HomeMy WebLinkAboutPM 12023 Phase 1 Bldg 18-20 Drainage Study
C:\USERS\GMEND\DESKTOP\1002_1 PHASE 1 BLDG 18-20 DRAINAGE REPORT_9-14_17.DOCX
DRAINAGE CONCEPT REPORT
McCutchen Commerce Center
PM No. 12023, Lot 1
Phase 1, Bldgs. 18-20 Final Improvements
Future Northeast Parking Bldg. 21
6900 McCutchen Road, Bakersfield CA
September 14, 2017
Page 2
C:\USERS\GMEND\DESKTOP\1002_1 PHASE 1 BLDG 18-20 DRAINAGE REPORT_9-14_17.DOCX
DRAINAGE CONCEPT – DISCUSSION:
PRE – DEVELOPED (EXISTING) SITE CONDITIONS:
The overall site (VTPM No. 12023 – Lots 1-4) currently comprises approximately
80 acres of vacant land which is currently being farmed. The land is relatively flat
but does contain a gentle slope of about 3-4 feet vertical fall from the northerly
edge of the site which is bordered by future Berkshire Road to the southerly edge
of the site which is defined as McCutchen Road. The overall site is currently one
lot but has received tentative approval for a parcel map. The approximate site
overall dimensions are about 1300+ lineal feet east to west and about 2600+ feet
north to south. The northerly 40+- acres is zoned R-2 and the southerly 40+-
acres is zoned M-1. No deviance from the current zoning is planned at this point.
Currently, approximately 9 acres of the south 40 acres have an active grading
permit GP#15-400000-80 and are rough graded. The overall drainage report
prepared by our firm dated March 17, 2016 has also been approved by the City of
Bakersfield (Attachment 1) and is included for reference.
The “north 40” acres which is zoned R-2 is, and will remain for the foreseeable
future, vacant and utilized for agriculture purposes. This area is mapped on the
tentative map as Parcels 2, 3 and 4. The topography of this area is gently sloping
north to south however; only one to two feet of vertical relief exists within the
approximately 1300 foot distance within these lots. In addition, an existing dirt
raised road (about one foot high) exists near the southerly portion of Parcel 2. The
area, currently in its agriculture use, is flood irrigated via a pump on the
northwesterly quadrant of the site near future Berkshire Road and a pipe system
that evenly distributes the irrigation water along the northerly edge of the property,
and then the crops are flood irrigated via a gravity sheet flow that slowly distributes
the irrigation water from north to south. The flows are then stopped and contained
by the raised dirt road near the southerly lot line for Parcel 2. Therefore, no
existing irrigation water or natural stormwater flows upon Parcels 2-4 are able to
infiltrate into the area of Parcel 1 (the “south 40”).
A similar situation occurs over Parcel 1 (the “south 40”). Natural or irrigated flows
begin just immediately south of the raised dirt road and flow southerly to
McCutchen Road where all flows are stopped and contained as the elevation of
McCutchen Road is actually higher then Parcel 1. As a result, flows from the
subject site are fully contained within the site and will remain so even in the
ultimate fully improved proposed development. No flows from within the subject
site do or will (in the future) flow to the offsite. In addition, flows from the
adjacent properties to the north, east, and west also do not flow to within the
subject property. For fairly obvious reasons, no pre-developed hydrology
calculations were performed for this report.
Page 3
C:\USERS\GMEND\DESKTOP\1002_1 PHASE 1 BLDG 18-20 DRAINAGE REPORT_9-14_17.DOCX
Exhibit A provides topographic information as shown on the tentative map.
POST – DEVELOPED (PROPOSED) SITE CONDITIONS:
The project relative to this drainage report is of only that portion of the southerly
40+- acre M-1 light industrial site described as Phase 1 and is located within the
southeasterly portion of Parcel 1 of VTPM No. 12023. The area described is
depicted on Exhibit B. The proposed improvements to the site include 3 new
20,469 square foot light industrial buildings (Building no. 18-20), landscaping and
parking. Building 17 and its associated basins have already been approved and
are in construction. Drainage from the public improvement is split into two areas
and have been approved for drainage and are in construction as stated in the
previously Approved Building 17 drainage study dated March 17, 2016. The
hydrology calculations for all remaining drainage areas for Bldgs. 18-20 are
provided in Exhibit C & C-1.
The overall and ultimate light industrial project for Parcel 1 “south 40” is being
designed as a commercial condominium and is so approved via the tentative
conditions of approval. An association and relative CCR’s have been prepared,
and the property association will manage and enforce all regulations as well as
provide weekly maintenance to any and all drainage structures within the private
onsite portion of this development.
The project has been uniquely designed in that the site utilizes a series of shallow
retention basins, with a maximum ponding depth of no more than 18 inches,
within the front yard areas of each building rather than a typical singular deep and
fenced retention basin in a corner of the development. A pictorial example of the
ponding methodology can be seen via the rendering shown in Exhibit D and is
applicable to the ponds fronting Building 18 thru 20 as previously approved for
Building 17 as well as the ponds immediately across and on the east side of the
roadway named Network Court. This methodology has been approved by the City
of Bakersfield Public Works Department (See Approved Drainage Study Building
17 dated March 17, 2017).
Since the private onsite driveways (roadways) have a flat centerline grade
throughout the development, the roadway stormwater flows begin at the crown
or centerline and thus drain to the roadway edge at 2% in a sheetflow (no
concentration of drainage) condition or configuration. The edge of the roadways
are not equipped with a standard curb and gutter but rather a concrete mow strip
type edging that is flush with the edge of roadway surface, thus allowing the sheet
flow drainage to exit the roadway and into the front yard retention basins. A cross
sectional example of this can be seen in Exhibit G. The sloping between the
roadway edge and bottom of basin will not exceed a gradient of 4 horizontal to 1
vertical. All of the shallow front yard retention basins within Phase 1 are connected
Page 4
C:\USERS\GMEND\DESKTOP\1002_1 PHASE 1 BLDG 18-20 DRAINAGE REPORT_9-14_17.DOCX
to each other via a series of 8” pvc type pipes or “Basin Interties” as they are
referred to within the construction documents. Since the roadway centerlines are
level, and the finish floor grades for all of the buildings are also level, the basins
area also level at the bottom grade of the basin as well as the elevation of the design
water surface (DWS) which is based upon the 100yr 24 hour rainfall event as
required by the City of Bakersfield. It should be noted that, even though the basins are
limited to a water depth of no more than 18”, the DWS for a 100 year storm is lower than the
full possible 18” depth of the basin. As a result, the ponds can actually hold a much
greater storm than what is required by city code. Also, what may initially appear to
be separate basins in front of each building, they are indeed all connected with the
basin intertie pipes and are thus one large connected basin as depicted in Exhibit
C. This configuration provides a unique advantage in that, should one area provide
a particularly greater infiltration or percolation rate than another, the ponding area
of greater infiltration will actually help to ‘draw down” the other areas as
stormwater will travel through the basin intertie pipes between one ponding area
and another.
Basin bottoms will be landscaped with low water consumption products as shown
on the landscape plans. The major portion of the basin bottoms will be of a grassy
type product called Kurapia. This product will provide the aesthetic appearance of
a grass but requires vastly less water and only requires mowing periodically. In
addition, since it is a living organism, it will provide a “bio-retention” type of
system for cleaning source and non-source point pollutants from the stormwater
prior to same entering into the percolation zones which ultimately end up
recharging the groundwater aquifers. This type of natural bio-cleansing of
pollutants is a much more effective method than the typical CDS or Vortechnix
type units which are geared more towards eliminating trash and solids. A weekly
gardener maintenance crew directed by the project association will provide regular
pickup of trash and solids from all areas onsite.
Other sources of stormwater inflow emanate from the roof and parking lot areas
of the site. These are collected within catch basins and conveyed via 8” pvc pipes
to an outlet into the bottom surface of the retention ponds near the bottom edge
of the pond, which provides a bio-type filtration of the stormwaters which in turn
will percolate into the groundwater aquifers. Again, since the bottom of the
retention ponds are of a biological grassy type living and regenerating organism,
there is, according to local city standards, no need to further provide any type of
water quality products or remediation to the systems proposed.
All hydrology calculations can be seen within Exhibit F. Calculations for the
hydrology/hydraulics of onsite subareas for catch basins and pipes are also
included within this report. As the methodology proposed within this project is
allowable although somewhat unique, we have provided a system that utilizes a
tremendous factor of safety within all of the calculations and the resultant product.
