HomeMy WebLinkAboutZC No. 22-0025PJ: VMS:\15_Zone Change\01_Active\2022\22-0025 (75 E. White & 2572 S. Union)\01_Hearing & Noticing Documents\Draft\01_ZC 22-0025_Staff
Report.Docx
CITY OF BAKERSFIELD
PLANNING COMMISSION
STAFF REPORT
MEETING DATE: October 3, 2024 AGENDA CATEGORY: 5.b
TO: Chair and Members of the Planning Commission
FROM: Paul Johnson, Planning Director
DATE: September 27, 2024
FILE: Zone Change No. 22-0025
STAFF PLANNER: Veronica Martinez, Assistant Planner
REQUEST: Zone change to change the zone classification from M-3 (Heavy Industrial) to M-2 (General
Manufacturing) in order to allow the continued operation of a trucking yard.
APPLICANT: Swanson Engineering, Inc. OWNER: FBT, Inc.
Attn: Bob Swanson Dave Laut
2000 Oak Street, Suite 150 2572 S. Union Ave
Bakersfield, CA 93301 Bakersfield, CA 93307
LOCATION: 75 E. White Lane & 2572 S. Union Avenue APN: 172-140-05; 172-160-14
PROJECT SIZE: 69 acres CEQA: Mitigated Negative Declaration
STAFF RECOMMENDATION: (1) Adopt Resolution ADOPTING Mitigated Negative Declaration pursuant to
Section 15074 of the California Environmental Quality Act; (2) Adopt Resolution APPROVING the change
in zone classification from M-3 to M-2 and recommend same to City Council.
SITE CHARACTERISTICS: The project site is partially developed with an existing trucking yard. Surrounding
properties are developed as north – the Bakersfield Municipal Airport and industrial uses; east – industrial
development; south – existing trucking yard; and west – trucking yard and commercial development.
BACKGROUND AND TIMELINE:
•May 31, 1978 – The site was annexed to the City of Bakersfield. This project site was included as
a portion of this annexation area (Annexation 261).
•November 17, 1999 – The City Council approved change of the zone classification of 3,461 acres
generally located between E. Brundage Ln and E. Pacheco Rd, Mt. Vernon Ave on the east and the
majority of parcels with frontage lying on the west side of S. Union Ave on the west from the
existing Casa Loma Specific Plan designation to RS-2.5, RS, E, R-2, R-3, C-2, M-1, M-2, M-3, and OS
~
BAKERSFIELD
TI-E SOOIO OF~ &I,,
Zone Change No. 22-0025
zones (Ordinance 3935).
•August 11, 2009 – The Board of Zoning Adjustment approved a Conditional Use Permit to operate
a concrete and asphalt recycling facility on a portion of the 69-acre site. The development was
not completed and has since expired (Conditional Use Permit No. 09-0315).
•January 14, 2022 – A site plan review application was received simultaneously with Zone Change
No. 22-0025 to allow the expansion of the existing truck yard consisting of 1,202 trucking yard
spaces and 418 car passenger-vehicle spaces.
•May 23, 2023 – A code violation was issued for the property due to the unauthorized operation
of a trucking yard without the necessary entitlement approvals (23-4813).
PROJECT ANALYSIS:
Zone Change. The proposed zone change from M-3 (Heavy Industrial) to M-2 (General Manufacturing)
will facilitate the continued operation of a trucking yard consisting of 1,202 truck parking spaces and 418
car passenger-vehicle spaces. A trucking yard is listed as a permitted use in the M-2 zone pursuant to
the City of Bakersfield Municipal Code but is not listed as a permitted use in the M-3 zone.
The applicant requests a zone change to allow the continued operation of a trucking yard on
approximately 69 acres. The development will also consist of 2 (two) commercial coaches for security
and a site manager. The property will be paved for truck storage and drive aisles. Ingress and egress to
the site will be provided from E. White Lane and S. Union Avenue. The facility will be open 24 hours a
day, 7 days a week.
