RESOLUTION NO.
A RESOLUTION OF THE COUNCIL OF THE CITY OF
BAKERSFIELD ADOPTNG THE 2003-2024 REGIONAL
TRANSPORTATION CAPITAL IMPROVEMENT PLAN
PHASE II
WHEREAS, Chapter 15.84 of the Bakersfield Municipal Code implemented a
Transportation Impact Fee program for new development in order for new development
to bear a proportionate share of the cost of the new or expanded transportation facilities
required by such development; and
WHEREAS, certain recent changes in the development pattern of the
Metropolitan area have occurred necessitating the addition of several projects to the
Facilities List; and
WHEREAS, the total cost of these additional projects is offset by savings in other
projects, resulting in no net change to the Transportation Impact Fee; and
WHEREAS, Chapter 15.84 of the Bakersfield Municipal Code requires that the
City Council annually update the capital improvement plan for road construction funded
by the impact fee program and adopt a proposed fee schedule; and
WHEREAS, Chapter 15.84 of the Bakersfield Municipal Code further requires
that the fee schedule adopted by the City Council be adjusted annually by the
Construction Cost Index; and
WHEREAS, a public hearing before the City Council was advertised and held
June 25, 2003.
NOW, THEREFORE, BE IT RESOLVED by the Council of the City of Bakersfield
as follows:
1. The above recitals are true and correct and incorporated herein.
2. That Capital Improvement Plan, Phase II set forth as Exhibit "A", is hereby
approved and adopted for all developments other than those which vested prior to
February 10, 1997.
3.. That the fee schedule for Phases I and II set forth as Exhibit "B" is hereby
approved and adopted.
............ 000 ............
- Page I of 2 Pages -
I HEREBY CERTIFY that the foregoing Resolution was passed and..a, dopted by the
Council of the City of Bakersfield at a regular meeting thereof held on JUN ~,5 2003 ,
by the following vote:
AYES:
NOES:
ABSTAIN:
ABSENT:
APPROVED
COUNCIL MEMBER COUCH, BENHAM, CARSON, HANSON, MAGGARD, SALVAGGIO, SULLIVAN
COUNCIL MEMBER
COUNCIL MEMBER
COUNCIL MEMBER
CITY CLERK and Ex Offi~ Clerk of the
Council of the City of Bakersfield
JUN ~ 5 2003
By hARVEY'L HALL
Mayor
APPROVED AS TO FORM:
BART J. THILTGEN
City Attorney
ALAN ~D/DANIEE~
Deputy City Attorney
raps
S:\PROJECTS\TIF~PHASE2\FY 2003-2024\Resolution. DOC Page 2 o£?
$8,102
$533900 $533,g00
AT&$F RR
>anama Lane
AT&SF
$183,662
$128136 $128136
$5,424
$1211263 $1211,263
$13200~
$128136 $12813~
Wible Rd SR 119 $1 r217,6~ $1,300,2.4~3 $1 34)0243 $1,300,243
TRANSPORTATION IMPACT FEES - PHASES I AND II
Phase I Phase II Phase II Phase II
Fee Per Fee per Fee per Fee per
L~nd IJ~e Tv~e Tv~e No. Unit Unit Unit Unit
Sin~lle Family, Detached 1 $1,17c~ $2,197 $2,346 $2,466
'- ' 2 $828 $1,471 $1,571 $1,651
Heavy/Service Industrial 3 $87 $87 $93 $98
Li~]ht Industrial 4 $38 $38 $41 $43
OFFICE COMMERCIAL
Under 100,000 sq.ft. 5 $33 $33 $35 $37
100,000 - 199,999 sq.ft. 6 $39 $39 $42 $44
200,000 sq.ft. & over 7 $41 $41 $44 $46
RETAIL COMMERCIAL
Under 10,000 sq.ft. 8 $39 $35 $37 $39
10,000 - 49,999 sq.ft. 9 $25 $45 $48 $51
50,000 - 99,999 sq.ft. 10 $28 $66 $64 $67
100,000 - 199,999 sq.ft. 11 $31 N/A N/A N/A
200,000 - 299,999 sq.ft. 12 $35 N/A N/A N/A
300,000 - 399,999 sq.ft. 13 $44 N/A N/A N/A
400,000 - 499,999 sq.ft. 14 $53 N/A N/A N/A
500,000 - 999,999 sq.ft. 15 $64 N/A N/A N/A
1,000,000 sq.ft. & over 16 $71 N/A N/A N/A
Effective Date 06/08/92 02/10/97 07/08/02 07/25~03
fee schedule. XLS EXHIBIT "B" 6/13/2003
PROJECTS TO BE ADDED TO THE TIF LIST
Date Requested
February 18, 2003
January, 2003
April, 2003
April3,2003
April22,2003
April29,2003
May2,2003
May 2, 2003
May2,2003
May 2, 2003
May 14, 2003
Proiect
Jewetta crossing of Goose Lake Slough. Cost - $290,000 Requested by
Ted Wright.