Page 5
C:\USERS\GMEND\DESKTOP\1002_1 PHASE 1 BLDG 18-20 DRAINAGE REPORT_9-14_17.DOCX
It should be noted for example as seen on Exhibit F, that the overall volume of
retention within the basins within phase 1 is 192% of that which is required by the city. The
conclusion can be drawn from Exhibit F and the above that the system proposed
provides an extremely conservative and effective methodology for the project
stormwater system, while providing numbers far in excess of that which is
mandated by the city requirements. In addition, the aesthetic value of said system
is more than evident as seen on Exhibit I. Once again, this stormwater
retention/disposal system will be maintained weekly by the association to ensure
functionality and appearance. It should also be noted that; in the event of a
catastrophic rainfall event (far in excess of a 100 year storm) which may cause
severe flooding; the finished floors of all buildings has been set to an elevation of
at least one foot above the ultimate low flow site outlet which is located at the
gutter flowline on McCutchen Road at the southeast corner of the project. Should
this occur, flows would then travel offsite to the east in a natural condition as
exists presently. As is evident on Exhibit F, the percolation rates and pond areas
are vastly more than adequate to serve the purpose. It is hereby mandated
within this report and the construction documents that the soils engineer
be present onsite during construction to assure the materials being used at
basin bottoms are compatible with the percolation rates required in order
to assure compliance with city requirements. A supporting addendum soils
report letter dated March 2, 2016 is included herein as Exhibit J.
Hydrology and hydraulic calculations for onsite storm drain piping are also
included herein and all supporting documentation for methodology relative to
basin and pipe sizing is per standards by the City of Bakersfield, and those
documents i.e. Plates D1 and D2 as well as excerpts from the city drainage
standards section 2.3.2.1 along with section 2.8.2.1.
In summary, we believe the proposed system not only serves the community better
than normal deeper, fenced, and sometimes not well maintained aesthetically
unpleasing standard retention basins, it also is in greater concert with the desires
called for within the NPDES, CalGreen, and LID standards. In addition, since no
“normal” storm drain and retention basin system is being proposed, there are no
public catch basins or RCP piping or large “hole in the ground” (retention basins)
areas, which in turn results in lowered developer costs, the elimination of city
public funded maintenance costs over the years, and an additional building within
the development which then results in additional tax revenues for decades or more
for the city while also creating additional building square footage which will result
in more jobs within the community.
Page 6
C:\USERS\GMEND\DESKTOP\1002_1 PHASE 1 BLDG 18-20 DRAINAGE REPORT_9-14_17.DOCX
Attachment 1
Copy of City Drainage Study Approval Letter
Page 7
C:\USERS\GMEND\DESKTOP\1002_1 PHASE 1 BLDG 18-20 DRAINAGE REPORT_9-14_17.DOCX
Exhibit A
VESTING TENTATIVE PARCEL MAP No. 12023
同調融や手で心競れei寄αlめれゐ競れ納れ同町の書館〃
○○め確γ紳あo磐
しoc▲調iN l州: q丁でo了甘∧青と照S「I〇D冊情唯S了岬凡了o「 〇回旧SOO「HE∧§了QUA即ER併笠場の00 2亀†oWN勢I博う0 SOO「岬.照AN∝ 27 EAS購軸00N了以肌o自供璽AND雌`恥胴軸各の摺親.譜盤恩諜報語継艶管轄Nま,離怒艶_議了併唯5晒冊
喜一 へ・ま 引 a 嘩隷雪上/s∴竪聖霊悪塁二王聖二蕊、
竃 」 ! i i l 6“i l t i l l ニ! ∞」 勤C倭蓬㌣ ̄ミミ二°一重二二三こう ̄〒 ̄せこ三二〇一二二‥「-義熱二三三二二二、 Pく二二二l丁 ̄\,示DiA 掌十 一一一葛 生P完了 ∴∵∵ 憎黙雷籍6 子もPc・榔 ノ■PARCELl 葛PMN0.∴∴∴30( AGRICULTUR l l PARCEL2 PMN0.う0 雪ぐ 爵音 PARCEL5
「伊/」臆・臆孟悌出師…Y 旧 旧 情 ∴∴ 性 情 pARC軋5 、、一 言龍一二二一ノ//「 l
TFiEg∴_ウノEL巨V.355十∴l 一、 ) ) ) .AR。乱4 自
l l 音 音 丁 擢終簿も 器終鰐 口
PHASE3 u 喜 雪 68鵜5’ S㈱“18 ̄と PHAS巨4I l )i )i ll 。 6う轡.之2’
132-・汀 -i- (
、音i
(
∴ i
PARCEL2 篭絡㈲
①∴<∴音 ∝i曇 , PHASE2 l
ト⊃音 ○○ I
∴芸 , i
ト○ ○ i
ト叱「 ∴: _二_」 据-2 s。。ti2t。E ,S,。A。 E」FV354+-,∥
「C i !45i 悟 憶 峠 l 喜 I I ll 音 当 i ( i ! I I I 」 ∴∴∴ ∴ ∴∵∴ ∴ ∴∴: 「 i i 、言 ! ÷i 菅 l之 一一一一--一一一書臆  ̄ ̄ ̄ ̄ ̄ ̄一 ̄ ̄-「--叫---へ--ニー「
1
、)
言
!
i
)
(
i PMNo,30 毒AGRICULTUR 富〈
)
(師の悪親」p岬, i
経絡鮮〉 (
PHASEl l
上 l_
誉 I P A R C E L 4
旨 へr.」_ 上i た 畠 ll
嘗 =
=
ll
= PMN0.∴∴30 ACRICULTUR ノら 音l脚馴丁P曲目00持 音、一一〇一--臆-iへ.
=
=
il
l
 ̄ 醐…AY 臨-W 乱臣V。5。十-」
) 主音′・・,、 .調-SS 亘∴十 一 ∴∵一∵一一∴一∴∴_∴∴∴∴∴∴∴ 、:
____」 SS “’/●」∴-∴β:S誓:c● 血c面c灘馳訟虹∴暁認子音←、- 一議講義ティ 1PA6竃1eふoR
盤認÷ 欝藷討 ̄二言語手請 剛 京8,cU1「とR,鋼DさW∧しX
VlaNITYMAP ANDPA\のS巾IEETmPRO\偶旧¶S I●プ「¶o事〇〇重 十千十!:I-I ∴∴∴∵
少 一 帖輯由輔車憫 叫生血∴∴同上「旧中門 窪亨 言 直しS了439プ】 豊EXP∴ト31 ̄14しこ JASON∈.VANCURE:N L.S.743g佳XPJ/51/14.)seO手cAし、{翁
12. ∈)OS¶Nc之oNiNG R-2 ▲ND 職-1
:二二驚簿薗藍臨
慧蘭欝繚
統薄隷書鵠醤悪書讐器I端豊艶
恥MN†§
Ⅲ圧「併しO物Nc ARE丁岬と蛾N丁S S撮O博i Oト1 P飛田.州洲A鼠Y ¶几雪R済)ORJ PREPARED βY C機ICAcO ¶T」とCOWP▲NY, DAT田〉 WAY 4. 2OO9 ^NDS11o録調∴AS ¶TしE NU軸B田ミo8-5書1㈱-q」
⑦ 事態露盤蕊轄笠譜総譜課溜N
⑧ 統認諾欝憶鰐豊叢患舘羅S
昌※丁l盤鷲了雷s怒蓋椋も篭一黙許㈱DS
⑥ 能講離乳慈基盤鵜落譜翁一能則
P匪I DOCIW即T REcOf①ED APfUし23. 1O42 IN BOOK IO77,PAc∈ 164.調働A」 R言の照〇年峨飛N c(九州「Y
⑯ 省提議謎認諾親藩能謂非
2(×鳩▲S INS†RUMENT No. O2OelOJ+49. OFFlaAI_随COROS,龍飛持cOON丁子
」とG王ND
① 剛ND㈹∪脚†寝るNO間
△ S且青2“ BRASS cAP叩∞Nα涯1モiN曝しし調ARi優りしS 74き8 0o物12“
。 善†洛譜隔晒硬肌C仲間灼
□ Sご丁2“脈〔職PiP己物巾I丁Acしま74き9
0罵. 僻照°∧」膝cOOS
AC. AC京王S
SF SOO雌「日E丁
(着し cROSS
P.∪.エ. PU閲C U¶uW EA剥各周丁服D H露遭O州
(R) 同的仙
/ / / / W相l庵R OF l応報)qjしA照∧c∝SS則餅I了
∂ 馴S¶N6 POⅥ駅戸の嘉
績 悶S¶N6 音岬Å.「駅 VA」l∈
〔し〔C口 と灼S¶Nc田上c〇割c日0×
-16“W鵜各XS¶青c肌瞭R UN且州D S)Z工
- SS -岳鴫S¶Nc SANI了ARY :蓬脂uN巳
㊤ 岳鴫S間c SANI丁ARY襲:W各R舶▲間帆と
PH▲iiNG
lll〔 LO†S SllOWN∴WAY BE; CONSTRUCltI) lN PH∧SCS. THE NUMB王R CF
離職AY NOT N関幾人尺-しY閲堪鋤碓00取説
哩壁
T間S PRO,gcT ISしOCATED IN FEVA F|(×D INSURANCE fiATE uAP NO.