Site Plan Review. If the zone change is approved to M-2 as requested, an application for site plan
approval is required. A Site Plan Review (No. 22-0026) is also being processed as a ministerial action.
Pursuant to BMC Section 17.08.060, no construction of any improvements which requires a building
permit for renovation of improvements shall be permitted without first obtaining site plan approval. The
proposed truck yard has been through a preliminary review by the Site Plan Review (SPR) Committee, as
listed below, for compliance with City development standards. The Development Services Director may
then approve, conditionally approve, or deny the site plan. There is no requirement for Planning
Commission consideration unless the Development Services Director’s decision is appealed.
• Development Services Department/Building Division
• Development Services Department/Planning Division
• Fire Department
•Water Resources
• Public Works Department/Engineering Division
• Public Works Department/Traffic Division
• Public Works Department/Solid Waste Division
• Recreation and Parks Department (as needed)
Compatibility with Land Use Element. Staff has reviewed the proposal for compatibility with the
applicable goals and policies contained within the Metropolitan Bakersfield General Plan Land Use
Element and finds the following:
•Policy 31. Allow for a variety of industrial uses, including land-extensive mineral extraction
and processing, heavy manufacturing, light manufacturing, warehousing and
distribution, transportation-related, and research and development uses.
The project is consistent with a variety of industrial uses such as transportation-related uses for
trucks. Therefore, the proposal is consistent with Policy 31.
•Policy 38. Minimize impacts of industrial traffic on adjacent residential parcels through the
use of site plan review and improvement standards.
The project is required to obtain a site plan review that adheres to the City's standards and
guidelines. Therefore, the proposal is consistent with Policy 38.
•Policy 75. Provide adequate land area for the expansion of existing uses and development of new
uses consistent with the policies of the general plan.
The project site is located on existing industrial land near industrial land uses. Therefore, adequate
land is available for the project, and the project expands existing industrial land. Therefore, the
project is consistent with Policy 75.
ENVIRONMENTAL REVIEW AND DETERMINATION:
In accordance with the California Environmental Quality Act (“CEQA”), Staff prepared an initial study to
review the potential environmental impacts of the project. The Initial Study was based on the following
project-specific analysis and technical studies: Air Quality Assessment; Biological Resources Study; Phase
I Cultural Resource Survey; and Traffic study with Vehicle Miles Traveled Analysis.
The Initial Study determined that compliance with the recommended mitigation measures, local
ordinances, state laws, and construction to the standards of the Uniform Building Codes will reduce
impacts to a less-than-significant level. Therefore, a Mitigated Negative Declaration (“MND”) was
prepared for this project in accordance with CEQA. The MND was circulated for a 30-day public and agency
review period from June 21, 2024, to July 22, 2024 (SCH No. 2024060954), and no comments were
received.
Comments Received. As of this writing, no public or agency comments have been received in response to
the Initial Study.
PUBLIC NOTIFICATION:
Public notice for the proposed project and environmental determination was advertised in The Bakersfield
Californian and posted on the bulletin board in the City of Bakersfield Development Services Building,
1715 Chester Avenue, Bakersfield, California. All property owners within 300 feet of the project site were
notified by United States Postal Service mail regarding this public hearing in accordance with city
ordinance and state law. Signs are required as part of the public notification process and must be posted
between 20 to 60 days before the public hearing date. Photographs of the posted signage and the
Declaration of Posting Public Hearing Notice signed by the applicant are on file at the Planning Division.
Comments Received. As of this writing, no written public comments have been received in response to
the public notice.
CONCLUSIONS:
Consistency with General Plan and Zoning Ordinance. The proposal is consistent with land use goals and
Zone Change No. 22-0025
Zone Change No. 22-0025
policies as contained in the General Plan, which encourages continuity of existing development and allows
incremental expansion of infrastructure. Additionally, the project would encourage infill of a vacant
expansion area. As noted above, any future development will comply with all applicable regulations and
design standards as identified in the Zoning Ordinance.