Masterson Street. Add 2 lanes from Paladino to Alfred Harrell Road.
Cost = 2 lanes x 1.5 miles x $ 229,577 = $ 688,731 plus
$968,034 is special costs (extra grading, culverts) = $ 1,656,836
Requested by: Carver/Carosella
McKee Road, Wible to 99. Cost = 2 lanes x I mile x $145,000 x 1.678 =
$486,620.00 Requested by Jack Turman.
McKee Road, Ashe to Stine. Cost = 2 lanes x 1 mile x $145,000 x 1.0678
= $309,662.00 Requested by Jim Delmarter
Jewetta crossing of North Kern WSD Canal at Snow
Cost = $250,000 Requested by Russ Johnson
Knudsen Drive, Olive to Bascilicata Drive. Cost - $105,000
Requested by Jacques R. LaRochelle, Assistant Public Works Director
Signal at Paladino and Morning Drive. Cost = $140,000
Imminent development in the area; arterial/arterial intersection.
Signal at Panama lane and Monitor Street. Cost = $140,000
Development in the area; arterial/collector intersection.
Freeway and Beltway Advanced Planning. Cost = $1,500,000
Planning, preliminary design and environmental documents for the East
and West Beltways and the Centennial Corridor
Signal at SR 178 and Miramonte Drive. Cost = $180,000
Requested by Sage Development Group
Farmer's Canal crossing of McCutcherffHosking. Cost: $100,000
Requested by Franklin (Bakersfield 26 LLC) for Tract 6190
TOTAL: $ 5,058,118
S:\PROJ ECTS\TIF\PHASE2\To Add2,wpd I
PROJECTS TO BE REMOVED FROM THE TIF LIST
Signal ~ McCutcheon & Progress Cost = $120,000 Reason: County request
May 16, 2003
May 16, 2003
May 16, 2003
May 16, 2003
May 16, 2003
May 16, 2003
May 16, 2003
Pacheco, Buena Vista to Gosford. Reason: This is no longer on the
circulation element. Cost - $619,324
Pacheco ~ BV Canal. Reason: This is no longer on the circulation
element. Cost = $85,424
Signal @ Pacheco and Old River. Reason: This is no longer on the
circulation element. Cost = $128,136
Signal ~ Pacheco and Gosford. Reason: This is no longer on the
cimulation element. Cost = $128,136
At-grade crossing ~ Pacheco and AT&SF RR. Reason: This is no longer
on the circulation element. Cost -- $106,780
Signal ~_~ Pacheco and Mountain Vista. Reason: This is no longer on the
circulation element. Cost = $128,136
Signal @ Panama Lane and Oswell. Reason: This is a duplication of a
project. Cost: 128,136.
TOTAL: $1,143,328.00
S:\PROJECTS\TIF\PHASE2\To Add2.wpd2
PROJECTS TO BE REVISED ON THE TIF LIST
May 16, 2003
Signal ~ Norris Road and Riverlakes to Norris Road and Quail Creek Rd.
Reason: Same location, different street name. No change to cost.
May 16, 2003
Signal (¢ Snow Road and Riverlakes to Snow Road and Quail Creek Rd.
Reason: Same location, different street name. No change to cost.