SWRCB, January 2002 Page of
Secondary Containment Testing Report Form
Thisform is intendedfor use by contractors performing periodic testing of USTsecondary containment systems. Use the
appropriate pages ofthis form to report resultsfor all components tested. The completedform, written test procedures, and
printouts from tests (ifapplicable), should be provided to thefacility owner /operator for submittal to the local regulatory agency.
1. FACILITY INFORMATION
Facility Name: Ramco Express Date of Testing: 12/29/2011
Facility Address: 2222 F Street Bakersfield, CA 93301
Facility Contact: Rami I Phone: 818- 339 -7288
Date Local Agency Was Notified of Testing: 12/1/2011
Name of Local Agency Inspector (rfpresent during testing): Ernie Medina
2. TESTING CONTRACTOR INFORMATION
Company Name: Confidence UST Services
Pass Fail
Technician Conducting Test: Bryan A Self
Repairs
Made Component
Credentials: x CSLB Licensed Contractor x SWRCB Licensed Tank Tester
Not
Tested
License Type: CSLB
87 STP Sump
License Number:804904
Manufacturer
Manufacturer Training
Component(s) Date Training Expires
Franklin Fueling TS -STS 1 -06 -2013
UST Service
technician
ICC 7 -5 -2013
Star. Smith. Fibercast Fiber Glass Systems N.A.
SWRCB Licensed Tank Tester 5/31/2014
3. SUMMARY OF TEST RESULTS
Component Pass Fail Not
Tested
Repairs
Made Component Pass Fail Not
Tested
Repairs
Made
87 STP Sump X
89 STP Sump X
91 STP Sump X
87 Annular X
89 Annular X
91 Annular X
UDC 1 -2 X
UDC 3 -4 X
If hydrostatic testing was performed, describe what was done with the water after completion of tests:
Water was nut back into test trailer and waste drum
CERTIFICATION OF TECHNICIAN RESPONSIBLE FOR CONDUCTING THIS TESTING
To the best ofmy knowledge, thefacts stated in this document are accurate and in full compliance with legal requirements
Technician's Signature:
SWRCB, January 2002 Page of
4. TANK ANNULAR TESTING
Test Method Developed By: Tank Manufacturer x Industry Standard Professional Engineer
Other (Spec)
Test Method Used: Pressure x Vacuum Hydrostatic
Other (Spec)
Test Equipment Used: Calibrated Gages Equipment Resolution:0.0625"
Tank # 87 Tank # 89 Tank # 91 Tank #
Is Tank Exempt From Testing ?' Yes X No Yes X No Yes X No Yes No
Tank Capacity: 10,000 10,000 10,000
Tank Material: FRP FRP FRP
Tank Manufacturer: O/C O/C O/C
Product Stored: 87 Annular Space 89 Annular Space 91 Annular Space
Wait time between applying
pressure /vacuum /water and
starting test:
5 Min 5 Min 5 Min
Test Start Time: 10:30 am 1:45 pm 2:55 pm
Initial Reading (Ri): 10 Hg 10 Hg 10 Hg
Test End Time: 11:30 am 2:45 pm 3:55 pm
Final Reading (RF): 10 Hg 10 Hg 10 Hg
Test Duration: 1 Hour 1 Hour I Hour
Change in Reading (RF -Ri): 0.00" 0.00" 0.00"
Pass /Fail Threshold or Criteria: 0.00, 0.00" 0.00"
Test Result: X Pass Fail X Pass Fail X Pass 0 Fail Pass Fail
Was sensor removed for testing? X Yes No NA X Yes No NA X Yes No NA Yes No NA
Was sensor properly replaced and
verified functional after testing? X Yes No NA X Yes No NA X Yes No NA Yes No NA
Comments — (include information on repairs made prior to testing, and recommendedfollow -upforfailed tests)