Recommendation. Staff finds that the applicable provisions of CEQA have been complied with, and the
proposal is compatible with the existing land use designation and land uses in the surrounding area. Based
on information in the record, Staff recommends your Commission: (1) Adopt Resolution ADOPTING a
Mitigated Negative Declaration pursuant to the California Environmental Quality Act; (2) adopt Resolution
APPROVING the zone change from M-3 (Heavy Industrial) to M-2 (General Manufacturing) and
recommend same to City Council.
ATTACHMENTS:
Map Set
•Aerial
•Zone Classification
•General Plan Designation
Mitigated Negative Declaration with Attachments
Planning Commission Draft Resolution
•Adopt MND with Attachments
•Approve ZC with Attachments
MAP SET
ZONE CHANGE
22-0025
AERIAL
I:"! ~
BAKERSFIELD
t
Feet
0 500 1,000
MAP PACKAGES
ZONE CHANGE
22-0025
CITY OF BAKERSFIELD
I 'I I '\ ·-·h II I \
'
~i ~ ...... -...... -< ;. _______ _
··-··-··-··~
M-1 ! [·-··-··-··-··-••iiiP .
. .
M-1
PAEHEE0
M-1
.
() ..
0~
C: iQ ~:--; --; I-< -< : !
M-1
R-2
R-2
R-1
Zone CLR
Commercial Zone Designations
-C-2 Regional
-Commercial
Industrial Zone Designations
-M-llight
-Manufacturing
~ M-3 Heavy Industrial
Residential Zone Designations
R-S-2.5A Residential
~ Suburban -2.5 acre
minimum
11 R-1 One Family
I I Dwelling
R-2 Limited Multiple [=i Family Dwelling Zone -
I unit/2,500 sq. It.
R-3 Limited Multiple
~ Family Dwelling Zone -
I unit/1,250 sq. It.
~ MH Mobile Home
--Roods
c:::] Parcels_ExportFeatures
EZJ SITEParcels_ExportFeatu
I:"! ~
BAKERSFIELD
t
Feet
0 500 1,000
MAP PACKAGES
ZONE CHANGE
22-0025
RR
LR
Land Use-CLR
RESIDENTIAL
LMR LowMedium
-
Density Residentiol:>
4 units but<:; 10
dwelling units/net acre
HR -High Density
-
Residential,> 17.42
units but<:; 72.6
dwelling units/net acre
HMR -High Medium
Density Residential:>
7.26 units but<:; 17.42
dwelling units/net acre
LR -Low Density
Residential,<:; 7.26
dwelling units/net acre
RR-RurolResidenlial:
2.5 gross acres/
dwelling unit
COMMERCIAL
-
GC-General
Commercial
INDUSTRIAL
-LI -LIGHT INDUSTRIAL
-SI-Servicelndustriol
-HI -Heavy Industrial
PUBLIC FACILITIES
-P-Public Facilities
PT-Public
-Transportation
Corridors
RESOURCE
R-IA -Resource-_ Intensive Agriculture:
20 acre minimum parcel
size
--Roods
c::::I Parcels_ExportFeatures
E:Z:ISITEP□rcels_Exporlfeotu
I:"! ~
BAKERSFIELD
t
Feet
0 500 1,000
MAP PACKAGES
Page 1 of 2
RESOLUTION NO. ______
RESOLUTION OF THE BAKERSFIELD PLANNING COMMISSION
RECOMMENDING THAT THE CITY COUNCIL ADOPT A MITIGATED
NEGATIVE DECLARATION FOR ZONE CHANGE LOCATED AT 75
EAST WHITE LANE & 2572 SOUTH UNION AVENUE
(ZC NO. 22-0025).
