HomeMy WebLinkAboutRES NO 052-2024 RESOLUTION NO. 052 - 2024
RESOLUTION DISPENSING WITH BIDDING UNDER
SECTION 3.20.060(D)(5) OF THE BAKERSFIELD
MUNICIPAL CODE RELATING TO DESIGN/BUILD
CONSTRUCTION PROCUREMENT PROCESS FOR THE
SORTING LINE AT THE MATERIALS RECOVERY
FACILITY (MRF).
WHEREAS, the sorting line at the Materials Recovery Facility (MRF) located
at 2260 South Union Avenue needs to be updated and modernized; and
WHEREAS, the use of design/build methodologies has been shown to be an
effective method of reducing construction costs; and
WHEREAS, the use of design/build joins the construction and design of a
project under one single legal entity thereby reducing conflicts; and
WHEREAS, the City Council believes the use of design/build is appropriate
for certain unique projects where specialized design or construction methods are
necessary or special design expertise must be employed,- and
WHEREAS, the City Council believes the public and the procurement
process can be adequately protected through the use of a fair competitive
process for choosing a design/build entity which best serves the interests of the
City.
NOW, THEREFORE, BE IT RESOLVED, by the Council of the City of Bakersfield
as follows:
1 The above recitals are true and correct and incorporated herein by
reference.
2. The sorting line at the MRF is appropriate for design/build because of
the specialized nature of the design and construction of the project.
3. The sorting line of the MRF justifies exception to the bidding process
and the City Council hereby determines that the work, supplies
equipment and material can best be obtained through the
design/build construction procurement process.
4. Upon adoption of this Resolution, the Public Works Director is
authorized to proceed with the design/build procurement process,
as set forth in the Bakersfield Municipal Code Section 3.20.060(D)(5),
for the sorting line of the MRF project.
-Page 1 of 2 Pages-
5. The Public Works Director shall recommend a design/build entity that
combines appropriately licensed contracting, architectural and
engineering services, as needed, into one legal entity.
6. The Public Works Director shall invite no less than three appropriate
design/build entities to participate in the selection process.
7. The Public Works Director shall, in a timely manner, bring the contract
for award of the project to the City Council for approval with a report
setting forth the reasons the award is recommended to the chosen
design/build entity.
I HEREBY CERTIFY that the foregoing Resolution was passed and adopted
by the Council of the City of Bakersfield of a regular meeting thereof held on
APR 1; 2024 by the following vote:
ay- COUNCIL MEMBER-ARI-A-3,GONZALES,WEIRrSMITH,FREEMAN GrAY,KKR
NOES: COUNCIL MEMBER
ABSTAIN: COUNCIL MEMBER
�BS 7E�p COUNCIL MEMBER
/11 x
)JULIE DRIMAKI!�,,Mmi �
City Clerk and Ex Officio Clerk of the
x
Council of the City of Bakersfield
APPROVED APP% t 2024
w
By d4jpw 4" 1
KAREN GOR
Mayor
APPROVED AS TO FORM:
VIRGINIA GENNARO
City Attorney
By
0 OSH RUDNICK
Deputy City Attorney
jz"
-Page 2 of 2 Pages-