HomeMy WebLinkAbout06/06/2014
OFFICE OF THE CITY MANAGER
June 6, 2014 TO: Honorable Mayor and City Council
FROM: Alan Tandy, City Manager AT/cb
Subject: General Information
Notable Items:
Attached you will find the monthly TRIP Status Report for the month of June. The report
gives a summary of each TRIP project in construction, in design, and under review.
Completion percentages and pictures of projects are also included. This is the third
edition of an important new report. You are encouraged to review it carefully.
Soundwalls are proposed as part of the Centennial Corridor Project to minimize noise
impacts and would be constructed within Caltrans’ right-of-way. As part of its
Centennial Corridor project, Caltrans has initiated its soundwall voting procedures
along Alternative B (preferred alternative). Soundwall voting is a required process and
allows affected property owners/residents (tenants) to provide input. If more than 50%
of the responding property owners and/or residents oppose the proposed soundwall, it
will not be constructed. Soundwall voting materials were mailed on May 30th to 305
affected property owners/residents along alternative B. The voting period began on
May 30th and will end on June 30th. A soundwall voting meeting is proposed at Munsey
Elementary School on June 25th from 4:00 p.m. to 7:00 p.m. Caltrans and its consultants
will be available to answer questions affected property owners/residents may have.
Attached is the Centennial Corridor Soundwall Survey. Good News:
The Mohawk Street North Ribbon Cutting Ceremony was Tuesday, June 3rd. The project
is a vital link to Bakersfield’s transportation network and consists of approximately .75
miles of new roadway from Rosedale Highway to Siena Lane, which collectively will
produce vehicular access on Mohawk Street from Rosedale Highway to Hageman
Road. Benefits of this roadway include reduced vehicle miles traveled, reduced
congestion, as well as air quality and transportation connectivity improvements.
Total project construction costs were $3.1 million. Funding for the project consisted of a
$1.4 million contribution from World Oil, $1 million from the California Transportation
Commission, and $1 million from Proposition 1B State-Local Partnership Program Funds.
The City of Bakersfield funded the balance. Thank you to all of those who played a
role and contributed to this important project! Attached are photos of the event.
General Information
June 6, 2014 Page 2
Rebounding from last week’s legal setback, the City received positive news yesterday
in its CEQA lawsuit against Kern Delta. As background, Kern Delta tried to increase
water diversions in 2006 without preparing an EIR. The City prevailed in its lawsuit
against Kern Delta, and the court issued an injunction prohibiting Kern Delta from
increasing water diversions until they complied with CEQA.
The decision from the trial court yesterday found that Kern Delta still had not complied
with CEQA in connection with its recent EIR and that the EIR failed to review the lost
recharge and groundwater levels within the City, and specifically, the impact on the City’s plans to run water down the Kern River channel. The court also ordered that the
injunction remain in place. In light of the drought, and for other reasons, this is very
good news indeed!
The Greater Bakersfield Chamber of Commerce recently honored Keep Bakersfield
Beautiful (KBB) and a special KBB volunteer! The annual Beautiful Bakersfield Awards
Banquet celebrates individuals, organizations, and businesses for positive contributions
to the community. KBB won the Public/Private Partnership category for spearheading
the Freeway Litter Cleanup Program. KBB volunteer Tom Burch won the Active Adults
category and the Chairman’s Award for cleaning up litter with KBB and Mayor Hall. For
the third year in a row, it was a proud evening for KBB and the Public Works
Department. Attached is a memo.
Saturday, June 7th, from 9 a.m. to 12:00 p.m. the Bakersfield Municipal Airport will be
having its annual fly-in and Open House Event. The event is hosted by the local
Experimental Aircraft Association, Chapter 71, and will feature experimental aircraft
displays, helicopter displays, and sailplanes. There will be food and drinks available at
the Rocket Shop Café as well as other fun activities for children. The club will offer free
introductory flights to children, ages 8-17 as part of their Young Eagles program for
those who arrive early.