EXHIBIT ’’A’’
Page 8
C:\USERS\GMEND\DESKTOP\1002_1 PHASE 1 BLDG 18-20 DRAINAGE REPORT_9-14_17.DOCX
Exhibit B
Page 9
C:\USERS\GMEND\DESKTOP\1002_1 PHASE 1 BLDG 18-20 DRAINAGE REPORT_9-14_17.DOCX
Exhibit C & C-1
BUILDING
17
BUILDING
18
BUILDING
20
DRAINAGE AREA B
TO POND 1
14,584 SF.
C = 0.95
DRAINAGE AREA
FUTURE 9 E'LY RG
TO POND 1
19,859 SF.
C = 0.50
DRAINAGE AREA
FUTURE 16 E'LY RG
TO POND 3
20,128 SF.
C = 0.50
DRAINAGE AREA
FUTURE 14 E'LY RG
TO POND 7
19,994 SF.
C = 0.50
DRAINAGE AREA
FUTURE 13 E'LY RG
TO POND 8
20,134 SF.
C = 0.50
BUILDING
19
POND 1
POND 3
DRAINAGE AREA
FUTURE 15 E'LY RG
TO POND 5
32,062 SF.
C = 0.50
POND 5 POND 7 POND 8
POND 10
DRAINAGE AREA
FUTURE BLDG 21
S'LY RG
TO POND 10
28,952 SF.
C = 0.50
POND 9
DRAINAGE AREA
BLDG 20
TO POND 9
59,137 SF.
C = 0.80
DRAINAGE AREA
BLDG 19
TO POND 6
69,374 SF.
C = 0.80
POND 6POND 4
DRAINAGE AREA
BLDG 18
TO POND 4
59,745 SF.
C = 0.80
DRAINAGE AREA
BLDG 17 WITH REAR SE
& BLDG 18
TO POND 2
83,254 SF.
C = 0.80
POND 2
DRAINAGE AREA A
TO POND 2
15,104 SF.
C = 0.95
Mc
C
U
T
C
H
E
N
R
O
A
D
NETWORK COURT
PROJECT:
MORAN DEVELOPMENT CORP.
7352 AUTOPARK DR.
HUNTINGTON BEACH, CA 92648
CONTACT: JOE MORAN
(714) 843-9116 C-HY-1
9/14/17DATE:HYDROLOGY STUDY
EXHIBIT - C
SHEET NO.:
SCALE:HORIZ: NO SCALE
VERT: NO SCALE
LEGEND
DRAINAGE AREAS
PIPE 3
PIPE 1
PIPE 2
PIPE 5
PIPE 6
PIPE 4 PIPE 7
PIPE 9
PIPE 16
PIPE 12
PIPE 11
PIPE 13
PIPE 15
PIPE 14
PIPE 10
PIPE 8
PIPE 16PIPE 16PIPE 16
BUILDING
17
BUILDING
18
BUILDING
20
BUILDING
19
DRAINAGE SUB-AREA
BUILDING 20 - ROOF
AREA = 9,560 SF
0.22 ACRES
DRAINAGE SUB-AREA
BUILDING 17 - REAR SE
& BUILDING 18
AREA = 26,450 SF
0.60 ACRES
DRAINAGE SUB-AREA
BUILDING 18 - REAR NE
BUILDING 19 - REAR SE
AREA = 26,300 SF
0.60 ACRES
DRAINAGE SUB-AREA
BUILDING 18 - NORTH PARKING
AREA = 3,825 SF 0.09 ACRES
DRAINAGE SUB-AREA
BUILDING 19 - SOUTH PARKING
AREA = 3,943 SF 0.09 ACRES
DRAINAGE SUB-AREA
BUILDING 19 - NORTH PARKING &
HALF PIPE 7 AREA
AREA = 3,775 SF 0.09 ACRES
(16,904 TOTAL AREA)
DRAINAGE SUB-AREA
BUILDING 19 - REAR NE
BUILDING 20 - REAR SE
AREA = 26,259 SF
0.60 ACRES
DRAINAGE SUB-AREA
BUILDING 20 - REAR NE
BUILDING 20 - NORTH PARKING
TOTAL AREAS = 11,900 SF
0.27 ACRES
DRAINAGE SUB-AREA
BUILDING 19 - REAR NE
BUILDING 120 - REAR SE
AREA = 3,876 SF 0.09 ACRES
(17,006 TOTAL AREA)DRAINAGE SUB-AREA
BUILDING 20 - REAR NE
AREA = 14,173 SF
0.33 ACRES
DRAINAGE SUB-AREA
BUILDING 20 -
NORTH PARKING
AREA = 814 SF
0.02 ACRES
DRAINAGE SUB-AREA
BUILDING 20 -
NORTH PARKING
AREA = 3,868 SF
0.09 ACRES
DRAINAGE SUB-AREA
FUTURE BLDG 21 - REAR NE
AREA = 3,145 SF
0.07 ACRES
DRAINAGE SUB-AREA
BUILDING 20 - REAR NE
BUILDING 20 - NORTH PARKING
AREA = 353 SF
0.008 ACRES
DRAINAGE SUB-AREA
BUILDING 17 - ROOF
AREA = 9,560 SF
0.22 ACRES
DRAINAGE SUB-AREA
BUILDING 18 - ROOF
AREA = 9,560 SF
0.22 ACRES
DRAINAGE SUB-AREA
BUILDING 19 - ROOF
AREA = 9,560 SF
0.22 ACRES
PROJECT:
MORAN DEVELOPMENT CORP.
7352 AUTOPARK DR.
HUNTINGTON BEACH, CA 92648
CONTACT: JOE MORAN
(714) 843-9116 C-HY-2
9/14/17DATE:PIPE ANALYSIS MAP
EXHIBIT - C1
SHEET NO.:
SCALE:HORIZ: NO SCALE
VERT: NO SCALE
LEGEND
SUB-AREAS
STORM DRAIN
TIME OF
CONCENTRATION
Page 10
C:\USERS\GMEND\DESKTOP\1002_1 PHASE 1 BLDG 18-20 DRAINAGE REPORT_9-14_17.DOCX
Exhibit D
EX
H
I
B
I
T
"
D
"
Page 11
C:\USERS\GMEND\DESKTOP\1002_1 PHASE 1 BLDG 18-20 DRAINAGE REPORT_9-14_17.DOCX
Exhibit F
Date:
8/28/2017
Lot Basin Design
Calculation for Basin(s)
Formula is:0.15 x C x Acres = Volume of Basin in Ac/ft
Formula for basin capacity:V=1/6(Abtm+4Amid+Atop)D
(18-inch Max. Stormwater Depth with 4:1 Side Slope Within DWS zone)
Drainage
Area (s.f.)C A
(ac)
V
(ac/ft)
Required
Storage
Abtm 4Amid
Basin sq/ft
@ top of
18"
freeboard
D to
Total
availa
ble18"
Depth
Total Basin
Ac.Ft.
Volume to
18"
Freeboard
Total 18"
Basin %
Storage
Provided vs.
Req'd
Fut 13-E'ly RG 20,134 0.50 0.462 0.034666 0.035 5693 26520 7,567 1.5 0.228 658.59%
Fut 14-E'ly RG 19,994 0.50 0.459 0.0344249 0.034 3826 18380 5,364 1.5 0.158 459.64%
Fut 15-E'ly RG 32,062 0.50 0.736 0.0552032 0.055 5770 28416 8,438 1.5 0.245 443.14%
Fut 16-E'ly RG 20,128 0.50 0.462 0.0346556 0.035 5882 28936 8,586 1.5 0.249 718.80%
Fut 9-E'ly RG 19,859 0.50 0.456 0.0341925 0.034 7946 36990 10,549 1.5 0.318 931.32%
Area B-McCutchen 14,584 0.95 0.335 0.0477094 0.048 0 1.50 0.000 0.00%
Bldg 17 83,254 0.80 1.911 0.2293499 0.229 3015 17116 5,543 1.5 0.147 64.25%
Area A-McCutchen 15,104 0.95 0.347 0.0494105 0.049 0 1.50 0.000 0.00%
Bldg 18 59,745 0.80 1.372 0.1645868 0.165 3552 20064 6,480 1.5 0.173 104.95%
Bldg 19 69,374 0.80 1.593 0.1911129 0.191 3548 20066 6,485 1.5 0.173 90.39%
Bldg 20 59,137 0.80 1.358 0.1629118 0.163 2553 14854 4,874 1.5 0.128 78.49%
Fut 21-S'ly RG 28,952 0.50 0.665 0.0498485 0.050 6384 31952 9,592 1.5 0.275 551.81%
10.15 1.088 2.094 192%
Conclusion: Surface Basins contain 192% of the capacity required per City of Bakersfield Standards for retention of 100 yr/24hr rain event.