Secondary containment systems where the continuous monitoring automatically monitors both the primary and secondary
containment, such as systems that are hydrostatically monitored or under constant vacuum, are exempt from periodic containment
testing. {California Code of Regulations, Title 23, Section 2637(a)(6)1
SWRCB, January 2002
6. PIPING SUMP TESTING
Page of
Test Method Developed By: Sump Manufacturer x Industry Standard Professional Engineer
Other (Specif
Test Method Used: Pressure Vacuum x Hydrostatic
Other (Specify)
Test Equipment Used: Ts -sts Equipment Resolution:
Sump # 87 STP Sump # 89 STP Sump # 91 STP Sump #
Sump Diameter: 37.00" 37.00" 37.00"
Sump Depth: 48.00" 48.00" 48.00"
Sump Material: FRP FRP FRP
Height from Tank Top to Top of
Highest Piping Penetration: 22.00" 27.00" 26.00"
Height from Tank Top to Lowest
Electrical Penetration: 11.00" 11.00" 11.00"
Condition of sump prior to testing: Clean & Dry Clean & Dry Clean & Dry
Portion of Sump Tested' Pipe Penetration Pipe Penetration Pipe Penetration
Does turbine shut down when
sump sensor detects liquid (both
product and water) ?*
X Yes No NA X Yes No
NA
X Yes No
NA Yes No NA
Turbine shutdown response time 7 Seconds 7 Seconds 7 Seconds
Is system programmed for fail -safe
shutdown?*
X Yes No NA X Yes No NA X Yes No NA Yes No NA
Was fail -safe verified to be
operational'?*
X Yes No NA X Yes No NA X Yes No NA Yes No NA
Wait time between applying
pressure /vacuum /water and starting
test:
5 Min 5 Min 5 Min
Test Start Time:
Initial Reading (Ri):
Test End Time: 99 MON
Final Reading (RF):
Test Duration: Results
Change in Reading (R,: -R,):
Pass/Fail Threshold or Criteria:
Test Result: X Pass Fail X Pass Fail X Pass Fail Pass Fail
Was sensor removed for testing'? X Yes No NA X Yes No NA X Yes No NA Yes No NA
Was sensor properly replaced and
verified functional after testing'? X Yes No NA X Yes No NA X Yes No NA Yes No NA
Comments — (include information on repairs made prior to testing, and recommendedfollow -up forfailed tests)
If the entire depth of the sump is not tested, specify how much was tested. If the answer to any of the questions indicated with an
asterisk(*) is "NO" or "NA ", the entire sump must be tested. (See SWRCB LG -160)
raa,oca+tata *.vr,ufla bv a..
ViOMPH
SWRCB, January 2002
7. UNDER - DISPENSER CONTAINMENT C TESTING
Page of
Test Method Developed By: UDC Manufacturer x Industry Standard Professional Engineer
Other (Specify)
Test Method Used: Pressure Vacuum x Hydrostatic
Other (Spec)
Test Equipment Used: Ts -sts Equipment Resolution:
UDC # 1 -2 UDC # 3 -4 UDC # UDC #
UDC Manufacturer: Bravo Box Bravo Box
UDC Material: Bravo Box Bravo Box
UDC Depth: 10.00" 10.00"
Height from UDC Bottom to Top
of Highest Piping Penetration:
Bottom of UDC Bottom of UDC
Height from UDC Bottom to
Lowest Electrical Penetration:
Bottom of UDC Bottom of UDC
Condition of UDC prior to
testing:
Clean Clean
Portion of UDC Tested Pipe Penetration Pipe Penetration
Does turbine shut down when
UDC sensor detects liquid (both
product and water) ?*
Yes No X NA Yes No X NA Yes No NA Yes No NA
Turbine shutdown response time N.A. N.A.