Budget News
The following referrals are in response to budget-related requests and questions
posed to staff since the May 21st, 2014 City Council Meeting.
• Councilmember Sullivan
o Tasers for Code Enforcement Officers TRIP Advisories:
State Route 58 Gap Project Closures
The contractor for the State Route 58 Gap Closure project will be working at the pump
station near the Chester Avenue/H Street westbound on-ramp during daytime hours
on Wednesday through Friday, June 11th-13th. This work will require the closure of the
General Information
June 6, 2014 Page 3
adjacent ramp between the hours of 6:30 a.m. and 4:00 p.m. each day. The daytime
ramp closure may continue into next week, June 16th-18th, if necessary.
During the closures, motorists will need to use the State Route 58/Union Avenue
Interchange, located approximately one mile to the east, or continue west on
Brundage Lane for approximately one mile to access northbound or southbound State
Route 99.
Additionally, motorists should anticipate full nighttime closures of P Street, at State Route 58, on Wednesday and Thursday, June 11th-12th, and Sunday through Tuesday,
June 15th-17th. The contractor will be erecting falsework for the P Street Bridge
widening, which will require the closure of the street between the hours of 8:30 p.m.
and 6:00 a.m., each night. During these hours, motorists can use Chester Avenue or
Union Avenue for north/south access across the freeway.
Intermittent Traffic Control Continues on State Route 178
Intermittent traffic control will continue for the next week along State Route 178, in the
vicinity of the Fairfax Interchange to Canteria Drive.
The contractor for the State Route 178/Morning Drive Interchange project will be
hauling materials onto the job site, and crews will be conducting traffic control as
needed with the use of flagging personnel, Monday through Friday, June 9th through
the 13th. These operations will be conducted between the hours of 6 a.m. and 4 p.m.,
each day.
Council Referrals:
Attached are responses to the following Council referrals:
• Councilmember Johnson
o GET Bus Service on East Truxtun
• Councilmember Maxwell
o 24th Street Design and Landscaping Update
o Westside Parkway Landscaping
• Councilmember Smith
o Weeds Along the Westside Parkway
Reports:
For your convenience, the following reports are attached:
• Streets Division work schedule for the week of June 9th ; and
• Letter from Bright House Networks regarding possible programming changes.
General Information
June 6, 2014 Page 4
Event Notifications:
o The first Movie in the Park, The Croods, will be today, Friday, June 6th at the Park at
River Walk. Sponsored by Bright House Networks, the Friday night movies start at dusk.
The first movie will feature local entertainment of a steel drum band starting at 6:30
p.m. Families are permitted to bring blankets and a picnic dinner. Alcohol is not
permitted. The movie is free and refreshments will be available for purchase.
o Yesterday kicked off the first of six weekend sessions of the Jehovah’s Witness
Watchtower Convention at Rabobank Arena. This is the largest group that meets in
Bakersfield. Each weekend meeting attracts about 6,000 delegates, filling up local
hotel rooms and restaurants during the summer. The dates of the remaining events are
June 13th-15th, June 20th-22nd, July 4th-6th, July 25th-27th, and August 1st-3rd.
o Rabobank Theater
Friday, June 6th at 8:00 p.m. Ron White
Saturday, June 7th at 8:00 p.m. Art Laboe’s Super Freestyle Explosion
Saturday, June 14th at 8:00 p.m. Intocable
o Attached is the Event Calendar for Rabobank Arena Theater and Convention Center.
AT:rs:al:cb cc: Department Heads Roberta Gafford, City Clerk
Page 1
TRIP projects are moving rapidly through the various stages of project development.
This report is to provide a periodic up-to-date snapshot of each project’s recent major
activities and progress. If you have questions, or need additional information, please
contact Janet Wheeler at the TRIP office, (661) 326-3491.