WHEREAS, Swanson Engineering, Inc. (applicant) on behalf of FBT, Inc. (property
owner), is requesting an amendment to Title 17 of the Bakersfield Municipal Code to
change the Zone District from M-3 (Heavy Manufacturing) to M-2 (General
Manufacturing) on approximately 69-acres located at 75 East White Lane & 2572 South
Union Avenue, as shown on attached Exhibit “B”, (the "Project"); and
WHEREAS, an initial study was conducted and it was determined that the Project
would not have a significant effect on the environment; therefore, a Negative
Declaration with mitigation measures was prepared in accordance with the California
Environmental Quality Act (CEQA); and
WHEREAS, the Secretary of the Planning Commission set Thursday, October 3, 2024
at 5:30 p.m. in the Council Chambers of City Hall, 1501 Truxtun Avenue, Bakersfield,
California, as the time and place for a public hearing before the Planning Commission to
consider the proposed Mitigated Negative Declaration and Project as required by
Government Code Section 65353, and notice of the public hearing was given in the
manner provided in Title 17 of the Bakersfield Municipal Code; and
WHEREAS, the laws and regulations relating to the preparation and adoption of
Mitigated Negative Declarations as set forth in CEQA, the State CEQA Guidelines, and
the City of Bakersfield CEQA Implementation Procedures have been duly followed by
City staff and the Planning Commission; and
WHEREAS, the City of Bakersfield Development Services Department (1715 Chester
Avenue, Bakersfield, California) is the custodian of all documents and other materials
upon which the environmental determination is based; and
WHEREAS, the facts presented in the staff report, initial study, and special studies,
and evidence received both in writing and by verbal testimony at the above-referenced
public hearing support the following findings:
1. All required public notices have been given. Hearing notices regarding the
Project were mailed to property owners within 300 feet of the Project area
and published in the Bakersfield Californian, a local newspaper of general
circulation, at least 20 days prior to the hearing.
2. The provisions of CEQA, the State CEQA Guidelines, and the City of
Bakersfield CEQA Implementation Procedures have been followed. Staff
determined that the proposal is a project under CEQA.
Page 2 of 2
3. A Mitigated Negative Declaration for the Project is the appropriate
environmental document to accompany its approval as the Project will not
significantly impact the physical environment.
NOW, THEREFORE, BE IT RESOLVED by the Bakersfield Planning Commission as
follows:
1. The above recitals, incorporated herein, are true and correct.
2. The Mitigated Negative Declaration is hereby recommended for adoption
by the City Council.
3. The project is subject to mitigation measures found in Exhibit A for the
Project located on the map as shown in Exhibit B, both of which are
incorporated herein.
I HEREBY CERTIFY that the foregoing Resolution was passed and adopted by the
Planning Commission of the City of Bakersfield at a regular meeting thereof held on the
3rd day of October 2024, on a motion by Commissioner _____and seconded by
Commissioner ______, by the following vote.
AYES:
NOES:
ABSENT:
APPROVED
______________________________________
DANIEL CATER, CHAIR
City of Bakersfield Planning Commission
Exhibits (attached):
Exhibit A: Mitigation Measures
Exhibit B: Location Map
By: VM/S:\15_Zone Change\01_Active\2022\22-0025 (75 E. White & 2572 S. Union)\01_Hearing & Noticing
Documents\Draft\PC\PC RES ENV.Docx
By VM/S:\15_Zone Change\01_Active\2022\22-0025 (75 E. White & 2572 S. Union)\01_Hearing & Noticing Documents\Draft\PC\ExhA Mitigation_75 E. White Ln.docx
EXHIBIT A
MITIGATION MEASURES
ZONE CHANGE NO. 22-0025
Air Quality Impact Mitigation Measures:
1. Prior to grading plan approval, the applicant/developer shall submit documentation to the
Planning Division that they are compliant with air quality control measures and rules required
by the San Joaquin Valley Air Pollution Control District. The documentation shall specify that
the Project has complied with the SJVAPCD’s Indirect Source Rule (Rule 9510).