Is system programmed for fail-
safe shutdown ?*
Yes No X NA Yes No X NA Yes No NA Yes No NA
Was fail -safe verified to be
operational?*
Yes No X NA Yes No X NA Yes No NA Yes No NA
Wait time between applying
pressure /vacuum /water and
starting test
5 Min 5 Min
Test Start Time:
Initial Reading (Ri): See 1. CON
Test End Time:
Final Reading (RF): Res dthop
Test Duration:
Change in Reading (RF -Ri):
Pass /Fail Threshold or Criteria:
Test Result: X Pass Fail X Pass Fail Pass Fail Pass Fail
Was sensor removed for testing? Yes No X NA Yes No X NA Yes No NA Yes No NA
Was sensor properly replaced and
verified functional after testing? Yes No X NA Yes No X NA Yes No NA Yes No NA
Comments — (include information on repairs made prior to testing, and recommendedfollow -upforfailed tests)
1 If the entire depth of the UDC is not tested, specify how much was tested. Ifthe answer to any of the questions indicated with an
asterisk ( *) is "NO" or "NA ", the entire UDC must be tested. (See SWRCB LG -160)
r-4fwl--Vnjr4---,um--,-.i(WI-Mlipty:ZEAX7711-76 I
MOOWI 9,16
SWRCB, January 2002
8. FILL RISER CONTAINMENT SUMP TESTING
Page of
Facility is Not Equipped With Fill Riser Containment Sumps X
Fill Riser Containment Sumps are Present, but were Not Tested
Test Method Developed By: Sump Manufacturer Industry Standard Professional Engineer
Other (Specify)
Test Method Used: Pressure Vacuum Hydrostatic
Other (Specify)
Test Equipment Used: Equipment Resolution:
Fill Sump # Fill Sump # Fill Sump # Fill Sump #
Sump Diameter:
Sump Depth:
Height from Tank Top to Top of
Highest Piping Penetration:
Height from Tank Top to Lowest
Electrical Penetration:
Condition of sump prior to
testing:
Portion of Sump Tested
Sump Material:
Wait time between applying
pressure /vacuum /water and
starting test:
Test Start Time:
Initial Reading (R,):
Test End Time:
Final Reading (RF):
Test Duration:
Change in Reading (RF -R,):
Pass /Fail Threshold or Criteria:
Test Result: Pass Fail Pass Fail Pass Fail Pass Fail
Is there a sensor in the sump? Yes No Yes No Yes No Yes No
Does the sensor alarm when
either product or water is
detected?
Yes No NA Yes No NA Yes No NA Yes No NA
Was sensor removed for testing? Yes No NA Yes No NA Yes No NA Yes No NA
Was sensor properly replaced and
verified functional after testing? Yes No NA Yes No NA 11 Yes No NA Yes No NA
Comments — (include information on repairs made prior to testing, and recommendedfollow -upforjailed tests)
SWRCB, January 2002
9. SPILL /OVERFILL CONTAINMENT BOXES
Page of
Facility is Not Equipped With Spill /Overfill Containment Boxes
Spill /Overfill Containment Boxes are Present, but were Not Tested X
Test Method Developed By: Spill Bucket Manufacturer x Industry Standard Professional Engineer
Other (Spec)
Test Method Used: Pressure Vacuum x Hydrostatic
Other (Spec)
Test Equipment Used: Ts -sts Equipment Resolution:
Spill Box # Spill Box # Spill Box # Spill Box #
Bucket Diameter:
Bucket Depth:
Wait time between applying
pressure /vacuum /water and
starting test:
Test Start Time:
Initial Reading (R,):
Test End Time:
Final Reading (RF):
Test Duration:
Change in Reading (RF -R,):
Pass /Fail Threshold or
Criteria:
Test Result: Pass Fail Pass Fail Pass Fail Pass Fail
Comments — (include information on repairs made prior to testing, and recommendedfollow -upforfailed tests)
The Spill Buckets Are Tested With The Annuel Monitor Cert.