MILESTONES
The Hageman Flyover Project took a major leap forward in May with the signing of the Final Environmental
Document. The environment review process has been completed, and the project will now move forward into
the design/right-of-way phases of development.
The spotlight this month is on Centennial Corridor, the last TRIP project to remain under environmental
review. The project marked a significant milestone on June 4th when the Bakersfield City Council approved the
purchase of the first property under the project’s early acquisition program. The Centennial Corridor draft
environmental document was circulated for public review and comment in May, and Caltrans will hold a public
hearing/open house at the Kern County Administrative Center, 1115 Truxtun Avenue on June 11th, from 4 to 7
p.m. (Caltrans will accept public comments through July 8th.) Caltrans will also host an open house for property
owners eligible to receive soundwalls with the project on June 25th, from 4 to 7 p.m., at Munsey Elementary
School, 3801 Brave Avenue (near South Real Road/Belle Terrace).
PROJECTS UNDER CONSTRUCTION
Three projects are currently under construction. Please see page 4 for new construction photos.
Westside Parkway 6C
Contractor: Security Paving Company
45% complete; anticipated completion: late 2014
The contractor will complete final excavation work at Renfro Road in June, allowing for construction of the
west half of the bridge and the final storm drain connection. Bridge abutments and columns are expected to
be completed in late June/early July. The contractor also plans to lay asphalt for the freeway’s western
connection to Stockdale Highway this month. Base paving for the freeway lanes is expected to begin later this
summer. The contractor is finishing the retaining wall for the eastbound off-ramp at Allen Road and
soundwalls are expected to be completed by the end of the month.
State Route 58 Gap Closure
Contractor: Security Paving Company
25% complete; anticipated completion: late 2014
The contractor is working simultaneously on the four bridges that must be widened to accommodate the
new traffic lanes. Planned activities for June include placing concrete for the stems, soffit, and deck, at
Cottonwood Road; pouring columns at the Bakersfield Corral Overhead; erecting falsework at Madison Street;
and erecting falsework and placing concrete for the stems and soffit at P Street. Widening the bridges allows
the new lanes to be built along a continuous construction corridor (separated from traffic by temporary
concrete barriers), reducing the need for trucks and equipment to enter and exit the construction area from
the existing freeway “fast” lanes.
June 2014
TRIP Status Report
TRIP Status Report
June 2014
Page 2
State Route 178/Morning Drive Interchange
Contractor: Granite Construction
35% complete; anticipated completion: late 2015
State Route 178 traffic continues to flow smoothly around the construction area. With traffic off the
mainline, work on the future Morning Drive bridge has accelerated. The abutments and columns are complete
and the contractor is preparing the base to build the bridge across State Route 178. Elsewhere on the project,
the contractor is grading for the future westbound lanes. The contractor is removing asphalt from the old
roadway, which will be recycled into the asphalt mix for the future freeway lanes. The existing road base
materials will also be recycled back into the project. Construction on the sound wall adjacent to the Canyon
Hills Church Residential Units is underway. As a reminder the speed limit on the bypass is 40 mph.
PROJECTS IN DESIGN AND RIGHT-OF-WAY
Four projects (totaling $150 million) will move out of design/right-of-way into construction this year, creating
new construction jobs and benefits for the local economy. The City received qualification responses from
seven construction management firms and 16 contractors, including three international firms. City staff is in
the process of short-listing and interviewing firms. Current project tasks and status are outlined below.