Biological Resources Impact Mitigation Measures:
2. Prior to ground disturbance and/or construction activities, the applicant/developer shall
consult with the California Department of Fish and Wildlife and United States Fish and Wildlife
Service requirements related to listed plant and animal species protected under the Federal
Endangered Species Act (FESA) and the California Endangered Species Act (CESA).
Geology and Soils, Cultural Resources, and Tribal Resources Impacts Mitigation Measures:
3. Prior to construction and as needed throughout the construction period, a construction
worker cultural awareness training program shall be provided to all new construction workers
within one week of employment at the project site. The training shall be prepared and
conducted by a qualified cultural resources specialist.
4. During construction, if paleontological or cultural resources are encountered during
construction or ground disturbance activities, all work within 50 feet of the find shall
immediately cease and the area cordoned off until a qualified cultural and/or
paleontological resource specialist that meets the Secretary of the Interior’s Professional
Qualification Standards can evaluate the find and make recommendations. If the specialist
determines that the discovery represents a potentially significant cultural resource,
additional investigations may be required. These additional studies may include avoidance,
testing, and excavation. All reports, correspondence, and determinations regarding the
discovery shall be submitted to the California Historical Resources Information System’s
Southern San Joaquin Valley Information Center at California State University Bakersfield.
5. During construction, if human remains are discovered, further ground disturbance shall be
prohibited pursuant to California Health and Safety Code Section 7050.5. The specific
protocol, guidelines, and channels of communication outlined by the Native American
Heritage Commission, in accordance with Health and Safety Code Section 7050.5, Public
Resources Code 5097.97, and Senate Bill 447 shall be followed. In the event of the discovery
of human remains, at the direction of the county coroner, Health and Safety Code Section
7050.5(c) shall guide Native American consultation.
Traffic Impact Mitigation Measures:
6. Prior to the issuance of building permits, the project applicant shall participate in the
Exhibit “A” Mitigation Measures
Zone Change No. 22-0025
Page 2 of 2
Regional Transportation Impact Fee (RTIF) program by paying the adopted fees in place
for the land use type at the time of development.
R-1
ZONE CHANGE
22-0025
CITY OF BAKERSFIELD
M-3
COUNTY
M-1
r·-··-··-··-··-·· : CITY
M-1
■■-■■-■■-■■-■■-■■-■■-..
M-1 !
r-··-··-··:::-··1
(Y"). a::! R-3 R-1 i
z
0
z
::J
I
M-3
• CSOlJN-TIY, PAEHEE0
C-2
M-1 R-1
R-3
M
<(
£!l z. z. w
M-1 w R-1 R-1 ci:::;
et::· <(,
al' ~.
~\l
WHFT-E
I et:: w al R-1 et::
<(
\.!)
T""f R-1 a::
M-
M-3
R-5
R-5 R-5
R-5-2.SA
>.-w
l.(l
M-1
..... ~ ~---■■-■■-■•-·1 __ ~ '----1
R-2
R-1
LEGEND
(ZONE DISTRICTS)
R-1 One Family Dwelling
6,000 sq.ft. min lot size
R-1-4.5 One Family Dwelling
4,500 sq.ft. min lot size
E Estate
I 0,000 sq.ft. min lat size
R-S Residential Suburban
24,000 sq.ft./dwelling unit
R-S-( } Residential Suburban
I, 1.5, 5 or 10 min lot size
R-2 Limited Multiple Family Dwelling
4,500 sq.ft. min lot size (single family}
6,000 sq.ft. min lot size (multifamily}
1,500 sq.ft. lat area/dwelling unit
R-3 Multiple Family Dwelling
6,000 sq.ft. min lot size
1,150 sq.ft. lot area/dwelling unit
R-4 High Density Multiple Family Dwelling
6,000 sq.ft. min lot size
600 sq.ft. lot area/dwelling unit
R-H Residential Halding
20 acre min lot size
A Agriculture
6,000 sq.ft. min lot size
A-10A Agriculture
20 acre min lot size
PUD Planned Unit Development
