HomeMy WebLinkAboutT7161-1 15-192 L&M Bond Release LtrPUBLIC WORKS DEPARTMENT
NICK FIDLER • DIRECTOR • CITY ENGINEER
September 30, 2016
Castle & Cooke California, Inc.
P.O. Box 11165
Bakersfield, California 93389 -1165
Re: Security Release for Tract 7161 Phase 1
Improvement Agreement No. 15 -192
Lexon Insurance Company
Labor and Material Bond No. 1119055 ($493,786.00)
To Whom It May Concern:
All improvements for the above - referenced Tract Map have been completed and a
NOTICE OF COMPLETION AND ACCEPTANCE OF WORK was filed on June 2 8, 2016 by the
City of Bakersfield. This letter is your authorization to release ONLY the Labor and Material
Bond No. 1119055. The original Labor and Material Bond is attached.
The Developer will maintain the Maintenance Bond No. 1136877 ($98,757.00) from Lexon
Insurance Company. The maintenance bond is required to guarantee all features of the
improvements for a minimum of one year from the date of recordation of the NOTICE OF
COMPLETION AND ACCEPTANCE OF WORK.
You are to maintain your policies of insurance for the duration of the warranty period.
Please submit to the City an updated copy of your Certificate of Insurance.
Should you have any questions regarding the above, please contact Michelle
Mendenhall at (661) 326 -3582.
Very Truly Yours,
Nick Fidler
City Engineer
By: w P
Daniel Padilla
Acting Civil Engineer IV - Subdivisions
XC: Reading file
Project file
S: /LANDDIVISION /REDUCE &RELEASE /2016/T7161 -1 15 -192 L &M BOND RELEASE
1600 Truxtun Avenue
Bakersfield • California • 93301
(661)326-3724
Fax (661) 852 -2120
www.bakersfieldcity.us
4�v P
B A
h
E
R
S
F
I E
L
D
PUBLIC WORKS DEPARTMENT
NICK FIDLER • DIRECTOR • CITY ENGINEER
September 30, 2016
Castle & Cooke California, Inc.
P.O. Box 11165
Bakersfield, California 93389 -1165
Re: Security Release for Tract 7161 Phase 1
Improvement Agreement No. 15 -192
Lexon Insurance Company
Labor and Material Bond No. 1119055 ($493,786.00)
To Whom It May Concern:
All improvements for the above - referenced Tract Map have been completed and a
NOTICE OF COMPLETION AND ACCEPTANCE OF WORK was filed on June 2 8, 2016 by the
City of Bakersfield. This letter is your authorization to release ONLY the Labor and Material
Bond No. 1119055. The original Labor and Material Bond is attached.
The Developer will maintain the Maintenance Bond No. 1136877 ($98,757.00) from Lexon
Insurance Company. The maintenance bond is required to guarantee all features of the
improvements for a minimum of one year from the date of recordation of the NOTICE OF
COMPLETION AND ACCEPTANCE OF WORK.
You are to maintain your policies of insurance for the duration of the warranty period.
Please submit to the City an updated copy of your Certificate of Insurance.
Should you have any questions regarding the above, please contact Michelle
Mendenhall at (661) 326 -3582.
Very Truly Yours,
Nick Fidler
City Engineer
By: w P
Daniel Padilla
Acting Civil Engineer IV - Subdivisions
XC: Reading file
Project file
S: /LANDDIVISION /REDUCE &RELEASE /2016/T7161 -1 15 -192 L &M BOND RELEASE
1600 Truxtun Avenue
Bakersfield • California • 93301
(661)326-3724
Fax (661) 852 -2120
www.bakersfieldcity.us