State Route 99/Hosking Avenue Interchange
Designer: Parsons and IBI
Design 98% complete; Right-of-Way 100% complete; anticipate bidding: Summer 2014
Completion of Plans: June 2014
Parsons has submitted final plans to Caltrans and approval of the plans is anticipated in late June
Beltway Operational Improvements
Designer: Parsons
Design 98% complete; Right-of-Way 90% complete; anticipate bidding: Fall 2014
Completion of Plans: late June 2014
Caltrans provided comments for 100% plans; Parsons will resubmit 100% plans to Caltrans on June 9th
Ongoing work by the consultant:
• Value Engineering-recommendations for pavement replacement strategy, cut-and-cover tunnel,
and retaining/screen wall are not currently incorporated into the design, but coordination with
Caltrans for approvals to move forward with separate packages is ongoing
• Preparing Request for Authorization submittal to Caltrans for construction funding obligation
• Railroad coordination for Construction and Maintenance Agreement
• Utility relocation coordination
Anticipated Right-of-Way completion: Summer 2014
• 41 Privately-owned parcels (3 Permanent Easements; 38 Temporary Construction Easements (TCE)
- Offers have been made on all TCE-only parcels; 37 parcels have signed
- Encroachment Permits for construction are being pursued from various public agency owners
Rosedale Highway
Designer: Mark Thomas Company (MTC)
Design 98% complete; Right-of-Way 90% complete; anticipate bidding: Fall 2014
Completion of Plans: June 2014
Final plans will be submitted to Caltrans June 11th
Negotiating construction and maintenance agreement with Railroad Company
Anticipated Right-of-Way completion: Summer 2014, dependent upon court hearing dates
• 99 Ownerships (105 parcels - Temporary Construction Easements and Permanent)
- 91 have signed; 81 ownerships have closed/been recorded; 10 escrows processing
- 8 Resolutions of Necessity (RON) actions filed
TRIP Status Report
June 2014
Page 3
State Route 178 Widening
Designer: TYLin International
Design 98% complete; Right-of-Way 10% complete; anticipate bidding: late 2014
Completion of Plans: late June 2014
• Construction Cooperative Agreement approved by City Council June 4th
- 100% plans submitted to Caltrans; final plans and specifications anticipated August 1st
Anticipated Right-of-Way completion: Fall 2014
• 40 Ownerships
- All appraisals are complete; all offers have been presented
- 3 ownerships acquired; 3 escrows open
- 16 ownerships scheduled for RON hearings on July 16th City Council meeting
24th Street Improvement Project
Designer: TYLin International (TYL)
Design 2% complete; Right-of-Way 3% complete; anticipate bidding: 2015
Survey work has begun
First Project Development Team meeting will be held in June
Property acquisitions are underway
• 23 residential properties; approx. 40 partial acquisitions and Temporary Construction Easements
- 6 appraisals are complete; 13 appraisals are in process
- 2 offers have been accepted (including one completed hardship case)
- 4 offers will be presented in June
Hageman Flyover
Design: Caltrans
Design 0% complete; Right-of-Way 0% complete
The Final Environmental Document was signed on May 19, 2014
PROJECTS UNDER ENVIRONMENTAL REVIEW
Centennial Corridor
Caltrans lead; Environmental Consultant: Parsons
75% to final environmental document completion
The draft project report and draft environmental document have been completed.
• Caltrans’ public hearing/open house is scheduled for June 11th
• An open house for property owners eligible for project soundwalls is scheduled for June 25th
• The public circulation/comment period extends through July 8, 2014
• All public comments must be made directly to Caltrans
- Mail: Jennifer H. Taylor, Office Chief
California Department of Transportation
855 M Street, Suite 200
Fresno, CA 93721
- Email: Centennial@dot.ca.gov
Advanced Preliminary Engineering for the project continues
Right-of-Way (Early Acquisition/Voluntary Basis Only as approved by City Council on March 5, 2014)
• Full Acquisitions required for the project: 199 single family residences & 36 commercial properties
- 92 ownerships have requested early acquisition
- Appraisals are underway; 13 offer packages have been prepared
- First property acquisition approved by City Council on June 4th
TRIP Status Report
June 2014
Page 4
PROJECT PHOTOS
Above left: Work continues on the east half of the Renfro Road Bridge across the Westside Parkway.