TT Travel Trailer Park
MH Mobilehame
(-0 Professianal ond Administrative Office
(-1 Neighborhood Commercial
(-1 Regional Commercial
(-( Commercial (enter
(-B Central Business
PCD Planned Commercial Development
M-1 Light Manufacturing
M-1 General Manufacturing
M-3 Heavy Industrial
P Automobile Parking
RE Recreation
Ch Church Overlay
OS Open Space
HOSP Hospital Overlay
AD Architectural Design Overlay
FP-P Flaadploin Primary
FP-S Floodplain Secondary
AA Airport Approach
DI Drilling Island
PE Petroleum Extraction Combining
S( Senior Citizen Overlay
HD Hillside Development Combining
WM-West Ming Specific Plan
I:"! ~
BAKERSFIELD
t
Feet
0 500 1,000
MAP PACKAGES
Page 1 of 2
RESOLUTION NO. ______ RESOLUTION OF THE BAKERSFIELD PLANNING COMMISSION RECOMMENDING THAT THE CITY COUNCIL APPROVE AN AMENDMENT TO TITLE 17 OF THE BAKERSFIELD MUNICIPAL CODE TO CHANGE THE ZONE DISTRICT FROM M-3 (HEAVY MANUFACTURING) TO M-2 (GENERAL MANUFACTURING)
LOCATED AT 75 EAST WHITE LANE & 2572 SOUTH UNION AVENUE (ZC NO. 22-0025).
WHEREAS, Swanson Engineering, Inc. (applicant) for FBT, Inc. (property owner), is
requesting to change the zone district from M-3 (Heavy Manufacturing) to M-2 (General
Manufacturing) on approximately 69-acres located at 75 East White Lane and 2572 South
Union Avenue, as shown in attached Exhibit “A” (the “Project”); and
WHEREAS, the applicant and/or property owner has indicated the purpose of the
Project is for compliance with the zoning ordinance; and
WHEREAS, adoption of a Mitigated Negative Declaration for the Project (SCH No.
2024060954) has been recommended; and
WHEREAS, the Secretary of the Planning Commission set Thursday, October 3, 2024,
at 5:30 p.m. in the Council Chambers of City Hall, 1501 Truxtun Avenue, Bakersfield,
California, as the time and place for a public hearing before the Planning Commission to consider the proposed Mitigated Negative Declaration and change to the zone district,
as required by Government Code Section 65353, and notice of the public hearing was given in the manner provided in Title 17 of the Bakersfield Municipal Code; and
WHEREAS, the facts presented in the staff report, initial study, and special studies,
and evidence received both in writing and by verbal testimony at the above referenced public hearing support the following findings:
1. All required public notices have been given. Hearing notices regarding the
Project were mailed to property owners within 300 feet of the Project area
and published in the Bakersfield Californian, a local newspaper of general
circulation, at least 10 days prior to the hearing.
2. The provisions of CEQA, the State CEQA Guidelines, and the City of
Bakersfield CEQA Implementation Procedures have been followed. Staff
determined that the proposal is a project under CEQA and an initial study
was completed.
3. The public necessity, general welfare, and good planning practices justify
the Project.
4. The Project is compatible with the zone districts and development of
surrounding properties and is consistent with the Metropolitan Bakersfield
General Plan.
Page 2 of 2
NOW, THEREFORE, BE IT RESOLVED by the Bakersfield Planning Commission as follows:
1. The above recitals, incorporated herein, are true and correct.
2. The Project is hereby recommended for approval by the City Council,
incorporating the change into the official zoning map as described in
Bakersfield Municipal Code Section 17.06.020 located on the map as shown
in Exhibit A and as specifically described in Exhibit B, all of which are
incorporated herein.
3.
I HEREBY CERTIFY that the foregoing Resolution was passed and adopted by the
Planning Commission of the City of Bakersfield at a regular meeting thereof held on the
3rd day of October 2024, on a motion by Commissioner _____and seconded by
Commissioner ______, by the following vote.