Perc Within Surface Retention Basins
Phase 1a & 1b 1.088 ac.ft. storage needed = 47396 cu.ft.
Note: Assumes a surface perc rate of 0.28 cu.ft/sq.ft/day for areas 1a and 1b (from soils report)
Fut 13-E'ly RG 0.035 ac.ft. storage needed = 1510 cu.ft.
11158.3 cu.ft. in 7 days Sump Drains in 0.9 days
Fut 14-E'ly RG 0.034 ac.ft. storage needed = 1500 cu.ft.
7499.0 cu.ft. in 7 days Sump Drains in 1.4 days
Fut 15-E'ly RG 0.055 ac.ft. storage needed = 2405 cu.ft.
11309.2 cu.ft. in 7 days Sump Drains in 1.5 days
Fut 16-E'ly RG 0.035 ac.ft. storage needed = 1510 cu.ft.
11528.7 cu.ft. in 7 days Sump Drains in 0.9 days
Fut 9-E'ly RG 0.034 ac.ft. storage needed = 1489 cu.ft.
and Area B-McC 15574.2 cu.ft. in 7 days Sump Drains in 0.7 days
Bldg 17 0.229 ac.ft. storage needed = 9990 cu.ft.
and Area A-McC 5909.4 cu.ft. in 7 days Sump Drains in 11.8 days
Bldg 18 0.165 ac.ft. storage needed = 7169 cu.ft.
6961.92 cu.ft. in 7 days Sump Drains in 7.2 days
Bldg 19 0.191 ac.ft. storage needed = 8325 cu.ft.
6954.1 cu.ft. in 7 days Sump Drains in 8.4 days
Bldg 20 0.163 ac.ft. storage needed = 7096 cu.ft.
5003.9 cu.ft. in 7 days Sump Drains in 9.9 days
Fut 21-S'ly RG 0.050 ac.ft. storage needed = 2171 cu.ft.
12512.6 cu.ft. in 7 days Sump Drains in 1.2 days
81898.6 cu.ft. in 7 days =
4.05 days
Note: Perc Rates and relative calculations taken from soils report by Salem Engineering Company.
Surface sumps will drain in average of
Total Surface Perc in Basins =
direct perc in sump =
direct perc in sump =
direct perc in sump =
direct perc in sump =
direct perc in sump =
direct perc in sump =
direct perc in sump =
direct perc in sump =
direct perc in sump =
direct perc in sump =
McCUTCHEN COMMERCE CENTER
6900 McCutchen Road - Bakersfield, Ca
On-Site Sumps including Public Streets & Private Driveway Drainage
using 34'-wide Driveways and no interior Curb & Gutter
ENTIRE Lot Drainage-includes Streets/Driveways
For Buildings 17 - 20, and 660' of McCutchen Road north side
Adequate Soils Substituted at Surface for Perc @ 2.1 gal/sf/day
100yr Storage/Sump
HYDROLOGY/HYDRAULIC CALCULATIONS
Project Address: McCutchen Commerce Center
JBC 1002.1Date:
9/9/2017
AREA NO.Pipe No. 1-3 - Bldg 17 Rear Building & Bldg 18 SE Corner Inflow Area
Given:
Site Designation:Light Industrial M-1
Develop Time of Concentration:Type of Flow = Open Channel - Paved
Tc base time (roof to gutter) 10
Elevation @ gutter or flowline/invert highpoint = 354.39
Elevation @ gutter or flowline/invert lowpoint = 352.62
Distance between high and low points = 195 feet
Average slope = 0.91%0.009 ft/ft
n factor 0.016 Concrete=0.013, AC Parking=0.016, AC Roads=0.018,
Proposed Pipe(feet) 224.00 Feet RipRap=0.030, Grassland=0.035
Velocity 5.5 fps
Travel Time = 0.6 minutes
Add overland flow 6.0 minutes (from C.O.B.Development Standards-2.3.2.1)
Tc = 10 minutes (base)+0.6 minutes (travel) + 6.0 minutes overland =16.6
Tc = 16.6 minutes
Develop Hydrology:
Q = cia Q=design runoff in cfs, c=runoff coefficient, i=intensity in inches/hr, a=area in acres
Given:
Storm Frequency:10 year - Local Waterway
c =0.9 from C.O.B.Development Standards-Plate D-2
i =1.75 from C.O.B.Development Standards-Plate D-1
a =0.60721 from hydrology plan
Calculate Q10 =0.96 cfs
Develop Hydraulic Calculations For Closed Conduit Pipe:
Pipe Analysis for 223 L.F. of 8 " PVC Pipe 1, 2 and 3
invert elevation in-351.12
Q10 =0.96 cfs
Props'd Pipe(feet)0.67
Proposed Slope 0.005
n factor 0.011 (SDR 35 or equal)
Q = A(1.486/n)(R2/3*S1/2)
A= 0.352566
1.486/n= 135.0909
R2/3= 0.303862
S1/2= 0.070866
Q= (capacity) 1.03 cfs =93% full
invert elevation out-----350.00
Velocity
V = (1.486*R2/3*S1/2)/n
constant 1.486
R2/3= 0.303862
S1/2= 0.070866
Velocity= 2.9 fps
Conclusion:8 " Pipe @ 0.50 % OK
minutes (from C.O.B.Development Standards-2.3.2.1), Natural
Open = 0, R3/Commercial/Industrial = 10, R1/R2 = 15
HYDROLOGY/HYDRAULIC CALCULATIONS
Project Address: McCutchen Commerce Center
JBC 1002.1Date:
9/9/2017
AREA NO.Pipe No. 4 Inflow Area Bldg 18 NE Rear Corner & Bldg 19 SE Corner
Given:
Site Designation:Light Industrial M-1
Develop Time of Concentration:Type of Flow = Open Channel - Paved
Tc base time (roof to gutter) 10
Elevation @ gutter or flowline/invert highpoint = 354.39
Elevation @ gutter or flowline/invert lowpoint = 352.62
Distance between high and low points = 196 feet
Average slope = 0.90%0.009 ft/ft
n factor 0.015 Concrete=0.013, AC Parking=0.016, AC Roads=0.018,
Proposed Pipe(feet) 56.50 Feet RipRap=0.030, Grassland=0.035
Velocity 5.8 fps
Travel Time = 0.6 minutes
Add overland flow 6.0 minutes (from C.O.B.Development Standards-2.3.2.1)
Tc = 10 minutes (base)+0.6 minutes (travel) + 6.0 minutes overland =16.6
Tc = 16.6 minutes
Develop Hydrology:
Q = cia Q=design runoff in cfs, c=runoff coefficient, i=intensity in inches/hr, a=area in acres
Given:
Storm Frequency:10 year - Local Waterway
c =0.9 from C.O.B.Development Standards-Plate D-2
i =1.75 from C.O.B.Development Standards-Plate D-1
a =0.60608 from hydrology plan
Calculate Q10 =0.95 cfs
Develop Hydraulic Calculations For Closed Conduit Pipe:
Pipe Analysis for 56.5 L.F. of 8 " PVC Pipe 4
invert elevation in-351.12
Q10 =0.95 cfs
Props'd Pipe(feet)0.67
Proposed Slope 0.005
n factor 0.011 (SDR 35 or equal)
Q = A(1.486/n)(R2/3*S1/2)
A= 0.352566
1.486/n= 135.0909
R2/3= 0.303862
S1/2= 0.070334
Q= (capacity) 1.02 cfs =94% full
invert elevation out-----350.84
Velocity
V = (1.486*R2/3*S1/2)/n
constant 1.486
R2/3= 0.303862
S1/2= 0.070334
Velocity= 2.9 fps
Conclusion:8 " Pipe @ 0.49 % OK
minutes (from C.O.B.Development Standards-2.3.2.1), Natural
Open = 0, R3/Commercial/Industrial = 10, R1/R2 = 15
HYDROLOGY/HYDRAULIC CALCULATIONS
Project Address: McCutchen Commerce Center
JBC 1002.1Date:
9/9/2017
AREA NO.Pipe No.5 Inflow Area Bldg 18 North Parking
Given:
Site Designation:Light Industrial M-1
Develop Time of Concentration:Type of Flow = Open Channel - Paved
Tc base time (roof to gutter) 10
Elevation @ gutter or flowline/invert highpoint = 354.39
Elevation @ gutter or flowline/invert lowpoint = 351.00
Distance between high and low points = 69 feet
Average slope = 4.91%0.049 ft/ft
n factor 0.015 Concrete=0.013, AC Parking=0.016, AC Roads=0.018,