Excavation on the west side will be completed in June, allowing the contractor to build the remainder of the
bridge. Above right: On the State Route 58 Gap Closure project, the contract has erected falsework at the
Cottonwood Road Bridge in preparation of placing concrete for stems and soffit, as well as the bridge deck
in June. Below left: State Route 178 traffic flows smoothly around the construction area. In the background,
mounds of base rock rise from the landscape as the contractor mines and separates existing materials from
the construction site to recycle back into the project. Below right: The Morning Drive Bridge abutments
and columns have been completed.
Mohawk Ribbon Cutting
PUBLIC WORKS DEPARTMENT
MEMORANDUM
TO: Alan Tandy, City Manager
FROM: Nick Fidler, Public Works Director
DATE: 06/06/14
SUBJECT: Greater Bakersfield Chamber of Commerce Awards
The Greater Bakersfield Chamber of Commerce recently honored Keep Bakersfield
Beautiful (KBB) and a special KBB volunteer! The annual Beautiful Bakersfield Awards
Banquet celebrates individuals, organizations, and businesses for positive contributions
to the community. KBB won the Public/Private Partnership category for spearheading
the Freeway Litter Cleanup Program. KBB volunteer Tom Burch won the Active Adults
category and the Chairman’s Award for cleaning up litter with KBB and Mayor Hall. For
the third year in a row, it was a proud evening for KBB and the Public Works
Department.
# # #
G:\GROUPDAT\Referrals\2014\05-21\#493 GET Services.docx
CITY OF BAKERSFIELD
PUBLIC WORKS DEPARTMENT
MEMORANDUM
TO: Alan Tandy, City Manager
FROM: Nick Fidler, Public Works Director
DATE: June 3, 2014
SUBJECT: GET Bus Service on East Truxtun
Referral No. 493
Staff has made contact with Louis Gill, CEO, Bakersfield Homeless Center. However,
due to scheduling conflicts staff was unable to arrange an appointment until this week
to meet with Karen King, CEO, GET Bus, and Mr. Gill, CEO, to discuss improved service
along the East Truxtun corridor.
Councilmember Johnson requested that staff meet with Mr. Gill at the
Bakersfield Homeless Center and GET officials to determine what can be
done to improve GET service along the East Truxtun corridor.
G:\GROUPDAT\Referrals\2014\05-07\#480 24th Street Update.docx
CITY OF BAKERSFIELD
PUBLIC WORKS DEPARTMENT
MEMORANDUM
TO: Alan Tandy, City Manager
FROM: Nick Fidler, Public Works Director
DATE: June 3, 2014
SUBJECT: 24th Street Design and Landscaping Update
Referral No. 480
A Design Consultant agreement with TY Lin for the 24th Street widening project from
State Route 99 to M Street was awarded at the May 7, 2014 Council meeting. TY Lin has
been issued a notice to proceed with Final Design of the project. The first order of work
will be to survey the existing conditions of the roadway so that the final design layout
can be determined. It will take several months for TY Lin to complete their survey work
and prepare the initial base plans that would then be used to begin the preparation of
the landscape plans for the 24th Street project. Once the layout is complete, staff
anticipates holding workshops with the community to get their input on the landscape
designs. Staff recommends providing an update to the Council later this summer when
this initial design work is completed and the areas to be landscaped have been
determined.
It is the intention of the City that the actual landscape design will be done by Roland
Gennick of Parsons. Roland presented the concept designs to the Council, and has
also met with the 24th Street area residents regarding the landscape concepts. For
coordination purposes, this work will likely be completed as a subcontract to TY Lin’s
agreement.
Councilmember Maxwell requested that Council be given an update of
the design and landscaping of 24th Street.
