HomeMy WebLinkAboutPM12100 St Permit #14-20001996 White Ln Perf Bond Release LtrPUBLIC WORKS DEPARTMENT
NICK FIDLER • DIRECTOR • CITY ENGINEER
March 30, 2017
Sierra Oaks Partners, LLC
27271 Las Ramblas, Suite 100
Mission Viejo, California 92691
Re: Security Release for Street Permit # 14- 20001996
Westchester Fire Insurance Company
Performance Bond No. K09115833 ($1,286,378.00)
To Whom It May Concern:
All improvements for the above - referenced Street Permit have been completed and a
NOTICE OF COMPLETION AND ACCEPTANCE OF WORK was filed on March 29, 2017 by the
City of Bakersfield. This letter is your authorization to release ONLY the Performance Bond
No. K09115833. The original Performance Bond is attached.
The Developer will maintain the Labor and Material Bond No. K09115833 ($643,189.00),
and Maintenance Bond No. K09115833 ($128,638.00) from Westchester Fire Insurance
Company. The maintenance bond is required to guarantee all features of the
improvements for a minimum of one year from the date of recordation of the NOTICE OF
COMPLETION AND ACCEPTANCE OF WORK.
You are to maintain your policies of insurance for the duration of the warranty period.
Please submit to the City an updated copy of your Certificate of Insurance.
Should you have any questions regarding the above, please contact Michelle
Mendenhall at (661) 326 -3582.
Very Truly Yours,
Nick Fidler
City Engineer
By:
Daniel APadilla
Civil Engineer IV - Subdivisions
XC: Reading file
Project file
S:/ LANDDIVISION /REDUCE&RELEASE/2016/ST #14- 20001996 PERF BOND RELEASE
1600 Truxtun Avenue
Bakersfield • California • 93301
(661)326-3724
Fax (661) 852 -2120
www.bakersfieldcity.us
<r
4.P`W P
B A
K
E
R
S
IF
l E
L
D
PUBLIC WORKS DEPARTMENT
NICK FIDLER • DIRECTOR • CITY ENGINEER
March 30, 2017
Sierra Oaks Partners, LLC
27271 Las Ramblas, Suite 100
Mission Viejo, California 92691
Re: Security Release for Street Permit # 14- 20001996
Westchester Fire Insurance Company
Performance Bond No. K09115833 ($1,286,378.00)
To Whom It May Concern:
All improvements for the above - referenced Street Permit have been completed and a
NOTICE OF COMPLETION AND ACCEPTANCE OF WORK was filed on March 29, 2017 by the
City of Bakersfield. This letter is your authorization to release ONLY the Performance Bond
No. K09115833. The original Performance Bond is attached.
The Developer will maintain the Labor and Material Bond No. K09115833 ($643,189.00),
and Maintenance Bond No. K09115833 ($128,638.00) from Westchester Fire Insurance
Company. The maintenance bond is required to guarantee all features of the
improvements for a minimum of one year from the date of recordation of the NOTICE OF
COMPLETION AND ACCEPTANCE OF WORK.
You are to maintain your policies of insurance for the duration of the warranty period.
Please submit to the City an updated copy of your Certificate of Insurance.
Should you have any questions regarding the above, please contact Michelle
Mendenhall at (661) 326 -3582.
Very Truly Yours,
Nick Fidler
City Engineer
By:
Daniel APadilla
Civil Engineer IV - Subdivisions
XC: Reading file
Project file
S:/ LANDDIVISION /REDUCE&RELEASE/2016/ST #14- 20001996 PERF BOND RELEASE
1600 Truxtun Avenue
Bakersfield • California • 93301
(661)326-3724
Fax (661) 852 -2120
www.bakersfieldcity.us
<r
4.P`W P