Proposed Pipe(feet) 150.50 Feet RipRap=0.030, Grassland=0.035
Velocity 13.6 fps
Travel Time = 0.1 minutes
Add overland flow 6.0 minutes (from C.O.B.Development Standards-2.3.2.1)
Tc = 10 minutes (base)+0.1 minutes (travel) + 6.0 minutes overland =16.1
Tc = 16.1 minutes
Develop Hydrology:
Q = cia Q=design runoff in cfs, c=runoff coefficient, i=intensity in inches/hr, a=area in acres
Given:
Storm Frequency:10 year - Local Waterway
c =0.9 from C.O.B.Development Standards-Plate D-2
i =1.75 from C.O.B.Development Standards-Plate D-1
a =0.68781 from hydrology plan Includes Sum Area Bldg 18 NE Rear 0.30 acres
Calculate Q10 =1.08 cfs
Develop Hydraulic Calculations For Closed Conduit Pipe:
Pipe Analysis for 150.5 L.F. of 8 " PVC Pipe 5
invert elevation in-350.84
Q10 =1.08 cfs
Props'd Pipe(feet)0.67
Proposed Slope 0.006
n factor 0.011 (SDR 35 or equal)
Q = A(1.486/n)(R2/3*S1/2)
A= 0.352566
1.486/n= 135.0909
R2/3= 0.303862
S1/2= 0.074833
Q= (capacity) 1.08 cfs =100% full
invert elevation out-----350.00
Velocity
V = (1.486*R2/3*S1/2)/n
constant 1.486
R2/3= 0.303862
S1/2= 0.074833
Velocity= 3.1 fps
Conclusion:8 " Pipe @ 0.56 % OK
minutes (from C.O.B.Development Standards-2.3.2.1), Natural
Open = 0, R3/Commercial/Industrial = 10, R1/R2 = 15
HYDROLOGY/HYDRAULIC CALCULATIONS
Project Address: McCutchen Commerce Center
JBC 1002.1Date:
9/9/2017
AREA NO.Pipe No.6 Inflow Area Bldg 19 South Parking
Given:
Site Designation:Light Industrial M-1
Develop Time of Concentration:Type of Flow = Open Channel - Paved
Tc base time (roof to gutter) 10
Elevation @ gutter or flowline/invert highpoint = 354.39
Elevation @ gutter or flowline/invert lowpoint = 351.00
Distance between high and low points = 86 feet
Average slope = 3.94%0.039 ft/ft
n factor 0.015 Concrete=0.013, AC Parking=0.016, AC Roads=0.018,
Proposed Pipe(feet) 145.00 Feet RipRap=0.030, Grassland=0.035
Velocity 12.1 fps
Travel Time = 0.1 minutes
Add overland flow 6.0 minutes (from C.O.B.Development Standards-2.3.2.1)
Tc = 10 minutes (base)+0.1 minutes (travel) + 6.0 minutes overland =16.1
Tc = 16.1 minutes
Develop Hydrology:
Q = cia Q=design runoff in cfs, c=runoff coefficient, i=intensity in inches/hr, a=area in acres
Given:
Storm Frequency:10 year - Local Waterway
c =0.9 from C.O.B.Development Standards-Plate D-2
i =1.75 from C.O.B.Development Standards-Plate D-1
a =0.48051 from hydrology plan Includes Sum Area Bldg 18 NE Rear 0.30 acres
Calculate Q10 =0.76 cfs
Develop Hydraulic Calculations For Closed Conduit Pipe:
Pipe Analysis for 145 L.F. of 8 " PVC Pipe 6
invert elevation in-350.84
Q10 =0.76 cfs
Props'd Pipe(feet)0.67
Proposed Slope 0.006
n factor 0.011 (SDR 35 or equal)
Q = A(1.486/n)(R2/3*S1/2)
A= 0.352566
1.486/n= 135.0909
R2/3= 0.303862
S1/2= 0.076092
Q= (capacity) 1.10 cfs =69% full
invert elevation out-----350.00
Velocity
V = (1.486*R2/3*S1/2)/n
constant 1.486
R2/3= 0.303862
S1/2= 0.076092
Velocity= 3.1 fps
Conclusion:8 " Pipe @ 0.58 % OK
minutes (from C.O.B.Development Standards-2.3.2.1), Natural
Open = 0, R3/Commercial/Industrial = 10, R1/R2 = 15
HYDROLOGY/HYDRAULIC CALCULATIONS
Project Address: McCutchen Commerce Center
JBC 1002.1Date:
9/9/2017
AREA NO.Pipe No. 7&7A Inflow Area BLD 19 NE REAR & BLDG 20 SE REAR
Given:
Site Designation:Light Industrial M-1
Develop Time of Concentration:Type of Flow = Open Channel - Paved
Tc base time (roof to gutter) 10
Elevation @ gutter or flowline/invert highpoint = 354.39
Elevation @ gutter or flowline/invert lowpoint = 352.62
Distance between high and low points = 113 feet
Average slope = 1.57%0.016 ft/ft
n factor 0.016 Concrete=0.013, AC Parking=0.016, AC Roads=0.018,
Proposed Pipe(feet) 56.50 Feet RipRap=0.030, Grassland=0.035
Velocity 7.2 fps
Travel Time = 0.3 minutes
Add overland flow 0.0 minutes (from C.O.B.Development Standards-2.3.2.1)
Tc = 10 minutes (base)+0.3 minutes (travel) + 0.0 minutes overland =10.3
Tc = 10.3 minutes
Develop Hydrology:
Q = cia Q=design runoff in cfs, c=runoff coefficient, i=intensity in inches/hr, a=area in acres
Given:
Storm Frequency:10 year - Local Waterway
c =0.9 from C.O.B.Development Standards-Plate D-2
i =1.80 from C.O.B.Development Standards-Plate D-1
a =0.60282 from hydrology plan
Calculate Q10 =0.98 cfs
Develop Hydraulic Calculations For Closed Conduit Pipe:
Pipe Analysis for 56.5 L.F. of 8 " PVC Pipe 7
invert elevation in-351.12
Q10 =0.98
Props'd Pipe(feet)0.67
Proposed Slope 0.005
n factor 0.011 (SDR 35 or equal)
Q = A(1.486/n)(R2/3*S1/2)
A= 0.352566
1.486/n= 135.0909
R2/3= 0.303862
S1/2= 0.070711
Q= (capacity) 1.02 cfs =95% full
invert elevation out-----350.84
Velocity
V = (1.486*R2/3*S1/2)/n
constant 1.486
R2/3= 0.303862
S1/2= 0.070711
Velocity= 2.9 fps
Conclusion:8 " Pipe @ 0.50 % OK
minutes (from C.O.B.Development Standards-2.3.2.1), Natural
Open = 0, R3/Commercial/Industrial = 10, R1/R2 = 15
HYDROLOGY/HYDRAULIC CALCULATIONS
Project Address: McCutchen Commerce Center
JBC 1002.1Date:
9/9/2017
AREA NO.Pipe No. 8 Inflow Area BLDG 19 NORTH PARKING
Given:
Site Designation:Light Industrial M-1
Develop Time of Concentration:Type of Flow = Open Channel - Paved
Tc base time (roof to gutter) 10
Elevation @ gutter or flowline/invert highpoint = 354.39
Elevation @ gutter or flowline/invert lowpoint = 352.62
Distance between high and low points = 88 feet
Average slope = 2.01%0.020 ft/ft
n factor 0.016 Concrete=0.013, AC Parking=0.016, AC Roads=0.018,
Proposed Pipe(feet) 150.00 Feet RipRap=0.030, Grassland=0.035
Velocity 8.1 fps
Travel Time = 0.2 minutes
Add overland flow 0.0 minutes (from C.O.B.Development Standards-2.3.2.1)
Tc = 10 minutes (base)+0.2 minutes (travel) + 0.0 minutes overland =10.2
Tc = 10.2 minutes
Develop Hydrology:
Q = cia Q=design runoff in cfs, c=runoff coefficient, i=intensity in inches/hr, a=area in acres
Given:
Storm Frequency:10 year - Local Waterway
c =0.9 from C.O.B.Development Standards-Plate D-2
i =1.80 from C.O.B.Development Standards-Plate D-1
a =0.38806 from hydrology plan
Calculate Q10 =0.63 cfs
Develop Hydraulic Calculations For Closed Conduit Pipe:
Pipe Analysis for 150 L.F. of 8 " PVC Pipe 8 (includes inflow from pipe 7)
invert elevation in-350.84