G:\GROUPDAT\Referrals\2014\05-07\#481 WSP Landscaping Funds.docx
CITY OF BAKERSFIELD
PUBLIC WORKS DEPARTMENT
MEMORANDUM
TO: Alan Tandy, City Manager
FROM: Nick Fidler, Public Works Director
DATE: June 3, 2014
SUBJECT: Westside Parkway Landscaping
Referral No. 481
Funds for the construction of the Westside Parkway predominantly come from the State
Transportation Improvement Program (STIP). The STIP is a statewide transportation funding
program that is administered locally by the Kern Council of Governments (KernCOG) and
which is ultimately approved by the California Transportation Commission (CTC). But
because of the scarcity of transportation funds in the state STIP program, the need for
roadway improvements to the transportation network within the county, and the
competitiveness of the various local transportation projects submitted for STIP funding from
within the county, landscaping of the Westside Parkway has never been able to be
programmed as a project in the STIP. Efforts to obtain the funds will continue over time.
Staff continues to pursue opportunities for grants or other programs when they become
available to provide some landscape improvements for the Westside Parkway. However,
it should also be noted that the Westside Parkway will ultimately become State Route 58,
and will then be owned and maintained by the State. Based on the drought and recent
Caltrans policies regarding landscaping and irrigation for their facilities, the landscaping
design completed several years ago is at a higher level of improvement than Caltrans
would currently accept to maintain. As a result, Caltrans will require significant redesign of
the landscape and irrigation system before they would agree to accept any landscaping
along the Westside Parkway which will be the new SR 58 alignment.
Councilmember Maxwell would like to know what happened to the funds
for landscaping Westside Parkway.
G:\GROUPDAT\Referrals\2014\05-21\#494 WSP Weeds.docx
CITY OF BAKERSFIELD
PUBLIC WORKS DEPARTMENT
MEMORANDUM
TO: Alan Tandy, City Manager
FROM: Nick Fidler, Public Works Director
DATE: June 3, 2014
SUBJECT: Weeds Along the Westside Parkway
Referral No. 494
Bakersfield Homeless Center (BHC) crews currently pick up litter along the Westside
Parkway. BHC has agreed to have their crews also pick-up tumbleweeds along the
Parkway. We appreciate BHC for their continued cooperation with the City.
In addition, Parks staff will spray herbicides on embankment areas covered with bark to
alleviate weed and tumbleweed growth. However, for those areas which are seeded
with native grasses, herbicide application cannot be used. BHC has agreed to have
their crews remove tumbleweeds growing on areas covered with native grasses by
hand. Parks staff is currently on a monthly spray schedule to catch up with current
weed growth. Once weed growth is controlled, Parks staff will perform semiannual
treatments with a pre-emergent. Pre-emergent will prevent germination of most of the
weeds; however, spot treatments will still be necessary.
Councilmember Smith requested that staff address the growth of
tumbleweeds along the Westside Parkway.
Week of June 9_2014_Work Schedule
Page 1 of 2
STREETS DIVISION – WORK SCHEDULE
Week of June 9, 2014 – June 13, 2014
Resurfacing/Reconstructing streets in the following areas:
Reconstructing various streets north of White Ln and west of Gosford Sealing streets in the area south of Stockdale Hwy and west of Allen Rd
Resurfacing streets in the area south of White Ln and west of Old River Rd
Preparing streets in the area west of Union Ave and south of Panama Ln for resurfacing
Miscellaneous Streets Division projects:
Video inspection of City owned Sewer & Storm lines to evaluate condition of pipes Repairing damaged sewer line found during video inspection
Miscellaneous concrete repairs throughout the city
Concrete work on various streets in the area north of E. California Ave and west of Williams in preparation for street reconstruction / resurfacing (HUD funded area)
Preparing site at Panorama & Columbus for temporary Fire Station 8
Concrete work on various streets in the area south of E. California Ave and east of Union Ave (HUD funded area)
THIS SPACE INTENTIONALLY LEFT BLANK
Week of June 9_2014_Work Schedule
Page 2 of 2 STREETS SWEEPING SCHEDULE
Monday, June 9, 2014
Between So. “H” St. & Union Avenue – Pacheco Rd. & Hosking Rd.