RAMCO EXPRESS RAMCD EXPRESS RAh1CO EXPRESS
2222 F STREET 2222 F STREET 2222 F STREET
BAKERSFIELD CA BAKERSFIELD CA BAKERSFIELD,CA
28203 28203 28203
12/29/2011 11 :15 AM 12/29/2011 11:32 AM 12/29/2011 12:ao PM
SUMP LEAK TEST REPORT SUMP LEAK TEST REPORT SUMP LEAK TEST REPORT
UDC 1 -2 UDC 1 -2 87 SIP
TEST STARTED 1100 AM TEST STARTED 11:16 AM TEST STARTED 12 :25 PM
TEST STARTED 12/29/2011 TEST STARTED 1212912011 TEST STARTED 12/29/2011
8EGlN LEVEL 1.0084 IN BEGIN LEVEL 1,0064 IN BEGIN LEVEL 4.1591 1N
END TIME 11:15 AM END TIME 11:31 AM END TIME 12:40 Pli
END DATE 12/29/2011 END DATE 12129/2011 END DATE 12/29!2011
END LEVEL 1.0077 IN END LEVEL 1,0058 IN END LEVEL 4.1576 IN
LEAK THRESHOLD 0.002 111 LEAK THRESHOLD 0.002 IN LEAK THRESHOLD 0.002 IN
TEST RESULT PASSED TEST RESULT PASSED TEST RESULT PASSED
UDC 3 -4 UDC 3-4
TEST STARTED 11:00 AM TEST STARTED 11:16 AM
TEST STARTED 12/29/2011 TEST STARTED 12/29/2011
BEGIN LEVEL 1,5769 IN BEGIN LEVEL 1.5758 IN
END TIME 11:15 AM FND TIME 11.31 AM
END DATE 12/29/2011 END DATE 12/29/2011
END LEVEL 1.5760 1N END LEVEL 1.5750 IN
LEAK THRESHOLD 0.002 IN LEAK THRESHOLD 0,002 IN
TEST RESULT PASSED TEST RESULT PASSED
91 STP
1ST SiAR1EL !2:49 PM
IEST STIJAED
BFI,Iti t.['vn. 2..-,514 IN
END TIME 1:04 PM
DO OP it 12129120'1
EtIO LEVEL 2,8566 IN
IFAK THRESHOLD 0.002. IN
IES1 RESULT PASSED
s
RAMCO EXPRESS
2222 F STRIET
BAKERSFIELO CA
28203
12/29/2011 1:47 PM
SUMP LEAK TEST REPORI
85 STP
TES1 STARTED i:32 PM
1F.S7 STARTED 12/29/2011
BEGIN 1 EVEL 3, a364 IN
END TIME 1:47 PM
END DATE 12/29/2011
END LEVEL 3.4356 IN
LEAK INRESHOLU O. 002 11
TEST RESULT PASSED
89 SIP
TES' STARTED 1:32 PM
TEST STARTED 12/29/2011
BEGIN LEVEL 4,1320 IN
END TIME 1:47 PM
END DATE 12/29/2011
END LEVEL 4, 1322 IN
LEAH: II;RESHOLD 0.002 IN
TEST RESULT PASSED
0 ,
RAMCG E*.P(IS; RAMCO EKKESS
2222 r SIREFT 2222 E STRFET
BAKERSFIELD CA BAKERSFIELD CA
2 °203 28203
12/29/2011 1:04 PM 12/25/2011 1:24 PM
SI-J1, LEA.t TES' REF'bki SUM[' LEAH TEST REPORT
8? SIP 91 STP
5' S, FI , 1 "t: 4'i +n TES! STARTED 1:09 PM
L`' SrN =iE 2;rillr'1t EST STARTED 1212`J12011
flud:I 1EUF1_ 0, imo III BEGIN LEvEI. 2. '659 1N
E11Ii I[ME 1:04 pM END FIME 1:24 PM
1,110 1141E ;1:23/2011 END DATE 12/29/2011
Et:G EVLL 4, i5l'15 IN END LEVEL 2.8545 IN
An HPEaiUIG 0.002 iN LEAF, THRESHOLD 0.002 IN
1ESi kESULi PASSED IEST RESULT PASSED
91 STP
1ST SiAR1EL !2:49 PM
IEST STIJAED
BFI,Iti t.['vn. 2..-,514 IN
END TIME 1:04 PM
DO OP it 12129120'1
EtIO LEVEL 2,8566 IN
IFAK THRESHOLD 0.002. IN
IES1 RESULT PASSED
s
RAMCO EXPRESS
2222 F STRIET
BAKERSFIELO CA
28203
12/29/2011 1:47 PM
SUMP LEAK TEST REPORI
85 STP
TES1 STARTED i:32 PM
1F.S7 STARTED 12/29/2011
BEGIN 1 EVEL 3, a364 IN
END TIME 1:47 PM
END DATE 12/29/2011
END LEVEL 3.4356 IN
LEAK INRESHOLU O. 002 11
TEST RESULT PASSED
89 SIP
TES' STARTED 1:32 PM
TEST STARTED 12/29/2011
BEGIN LEVEL 4,1320 IN
END TIME 1:47 PM
END DATE 12/29/2011
END LEVEL 4, 1322 IN
LEAH: II;RESHOLD 0.002 IN
TEST RESULT PASSED
0 ,