Q10 =0.63 cfs
Props'd Pipe(feet)0.67
Proposed Slope 0.006
n factor 0.011 (SDR 35 or equal)
Q = A(1.486/n)(R2/3*S1/2)
A= 0.352566
1.486/n= 135.0909
R2/3= 0.303862
S1/2= 0.074833
Q= (capacity) 1.08 cfs =58% full
invert elevation out-----350.00
Velocity
V = (1.486*R2/3*S1/2)/n
constant 1.486
R2/3= 0.303862
S1/2= 0.074833
Velocity= 3.1 fps
Conclusion:8 " Pipe @ 0.56 % OK
minutes (from C.O.B.Development Standards-2.3.2.1), Natural
Open = 0, R3/Commercial/Industrial = 10, R1/R2 = 15
INCLUDES HALF BLDG 19 NE REAR &
BLDG 20 SE REAR
HYDROLOGY/HYDRAULIC CALCULATIONS
Project Address: McCutchen Commerce Center
JBC 1002.1Date:
9/9/2017
AREA NO.Pipe No. 9 Inflow Area BLDG 20 SOUTH PARKING
Given:
Site Designation:Light Industrial M-1
Develop Time of Concentration:Type of Flow = Open Channel - Paved
Tc base time (roof to gutter) 10
Elevation @ gutter or flowline/invert highpoint = 354.39
Elevation @ gutter or flowline/invert lowpoint = 352.62
Distance between high and low points = 87 feet
Average slope = 2.03%0.020 ft/ft
n factor 0.016 Concrete=0.013, AC Parking=0.016, AC Roads=0.018,
Proposed Pipe(feet) 150.00 Feet RipRap=0.030, Grassland=0.035
Velocity 8.2 fps
Travel Time = 0.2 minutes
Add overland flow 0.0 minutes (from C.O.B.Development Standards-2.3.2.1)
Tc = 10 minutes (base)+0.2 minutes (travel) + 0.0 minutes overland =10.2
Tc = 10.2 minutes
Develop Hydrology:
Q = cia Q=design runoff in cfs, c=runoff coefficient, i=intensity in inches/hr, a=area in acres
Given:
Storm Frequency:10 year - Local Waterway
c =0.9 from C.O.B.Development Standards-Plate D-2
i =1.80 from C.O.B.Development Standards-Plate D-1
a =0.3904 from hydrology plan
Calculate Q10 =0.63 cfs
Develop Hydraulic Calculations For Closed Conduit Pipe:
Pipe Analysis for 148 L.F. of 8 " PVC Pipe 8 (includes inflow from pipe 7)
invert elevation in-350.84
Q10 =0.63 cfs
Props'd Pipe(feet)0.67
Proposed Slope 0.006
n factor 0.011 (SDR 35 or equal)
Q = A(1.486/n)(R2/3*S1/2)
A= 0.352566
1.486/n= 135.0909
R2/3= 0.303862
S1/2= 0.075498
Q= (capacity) 1.09 cfs =58% full
invert elevation out-----350.00
Velocity
V = (1.486*R2/3*S1/2)/n
constant 1.486
R2/3= 0.303862
S1/2= 0.075498
Velocity= 3.1 fps
Conclusion:8 " Pipe @ 0.57 % OK
minutes (from C.O.B.Development Standards-2.3.2.1), Natural
Open = 0, R3/Commercial/Industrial = 10, R1/R2 = 15
PLUS HALF BLDG 19 NE REAR & BLDG 20
SE REAR
HYDROLOGY/HYDRAULIC CALCULATIONS
Project Address: McCutchen Commerce Center
JBC 1002.1Date:
9/9/2017
AREA NO.Pipe No. 10-12 Inflow Area
Given:
Site Designation:Light Industrial M-1
Develop Time of Concentration:Type of Flow = Open Channel - Paved
Tc base time (roof to gutter) 10
Elevation @ gutter or flowline/invert highpoint = 354.39
Elevation @ gutter or flowline/invert lowpoint = 353.18
Distance between high and low points = 170 feet
Average slope = 0.71%0.007 ft/ft
n factor 0.016 Concrete=0.013, AC Parking=0.016, AC Roads=0.018,
Proposed Pipe(feet) 0.00 Feet RipRap=0.030, Grassland=0.035
Velocity 4.8 fps
Travel Time = 0.6 minutes
Add overland flow 6.0 minutes (from C.O.B.Development Standards-2.3.2.1)
Tc = 10 minutes (base)+0.6 minutes (travel) + 6.0 minutes overland =16.6
Tc = 16.6 minutes
Develop Hydrology:
Q = cia Q=design runoff in cfs, c=runoff coefficient, i=intensity in inches/hr, a=area in acres
Given:
Storm Frequency:10 year - Local Waterway
c =0.9 from C.O.B.Development Standards-Plate D-2
i =1.75 from C.O.B.Development Standards-Plate D-1
a =0.32537 from hydrology plan
Calculate Q10 =0.51 cfs
Develop Hydraulic Calculations For Closed Conduit Pipe:
Pipe Analysis for 195 L.F. of 8 " PVC Pipe 10, 11, and 12
invert elevation in-350.68
Q10 =0.51 cfs
Props'd Pipe(feet)0.67
Proposed Slope 0.003
n factor 0.011 (SDR 35 or equal)
Q = A(1.486/n)(R2/3*S1/2)
A= 0.352566
1.486/n= 135.0909
R2/3= 0.303862
S1/2= 0.058992
Q= (capacity) 0.85 cfs =60% full
invert elevation out-----350.00
Velocity
V = (1.486*R2/3*S1/2)/n
constant 1.486
R2/3= 0.303862
S1/2= 0.058992
Velocity= 2.4 fps
Conclusion:8 " Pipe @ 0.35 % OK
minutes (from C.O.B.Development Standards-2.3.2.1), Natural
Open = 0, R3/Commercial/Industrial = 10, R1/R2 = 15
HYDROLOGY/HYDRAULIC CALCULATIONS
Project Address: McCutchen Commerce Center
JBC 1002.1Date:
9/9/2017
AREA NO.Pipe No. 13 BLDG 20 NORTH PARKING Inflow Area
Given:
Site Designation:Light Industrial M-1
Develop Time of Concentration:Type of Flow = Open Channel - Paved
Tc base time (roof to gutter) 10
Elevation @ gutter or flowline/invert highpoint = 353.94
Elevation @ gutter or flowline/invert lowpoint = 353.23
Distance between high and low points = 78 feet
Average slope = 0.91%0.009 ft/ft
n factor 0.016 Concrete=0.013, AC Parking=0.016, AC Roads=0.018,
Proposed Pipe(feet) 0.00 Feet RipRap=0.030, Grassland=0.035
Velocity 5.5 fps
Travel Time = 0.2 minutes
Add overland flow 0.0 minutes (from C.O.B.Development Standards-2.3.2.1)
Tc = 10 minutes (base)+0.2 minutes (travel) + 0.0 minutes overland =10.2
Tc = 10.2 minutes
Develop Hydrology:
Q = cia Q=design runoff in cfs, c=runoff coefficient, i=intensity in inches/hr, a=area in acres
Given:
Storm Frequency:10 year - Local Waterway
c =0.9 from C.O.B.Development Standards-Plate D-2
i =1.80 from C.O.B.Development Standards-Plate D-1
a =0.0888 from hydrology plan
Calculate Q10 =0.14 cfs
Develop Hydraulic Calculations For Closed Conduit Pipe:
Pipe Analysis for 14 L.F. of 8 " PVC Pipe 13
invert elevation in-350.53
Q10 =0.14 cfs
Props'd Pipe(feet)0.67
Proposed Slope 0.038
n factor 0.011 (SDR 35 or equal)
Q = A(1.486/n)(R2/3*S1/2)
A= 0.352566
1.486/n= 135.0909
R2/3= 0.303862
S1/2= 0.194422
Q= (capacity) 2.81 cfs =5% full
invert elevation out-----350.00
Velocity
V = (1.486*R2/3*S1/2)/n
constant 1.486
R2/3= 0.303862
S1/2= 0.194422
Velocity= 8.0 fps
Conclusion:8 " Pipe @ 3.78 % OK
minutes (from C.O.B.Development Standards-2.3.2.1), Natural
Open = 0, R3/Commercial/Industrial = 10, R1/R2 = 15
HYDROLOGY/HYDRAULIC CALCULATIONS
Project Address: McCutchen Commerce Center
JBC 1002.1Date:
9/9/2017
AREA NO.Pipe No. 14 FUT.BLDG 21 NE REAR PARKING Inflow Area
Given:
Site Designation:Light Industrial M-1
Develop Time of Concentration:Type of Flow = Open Channel - Paved