AYES:
NOES:
ABSENT:
APPROVED
______________________________________ DANIEL CATER, CHAIR
City of Bakersfield Planning Commission Exhibits (attached):
Exhibit A: Conditions Exhibit B: Location Map
Exhibit C: Legal Description
By: VM/S:\15_Zone Change\01_Active\2022\22-0025 (75 E. White & 2572 S. Union)\01_Hearing & Noticing Documents\Draft\PC\PC RES ZC.Docx
By VM/S:\15_Zone Change\01_Active\2022\22-0025 (75 E. White & 2572 S. Union)\01_Hearing & Noticing Documents\Draft\PC\ExhA Mitigation_75 E. White Ln.docx
EXHIBIT A
MITIGATION MEASURES
ZONE CHANGE NO. 22-0025
Air Quality Impact Mitigation Measures:
1. Prior to grading plan approval, the applicant/developer shall submit documentation to the
Planning Division that they are compliant with air quality control measures and rules required
by the San Joaquin Valley Air Pollution Control District. The documentation shall specify that
the Project has complied with the SJVAPCD’s Indirect Source Rule (Rule 9510).
Biological Resources Impact Mitigation Measures:
2. Prior to ground disturbance and/or construction activities, the applicant/developer shall
consult with the California Department of Fish and Wildlife and United States Fish and Wildlife
Service requirements related to listed plant and animal species protected under the Federal
Endangered Species Act (FESA) and the California Endangered Species Act (CESA).
Geology and Soils, Cultural Resources, and Tribal Resources Impacts Mitigation Measures:
3. Prior to construction and as needed throughout the construction period, a construction
worker cultural awareness training program shall be provided to all new construction workers
within one week of employment at the project site. The training shall be prepared and
conducted by a qualified cultural resources specialist.
4. During construction, if paleontological or cultural resources are encountered during
construction or ground disturbance activities, all work within 50 feet of the find shall
immediately cease and the area cordoned off until a qualified cultural and/or
paleontological resource specialist that meets the Secretary of the Interior’s Professional
Qualification Standards can evaluate the find and make recommendations. If the specialist
determines that the discovery represents a potentially significant cultural resource,
additional investigations may be required. These additional studies may include avoidance,
testing, and excavation. All reports, correspondence, and determinations regarding the
discovery shall be submitted to the California Historical Resources Information System’s
Southern San Joaquin Valley Information Center at California State University Bakersfield.
5. During construction, if human remains are discovered, further ground disturbance shall be
prohibited pursuant to California Health and Safety Code Section 7050.5. The specific
protocol, guidelines, and channels of communication outlined by the Native American
Heritage Commission, in accordance with Health and Safety Code Section 7050.5, Public
Resources Code 5097.97, and Senate Bill 447 shall be followed. In the event of the discovery
of human remains, at the direction of the county coroner, Health and Safety Code Section
7050.5(c) shall guide Native American consultation.
Traffic Impact Mitigation Measures:
6. Prior to the issuance of building permits, the project applicant shall participate in the
Exhibit “A” Mitigation Measures
Zone Change No. 22-0025
Page 2 of 2
Regional Transportation Impact Fee (RTIF) program by paying the adopted fees in place
for the land use type at the time of development.
R-1
ZONE CHANGE
22-0025
CITY OF BAKERSFIELD
M-3
COUNTY
M-1
r·-··-··-··-··-·· : CITY
M-1
■■-■■-■■-■■-■■-■■-■■-..
M-1 !
r-··-··-··:::-··1
(Y"). a::! R-3 R-1 i
z
0
z
::J
I
M-3
• CSOlJN-TIY, PAEHEE0
C-2
M-1 R-1
R-3
M
<(
£!l z. z. w
M-1 w R-1 R-1 ci:::;
et::· <(,
al' ~.
~\l
WHFT-E
I et:: w al R-1 et::
<(
\.!)
