Resources Department
City Of Bakersfield
661-326-3715
From: Blaine Neptune [mailto:BNeptune@mcintoshassoc.com]
Sent: Tuesday, January 28, 2014 2:54 PM
To: Don Richardson
Cc: Jim Holladay; Manpreet Behl; Roger McIntosh; Matt Wade
(mwade@landstonecompanies.com); Mark Windes
(mwindes@landstonecompanies.com); Ryan Joyce
(rjoyce@landstonecompanies.com); Larry Burns (LarryBurns@krazan.com)
Subject: Tract 6921
Don,
The apartment site for Tract 6921 is currently being graded and is
running a little short on dirt. I had a conversation with Jim Holiday
on Friday to see if he was o.k. with borrowing from the sump. He had no
issue with it as but stipulated if the design water depth exceeded 10’
we would need a slope stability analysis. The current design depth of
the sump is 8’ so it can lower it 2’ without a slope stability analysis.
The attached sketch shows what we would like to do.
The ramp would be extended at the 15% and a 30’ bench would be left
around the existing outlet structure (similar to how we lowered the sump
for tract 7222). The result would be an additional 1 AC-FT. of
storage. Please confirm this is acceptable and if so can you have the
gate unlocked on Thursday so the grading contractor can access the sump.
Thanks.
Blaine Neptune, RCE
McIntosh & Associates
2001 Wheelan Ct.
Bakersfield, CA 93309
661-834-4814
bneptune@mcintoshassoc.com