Tc base time (roof to gutter) 10
Elevation @ gutter or flowline/invert highpoint = 353.94
Elevation @ gutter or flowline/invert lowpoint = 352.62
Distance between high and low points = 69 feet
Average slope = 1.91%0.019 ft/ft
n factor 0.016 Concrete=0.013, AC Parking=0.016, AC Roads=0.018,
Proposed Pipe(feet) 0.00 Feet RipRap=0.030, Grassland=0.035
Velocity 7.9 fps
Travel Time = 0.1 minutes
Add overland flow 0.0 minutes (from C.O.B.Development Standards-2.3.2.1)
Tc = 10 minutes (base)+0.1 minutes (travel) + 0.0 minutes overland =10.1
Tc = 10.1 minutes
Develop Hydrology:
Q = cia Q=design runoff in cfs, c=runoff coefficient, i=intensity in inches/hr, a=area in acres
Given:
Storm Frequency:10 year - Local Waterway
c =0.9 from C.O.B.Development Standards-Plate D-2
i =1.80 from C.O.B.Development Standards-Plate D-1
a =0.0722 from hydrology plan
Calculate Q10 =0.12 cfs
Develop Hydraulic Calculations For Closed Conduit Pipe:
Pipe Analysis for 32.5 L.F. of 8 " PVC Pipe 14
invert elevation in-350.41
Q10 =0.12 cfs
Props'd Pipe(feet)0.67
Proposed Slope 0.002
n factor 0.011 (SDR 35 or equal)
Q = A(1.486/n)(R2/3*S1/2)
A= 0.352566
1.486/n= 135.0909
R2/3= 0.303862
S1/2= 0.044721
Q= (capacity) 0.65 cfs =18% full
invert elevation out-----350.35
Velocity
V = (1.486*R2/3*S1/2)/n
constant 1.486
R2/3= 0.303862
S1/2= 0.044721
Velocity= 1.8 fps
Conclusion:8 " Pipe @ 0.20 % OK
minutes (from C.O.B.Development Standards-2.3.2.1), Natural
Open = 0, R3/Commercial/Industrial = 10, R1/R2 = 15
HYDROLOGY/HYDRAULIC CALCULATIONS
Project Address: McCutchen Commerce Center
JBC 1002.1Date:
9/9/2017
AREA NO.Pipe No. 15 FUT BLDG 21 NE PARKING Inflow Area
Given:
Site Designation:Light Industrial M-1
Develop Time of Concentration:Type of Flow = Open Channel - Paved
Tc base time (roof to gutter) 10
Elevation @ gutter or flowline/invert highpoint = 353.85
Elevation @ gutter or flowline/invert lowpoint = 352.62
Distance between high and low points = 60 feet
Average slope = 2.05%0.021 ft/ft
n factor 0.016 Concrete=0.013, AC Parking=0.016, AC Roads=0.018,
Proposed Pipe(feet) 0.00 Feet RipRap=0.030, Grassland=0.035
Velocity 8.2 fps
Travel Time = 0.1 minutes
Add overland flow 0.0 minutes (from C.O.B.Development Standards-2.3.2.1)
Tc = 10 minutes (base)+0.1 minutes (travel) + 0.0 minutes overland =10.1
Tc = 10.1 minutes
Develop Hydrology:
Q = cia Q=design runoff in cfs, c=runoff coefficient, i=intensity in inches/hr, a=area in acres
Given:
Storm Frequency:10 year - Local Waterway
c =0.9 from C.O.B.Development Standards-Plate D-2
i =1.80 from C.O.B.Development Standards-Plate D-1
a =0.0803 from hydrology plan PLUS SUM AREAS PIPE 14&15
Calculate Q10 =0.13 cfs
Develop Hydraulic Calculations For Closed Conduit Pipe:
Pipe Analysis for 64 L.F. of 8 " PVC Pipe 15
invert elevation in-350.35
Q10 =0.13 cfs
Props'd Pipe(feet)0.67
Proposed Slope 0.005
n factor 0.011 (SDR 35 or equal)
Q = A(1.486/n)(R2/3*S1/2)
A= 0.352566
1.486/n= 135.0909
R2/3= 0.303862
S1/2= 0.073946
Q= (capacity) 1.07 cfs =12% full
invert elevation out-----350.00
Velocity
V = (1.486*R2/3*S1/2)/n
constant 1.486
R2/3= 0.303862
S1/2= 0.073946
Velocity= 3.0 fps
Conclusion:8 " Pipe @ 0.55 % OK
minutes (from C.O.B.Development Standards-2.3.2.1), Natural
Open = 0, R3/Commercial/Industrial = 10, R1/R2 = 15
HYDROLOGY/HYDRAULIC CALCULATIONS
Project Address: McCutchen Commerce Center
JBC 1002.1Date:
9/9/2017
AREA NO.PIPES 16-19 BLD 17-20 ROOF TO BASINS
Given:
Site Designation:Light Industrial M-1
Develop Time of Concentration:Type of Flow = Open Channel - Paved
Tc base time (roof to gutter) 10
Elevation @ gutter or flowline/invert highpoint = 370.39
Elevation @ gutter or flowline/invert lowpoint = 352.20
Distance between high and low points = 109 feet
Average slope = ######0.167 ft/ft
n factor 0.016 Concrete=0.013, AC Parking=0.016, AC Roads=0.018,
Proposed Pipe(feet) 0.00 Feet RipRap=0.030, Grassland=0.035
Velocity 23.4 fps
Travel Time = 0.1 minutes
Add overland flow 0.0 minutes (from C.O.B.Development Standards-2.3.2.1)
Tc = 10 minutes (base)+0.1 minutes (travel) + 0.0 minutes overland =10.1
Tc = 10.1 minutes
Develop Hydrology:
Q = cia Q=design runoff in cfs, c=runoff coefficient, i=intensity in inches/hr, a=area in acres
Given:
Storm Frequency:10 year - Local Waterway
c =0.9 from C.O.B.Development Standards-Plate D-2
i =1.80 from C.O.B.Development Standards-Plate D-1
a =0.21947 from hydrology plan PLUS SUM AREAS PIPE 14&15
Calculate Q10 =0.36 cfs
Develop Hydraulic Calculations For Closed Conduit Pipe:
Pipe Analysis for 12 L.F. of 8 " PVC Pipe 15
invert elevation in-352.22
Q10 =0.36 cfs
Props'd Pipe(feet)0.67
Proposed Slope 0.185
n factor 0.011 (SDR 35 or equal)
Q = A(1.486/n)(R2/3*S1/2)
A= 0.352566
1.486/n= 135.0909
R2/3= 0.303862
S1/2= 0.430116
Q= (capacity) 6.22 cfs =6% full
invert elevation out-----350.00
Velocity
V = (1.486*R2/3*S1/2)/n
constant 1.486
R2/3= 0.303862
S1/2= 0.430116
Velocity= 17.7 fps
Conclusion:8 " Pipe @ 18.50 % OK
minutes (from C.O.B.Development Standards-2.3.2.1), Natural
Open = 0, R3/Commercial/Industrial = 10, R1/R2 = 15
Page 12
C:\USERS\GMEND\DESKTOP\1002_1 PHASE 1 BLDG 18-20 DRAINAGE REPORT_9-14_17.DOCX
Exhibit G
NOTES:1. OVEREXCAVATE TO A DEPTH OF 11
F
E
E
T
B
E
L
O
W
E
X
I
S
T
I
N
G
G
R
A
D
E
A
N
D
B
A
C
K
F
I
L
L
T
O
E
L
E
V
A
T
I
O
N
350.00 WITH A MATERIAL APPROVE
D
B
Y
T
H
E
S
O
I
L
S
E
N
G
I
N
E
E
R
T
O
E
N
S
U
R
E
A
D
E
Q
U
A
T
E
P
E
R
M
E
A
B
I
L
I
T
Y
FOR WATER TO DRAIN IN SEVEN DA
Y
S
O
R
L
E
S
S
.
A
S
O
I
L
S
E
N
G
I
N
E
E
R
I
S
R
E
Q
U
I
R
E
D
T
O
B
E
O
N
S
I
T
E
D
U
R
I
N
G
CONSTRUCTION OF THE SUMP.2. PONDING BASINS NOT TO EXCEED 1
8
"
A
T
M
A
X
I
M
U
M
D
E
P
T
H
T
O
O
V
E
R
F
L
O
W
/
O
U
T
L
E
T
.
3. UPON COMPLETION OF THE CONST
R
U
C
T
I
O
N
O
F
T
H
E
B
A
S
I
N
,
T
H
E
S
O
I
L
S
E
N
G
I
N
E
E
R
S
H
A
L
L
P
R
O
V
I
D
E
T
H
E
CITY WITH WRITTEN VERIFICATION TH
A
T
T
H
E
R
E
Q
U
I
R
E
M
E
N
T
S
H
A
V
E
B
E
E
N
M
E
T
P
E
R
D
R
A
I
N
A
G
E
APPROVAL LETTER.4. THE RETENTION BASINS, ONSITE CAT
C
H
B
A
S
I
N
S
A
N
D
S
T
O
R
M
D
R
A
I
N
S
Y
S
T
E
M
S
H
A
L
L
B
E
M
A
I
N
T
A
I
N
E
D
PRIVATELY AND THE CITY OF BAKERS
F
I
E
L
D
W
I
L
L
N
O
T
A
S
S
U
M
E
R
E
S
P
O
N
S
I
B
I
L
I
T
Y
O
V
E
R
T
H
E
MAINTENANCE.