T""f R-1 a::
M-
M-3
R-5
R-5 R-5
R-5-2.SA
>.-w
l.(l
M-1
..... ~ ~---■■-■■-■•-·1 __ ~ '----1
R-2
R-1
LEGEND
(ZONE DISTRICTS)
R-1 One Family Dwelling
6,000 sq.ft. min lot size
R-1-4.5 One Family Dwelling
4,500 sq.ft. min lot size
E Estate
I 0,000 sq.ft. min lat size
R-S Residential Suburban
24,000 sq.ft./dwelling unit
R-S-( } Residential Suburban
I, 1.5, 5 or 10 min lot size
R-2 Limited Multiple Family Dwelling
4,500 sq.ft. min lot size (single family}
6,000 sq.ft. min lot size (multifamily}
1,500 sq.ft. lat area/dwelling unit
R-3 Multiple Family Dwelling
6,000 sq.ft. min lot size
1,150 sq.ft. lot area/dwelling unit
R-4 High Density Multiple Family Dwelling
6,000 sq.ft. min lot size
600 sq.ft. lot area/dwelling unit
R-H Residential Halding
20 acre min lot size
A Agriculture
6,000 sq.ft. min lot size
A-10A Agriculture
20 acre min lot size
PUD Planned Unit Development
TT Travel Trailer Park
MH Mobilehame
(-0 Professianal ond Administrative Office
(-1 Neighborhood Commercial
(-1 Regional Commercial
(-( Commercial (enter
(-B Central Business
PCD Planned Commercial Development
M-1 Light Manufacturing
M-1 General Manufacturing
M-3 Heavy Industrial
P Automobile Parking
RE Recreation
Ch Church Overlay
OS Open Space
HOSP Hospital Overlay
AD Architectural Design Overlay
FP-P Flaadploin Primary
FP-S Floodplain Secondary
AA Airport Approach
DI Drilling Island
PE Petroleum Extraction Combining
S( Senior Citizen Overlay
HD Hillside Development Combining
WM-West Ming Specific Plan
I:"! ~
BAKERSFIELD
t
Feet
0 500 1,000
MAP PACKAGES
r
PARCEL 1: APN: 172-140-05
Exhibit "A"
Legal Description
FBT, INC.
Zone Change
(
The East half of Lot 14; the East half of Lot 15; all of those portions of Lot 13 and Lot 18, which lie
West of the center line of the Kern Island Canal, all in Section 17, Township 30 South, Range 28
East, M ount Diablo Base and Meridian, City of Bakersfield, County of Kern, State of California, as
shown on Sa les Map No. 1 of Kern County Lands of J.B. Haggin, recorded in the office of the
County Recorder of Kern County on May 3, 1889.
EXCEPTING THEREFROM t hose port ions of Lot 13 and Lot 14 described as follows:
Com mencing at a 3" brass cap in a lamp hole, same being the East quarter corner of Section 18
of said Township and Range, also being a point on the center line of County Road No. 782, also
known as "White Lane"; thence East, 1235.00 feet along the center line of said County Road No.
782 to the True Point of Beginning; thence southerly 430 feet along a line perpendicular to the
center line of said County Road No. 782; thence Easterly 456.00 feet along a line parallel with the
center line of said County Road No. 782 to the center line of the central branch of the Kern Island
Canal; thence northwesterly along t he center line of said canal to the centerline of said County
Road No. 782; thence westerly along t he cent er line of said County Road No.782, a distance of
202.00 feet to the True Point of Beginning.
Containing 63.60± acres gross
PARCEL 2: APN: 172-160-14
Parcel 3 of Parcel Map No. 2754, per M ap recorded January 16, 1975 in Book 12, Page 100 of
Parcel Maps, in the office of the County recorder of said County, also being a portion of the
Southwest quart er of Section 17, Township 30 South, Range 27 East, Mount Diablo Base and
Meridian, situated in the City of Bakersfield, County of Kern, State of California.
Containing 4.50± acres gross
1 of 1