HomeMy WebLinkAboutJBI Oaks - WorkplanWorkplan for Jeffries Bros. Brookside at the Oaks
Facility: Jeffries Bros. Brookside at the Oaks
8803 Camino Media
Bakersfield, CA. 93311
Contractor: Cal Valley Equipment
7608 Fruitvale Avenue
Bakersfield, CA. 93308
License: 998733 A, Haz
Contact:
Jerry Rangel
Office: (661) 327-9341
Cell: (661) 979-0953
Email: jerryr@calvalley.com
Scope of work:
Remove and replace all dispensers, UDCs, product piping, vapor return piping, and
conduit from dispensing area under canopy to UST piping sumps. Replace the
existing Veeder Root TLS-350 with a new TLS-450.
Permit number:
Bakersfield Fire Department: 23-10000909
Proposed timeline:
*Depending on dispenser shipping date, 8-12 week estimate from manufacturer
May 1st: Close site, remove fuel island equipment, and blow back lines to the USTs.
May 6th – 10th: Sawcut, breakout, and remove concrete.
May 13th – 17th: Excavate and remove existing UDCs and piping. Conduct soil sampling as
required.
May 20th -24th: Set UDCs, run conduit, and install TLS.
May 27th – June 7th: Install UDC fittings, run Brugg piping, connect to existing turbines.
Perform primary and secondary backfill inspections and testing.
June 10th – 21st: Backfill, concrete, and concrete cure time.
June 24th – 28th: Set dispensers, purge, and calibrate.
July 1st – 5th: Perform final testing with BFD and SJVAPCD
Sign: _____________________________________ Date: ______________ 02/07/24