N
E
T
W
O
R
K
C
O
U
R
T
5
'
SIDESLOPES TO DAYLITE AT 5:1 MAX.POND SIDESLOPES AT 4:1 MAXADDITIONALSTORAGE-EXCEEDS REQUIRED100 YEAR REQUIREDSTORAGE MAX. OUTLET/OVERFLOW AT 351.50100 YEAR DWSAT 350.82
VARIES
PROP 6" WIDE x 1' DEEPCONC. MOW STRIP (TYP.)
P
R
O
P
8
"
P
V
C
B
A
S
I
N
I
N
T
E
R
T
I
E
,
L
E
V
E
L
@
I
N
V
E
R
T
3
5
0
.
0
0
BTM=350.00
F
F
=
3
5
4
.
3
9
3
5
3
.
2
8
F
S
H
P
P
R
O
P
.
F
S
O
V
E
R
S
T
O
R
M
D
R
A
I
N
3
5
2
.
6
2
T
G
3
5
3
.
0
6
F
L
H
P
3
5
2
.
6
2
T
G
P
R
O
P
.
8
"
P
V
C
P
R
O
P
.
C
A
T
C
H
B
A
S
I
N
P
R
O
P
.
C
A
T
C
H
B
A
S
I
N
P
R
O
P
.
8
"
P
V
C
B
T
M
=
3
5
0
.
0
0
P
R
O
P
.
3
4
'
W
I
D
E
P
R
I
V
A
T
E
D
W
Y
3
5
1
.
8
4
F
S
C
L
2
%
2
%
1
7
'
1
7
'
M
I
N
I
M
U
M
2
%
S
L
O
P
E
A
W
A
Y
F
R
O
M
B
U
I
L
D
I
N
G
I
N
F
I
R
S
T
5
F
E
E
T
.
A
P
P
L
I
E
S
T
O
A
L
L
S
I
D
E
S
O
F
B
U
I
L
D
I
N
G
.
(
T
Y
P
.
)
3
5
0
.
4
8
H
G
L
3
5
0
.
0
0
I
N
V
.
@
O
U
T
L
E
T
S
E
E
N
O
T
E
1
A
D
D
I
T
I
O
N
A
L
S
T
O
R
A
G
E
-
E
X
C
E
E
D
S
R
E
Q
U
I
R
E
D
1
0
0
Y
E
A
R
R
E
Q
U
I
R
E
D
S
T
O
R
A
G
E
P
O
N
D
S
I
D
E
S
L
O
P
E
S
A
T
4
:
1
M
A
X
M
A
X
.
O
U
T
L
E
T
/
O
V
E
R
F
L
O
W
A
T
3
5
1
.
5
0
1
0
0
Y
E
A
R
D
W
S
A
T
3
5
0
.
8
2
P
R
O
P
.
S
I
D
E
W
A
L
K
SEE NOTE 1 VARIES
3
5
0
.
0
0
P
O
N
D
E
D
G
E
3
5
0
.
0
0
P
O
N
D
E
D
G
E
B
U
I
L
D
I
N
G
1
8
-
2
0
EXHIBIT G
Page 13
C:\USERS\GMEND\DESKTOP\1002_1 PHASE 1 BLDG 18-20 DRAINAGE REPORT_9-14_17.DOCX
Exhibit I
EX
H
I
B
I
T
"
I
"
Page 14
C:\USERS\GMEND\DESKTOP\1002_1 PHASE 1 BLDG 18-20 DRAINAGE REPORT_9-14_17.DOCX
Exhibit J
4729 W. Jacquelyn Avenue
Fresno, CA 93722
Phone (559) 271-9700
Fax (559) 275-0827
SAN JOSE ▪ STOCKTON ▪ FRESNO ▪ BAKERSFIELD ▪ RANCHO CUCAMONGA
March 2, 2016 Project No. 2-212-0480
Mr. Jack Brey
JB Consulting Services, LLC
9519 Lake Superior Drive
Bakersfield, CA 93312
Subject: DESIGN MEMORANDUM- STORMWATER RETENTION BASINS
PROPOSED MCCUTCHEON & RELIANCE COMMERCIAL DEVELOPMENT
NEC MCCUTCHEON ROAD & RELIANCE DRIVE
BAKERSFIELD, CALIFORNIA
Dear Mr. Brey:
SALEM Engineering Group, Inc. (SALEM) is pleased to submit this Stormwater Retention Basin Design
Memorandum for the subject site located in Bakersfield, California. JB Consulting Services, LLC (JB)
authorized the scope of work in a March 1, 2016 communication.
1.0 PROJECT DESCRIPTION
SALEM previously conducted a Geotechnical Engineering Investigation Update for the above-noted
project summarized in our report dated November 18, 2015. On a preliminary basis, it is understood that
development will include the construction of 24 condominium type commercial structures. The structures
range in size from approximately 9,000 sq. ft. to approximately 18,000 sq. ft. and are anticipated to be
single or two story masonry structures utilizing conventional footings and slab-on-grade construction.
Distributed landscape areas will be designed to accept storm water run-off in lieu of the centralized storm
water retention area originally planned.
SALEM previously conducted several percolation tests at the project site. Testing data suggested the
proposed infiltration basins (as originally designed) would not meet the 7-day drain time requirement. As
such, our 2015 Geotechnical Engineering Investigation Update report proposed construction of infiltration
sumps (trenches) within the retention basin floor. The current drainage system design includes construction
of two to three approximately 40 foot long by 10 foot wide by 11 foot deep rock-filled trenches at the center
of the retention basins to allow rapid infiltration through a surficial, lower-permeability soil horizon into
more permeable underlying sediments.
2.0 ALTERNATE BASIN DESIGN RECOMMENDATIONS
Pertinent conclusions from our previous geotechnical investigations at the subject site include: Geotechnical soil boring logs from throughout the proposed development show that a moderately
permeable silty sand exists at depths of 3 to 5 feet below a lower-permeability sandy silt surface
soil.
Project No. 2-212-0480 Page 2 of 3
During 2012, SALEM conducted eight shallow percolation tests throughout the site. The tests were
conducted in both the sandy silt and underlying silty sand soil horizons. Testing results suggest the
silty sand unit is capable of absorption rates of at least 2 gal/ft2/day — a rate sufficient to allow the
planned basins to drain within 7 days.
SALEM recommended soil overexcavation of at least 12 inches below building footings that are at
least 18 inches below lowest adjacent grade.
SALEM is aware that a City of Bakersfield-approved mitigation method for slow infiltration rates in
stormwater basins includes the removal and replacement of lower permeability materials at the design basin
floor with materials with sufficient permeability to meet the 7-day drain time requirement.
As an alternative to the design recommendations in our 2015 report, SALEM recommends the following:
While conducting grading operations for the site building pads, continue overexcavation into the
lower silty sand unit and stockpile these soils. Excavate and stockpile sandy silt surficial soil from
the bottoms of proposed basins to a depth that penetrates into the lower silty sand unit.
Place and compact the lower permeability soils into the building pad excavation and bring to
planned grade. Place and compact the higher-permeability silty sand soil over the basin floor area.
The basin floor replacement soils should be placed in lifts, moisture conditioned to near optimum
moisture content, and compacted to between 90% to 92% relative compaction.
SALEM personnel should conduct adequate testing and observations during building pad
excavation and replacement of the basin floors to ensure that material properties meet the intent of
this alternative design recommendation.
Following completion of basin floor replacement, one percolation test for each 4 to 5 basins should
be conducted to verify the alternative design absorption rates.
3.0 LIMITATIONS
The analyses and recommendations submitted in this memorandum are based upon the data obtained from
previous test borings and percolation tests conducted by SALEM, and from data obtained from JB. The
memorandum does not reflect variations which may occur between test locations. The nature and extent of
such variations may not become evident until construction is initiated.
The findings and recommendations presented in this memorandum are valid as of the present and for the
proposed construction. If site conditions change due to natural processes or human intervention on the
property or adjacent to the site, or changes occur in the nature or design of the project, or if there is a
substantial time lapse between the submission of this report and the start of the work at the site, the
conclusions and recommendations contained in our report will not be considered valid unless the changes
are reviewed by SALEM and the conclusions of our report are modified or verified in writing. The validity
of the recommendations contained in this memorandum is also dependent upon an adequate testing and
observations program during the construction phase. Our firm assumes no responsibility for construction
compliance with the design concepts or recommendations unless we have been retained to perform the on-
site testing and review during construction. SALEM has prepared this memorandum for the exclusive use
of the owner and project design consultants.
Project No. 2-212-0480 Page 3 of 3
We appreciate the opportunity to submit this Design Memorandum. Should you have questions regarding
this proposal, please contact the undersigned at (559) 271-9700.
Respectfully submitted,
SALEM Engineering Group, Inc.
Bruce E. Myers, PE, CEG
Senior Engineer / Eng. Geologist
PE 62067 / CEG 2102