Between Stockdale Hwy. & Truxtun Ave. (ext.) – Coffee Rd & Partridge Ave.
Tuesday, June 10, 2014
Between 99 Hwy. & So. “H” St. – Ming Ave. & Panama Ln.
Cul-De-Sacs on the north side of Magdelena Ave., west of So. “H” St.
Wednesday, June 11, 2014
City areas between Brundage Ln. & Ming Ave. – So. “H” St. & Union Ave.
City areas between Wilson Rd. & Pacheco Rd. – So. “H” St. & Union Ave.
Between Casa Loma Dr. & Planz Rd. – Madison Ave. & Cottonwood Dr.
Between Planz Rd. & Brook St. – Madison Ave. & Hale St. Thursday, June 12, 2014
Between Carr St. & California Ave. – Mohawk St. & Stockdale Hwy.
Between Stockdale Hwy. & Marella Wy. – California Ave. & Montclair St. Between La Mirada Dr. & Chester Ln. – Montclair St. & No. Stine Rd.
Between California Ave. (ext.) & Stockdale Hwy. – No. Stine Rd. & 99 Hwy.
Between Stockdale Hwy. & Ming Ave. – New Stine Rd. & Ashe Rd.
Between Mountain Ridge Dr. & Ashe Rd. – Taft Hwy. & Berkshire Rd.
Friday, June 13, 2014 Between Ming Ave. & White Ln. – Buena Vista Rd & Old River Rd.
Between Stine Rd. & 99 Hwy. – Ming Avenue & Adidas.
Between Panama Ln. & Birkshire Rd. – Gosford Rd. & Stine Rd.
NOTE: If raining, there will be no street sweeping service and all street cleaning personnel will be assigned to cleaning plugged drains and part circle culverts. This also applies when a large number of street sweeper are in Fleet for repairs. Areas that have been missed during this time will be swept at the
end of the month.
BOX OFFICE HOURS
Mon-Fri 10 AM - 5 PM
Closed Saturday & Sunday
(Excluding Event Days)
TICKETMASTER LOCATIONS
Walmart - 2601 Fashion Place
Walmart - 6225 Colony Street
Walmart - 8400 Rosedale Hwy
CHARGE-BY-PHONE
1-800-745-3000
GROUP SALES INFORMATION
661-852-7309
SEASON TICKET INFORMATION
Bakersfield Condors
661-324-PUCK (7825)
www.bakersfieldcondors.com
Bakersfield Symphony
661-323-7928
www.BSOnow.org
Bakersfield Community
Concert Association
661-589-2478
661-663-9006
www.bakersfieldcca.org
UPCOMING EVENTS
July 23 – Goo Goo Dolls & Daughtry7:30 PM
$59.50 & $44.50 On Sale Now
April 30-May 3, 2015 – Marvel Universe Live!
$150, $100, $50, $40 On Sale Now
June 3-4 – Sesame Street Live
$50.00, $32.00, $24.00, $17.00 On Sale Now
June 6 – Ron White 8:00 PM
$53.25, $43.25 On Sale Now
June 7 – Art Laboe’s Super Freestyle Explosion 8:00 PM
$69.50, $49.50, $39.50, $34.50, $28.50On Sale Now
June 14 – Intocable 8:00 PM
$85.00 $70.00 $55.00 $45.00 $35.00 $25.00On Sale Now
June 27 – Espinoza Paz 8:00 PM
$127, $97, $82, $67, $52, $32 On Sale Now
August 7 – Prince Royce 8:00 PM
$198.50, $53.50, $43.50, $33.50 On Sale Now
October 14 – Straight No Chaser7:30 PM
$47, $37, $27 On Sale Now
September 13 – Starship 8:00 PM
$12.50 On Sale Now
October 4 – Bluffett 8:00 PM
$12.50 On Sale Now
www.rabobankarena.com - www.bhnamphitheatre.com