ELD Test Date:
Customer:
Location:
Tested By: CGRS, Inc.
5444 Dry Creek Road
Sacramento, CA 95838
Project No:61-21735
Tanknology
7-Eleven #38837
11000 N. MoPac Expressway #500
Austin, TX 78759
3698 Ming Ave.
Bakersfield, CA 93309
June 15, 2020
®
Location:CGRS Project No :
Test Date:
CGRS Techs:
IOTA Tech Signature:
Sergio L. Nunez CA Tank Tester #06-1727
Reviewed by:
Chris Murphy Director of CA Services
6/16/2020
Date
Diesel Primary Containment System PASS
6/15/2020
Date
87 Octane TK2 Primary Containment System PASS
91 Octane Primary Containment System PASS
Post Installation ELD Test Results
87 Octane TK1 Primary Containment System PASS
3698 Ming Ave.Sergio L. Nunez
Bakersfield, CA 93309
Test Certification
Post Installation Enhanced Leak Detection (ELD)
61-21735
7-Eleven #38837 June 15, 2020
This document certifies that the UST systems listed below at the above referenced location have been tested
and passed the iota®VaporTite V005 tightness test and iotaVision™L005.CGRS further certifies that the
iota®VaporTite V005 and iotaVision™L005 meets the post installation testing requirements for post
installation testing for newly installed underground storage tank systems as per the California Health and
Safety Code,Chapter 6.7,section 25290.1(j)(1).
Final Test Date:IOTA Technicians:
Site Information Installation Contractor Information
Facility:Customer Name/CA Contractor's License #:
Address:Address:
City, State, Zip:City, State, Zip:
County:Contact:
CUPA Contact:Phone/Email:
CUPA Email:
Tank No.Capacity (gal.)Product Type Manufacturer Brine Test Result
Tank 1 12,000 87 Octane TK1 DW Fiberglass Xerxes Yes PASS
Tank 2 12,000 87 Octane TK2 DW Fiberglass Xerxes Yes PASS
Tank 3 12,000 91 Octane DW Fiberglass Xerxes Yes PASS
Tank 4 10,000 Diesel DW Fiberglass Xerxes Yes PASS
Tank Top Sumps Diameter (in.)Depth (in.)Volume (gal.)Description Test Result
S1 48 60 470.01 87 TS1 PASS
S2 42 60 359.86 87 FS2 PASS
S3 48 60 470.01 87 TS2 PASS
S4 42 60 359.86 87 FS2 PASS
S5 48 60 470.01 91 TS PASS
S6 42 60 359.86 91 FS PASS
S7 48 60 470.01 DSL TS PASS
S8 42 60 359.86 DSL FS PASS
Junction Boxes with Tank Connection Description Test Result
S1 Tank Probe and Turbine J-Box Open During Test PASS
S3 Tank Probe and Turbine J-Box Open During Test PASS
S5 Tank Probe and Turbine J-Box Open During Test PASS
S7 Tank Probe and Turbine J-Box Open During Test PASS
UDCs Length (in.)Width (in.)Depth (in.)Volume (gal.)Description Test Result
UDC1 36 18 28 78.55 OPW PASS
UDC2 36 18 28 78.55 OPW PASS
UDC3 36 18 28 78.55 OPW PASS
UDC4 36 18 28 78.55 OPW PASS
Transition Sump Length (in.)Width (in.)Depth (in.)Volume (gal.)Description Test Result
TS1 24 22 32 73.14 Bravo PASS
Product Piping Manufacturer Type Size (in.)Length (ft.) Test Result
87 PL1 NOV DW Fiberglass 2 250 PASS
87 PL2 NOV DW Fiberglass 2 10 PASS
91 PL NOV DW Fiberglass 2 195 PASS
DSL PL NOV DW Fiberglass 2 145 PASS
Vent Piping Manufacturer Type Size (in.)Length (ft.)Test Result
87 TK1 Vent NOV DW Fiberglass 2 45 PASS
87 TK2 Vent NOV DW Fiberglass 2 60 PASS
91 Vent NOV DW Fiberglass 2 90 PASS
DSL Vent NOV DW Fiberglass 2 90 PASS
Vapor Piping Manufacturer Type Size (in.)Length (ft.)Test Result
VR NOV DW Fiberglass 3 275 PASS
Reviewed By Date IOTA Tech Signature Date
6/15/2020
CA License No.
6/16/2020 06-1727
3698 Ming Ave.4583 E. Eisenhower Circle
Anaheim, CA 92807
COMPONENTS IN CONTAINMENT
Kern Gary Redfern
Bakersfield FD; Howard Wines; Kris Karns 714-497-5812/gredfern@rdbuilders.com
Leak Logs / Repair
Bakersfield, CA 93309
kkarns@bakersfieldfire.us; hwines@bakersfieldfire.us
PIPING
TANKS
Final ELD Test Project Worksheet
6/15/2020
7-Eleven #38837 RD Builders
Sergio L. Nunez
Location:CGRS Project No :
Test Date:
CGRS Techs:
IOTA Tech Signature:
Sergio L. Nunez CA Tank Tester #06-1727
Reviewed by:
Chris Murphy Director of CA Services
Secondary Flow Communication Test Certification
61-21735
7-Eleven #38837 June 15, 2020
3698 Ming Ave.Sergio L. Nunez
Bakersfield, CA 93309
COMPONENTS RESULTS
Piping Secondary Communication Confirmation
87 PL PASS
91 PL PASS
6/16/2020
Date
DSL PL PASS
6/15/2020
Date
VR PASS
DSL Vent PASS
87 Vent PASS
91 Vent PASS
CGRS certifies that at the time the final ELD testing was performed, air flow communication was confirmed
throughout the secondary piping components listed below.