HomeMy WebLinkAboutRES NO 055-05RESOLUTION NO. 0 ~ 5 - 0 5
A RESOLUTION OF THE COUNCIL OF THE
CITY OF BAKERSFIELD ADOPTING
DRAINAGE PLAN FOR THE GOLDEN
VALLEY PLANNED DRAINAGE AREA AND
MAKING FINDINGS RELATIVE THERETO.
RECITALS
WHEREAS, the City Council by Resolution of Intention No. 1372, adopted
March 9, 2005, in the Council chambers in the City Hall, 1501 Truxtun Avenue,
Bakersfield, California, identified the Golden Valley Planned Drainage Area, and;
WHEREAS, the new project will complete the pipeline system that will
drain water to a central basin, and;
WHEREAS, the completion of the project will improve the efficiency of the
storm water drainage facilities in the benefit area, and;
WHEREAS, the City Council finds that the completion of the system is in
the best interest for the health, safety and welfare of the community.
NOW, THEREFORE, BE IT RESOLVED by the Council of the City of
Bakersfield as follows:
1. The foregoing recitals are true and correct and incorporated herein
by reference.
2. The Golden Valley Planned Drainage Area has been identified as
necessary for the removal of surface and storm waters from the local and neighborhood
drainage areas.
3. The Council hereby finds that, as to the Golden VaLley Planned
Drainage Area, as described in the plans and maps attached hereto and incorporated
herein by reference, subdivision and development of property within each such area will
require construction of facilities, described in each such area either on the basis of
benefits conferred on property for subdivision or on the need for such facilities created
by the proposed subdivision and development of other property within such area, and
that the fees provided within the schedule attached, are fairly apportioned.
4. The Golden Valley Planned Drainage Area is hereby adopted.
- Page 1 of 2 Pages -
S:/PROJECTSIPSA,POA/Estab/Golden ValleyPDA Adopt of Res. DOC
I HEREBY CERTIFY that the foregoing Resolution was passed and
adopted, by the Council of the City of Bakersfield at a regular meeting thereof held on
MAR $ 0 ZOO§ by the following vote:
NOES:
ABSTAIN:
ABSENT:
COUNClLMEMBER COUCH, CARSON, BENHAM, MAGGARD, HANSON, SULLIVAN, SCRIVNER
COUNClLMEMBER
COUNCILMEMBER
COUNCILMEMBER
PAME'~-A A. McCARTHY, CMC
CITY CLERK and Ex Officio Clerk'O~f the
Council of the City of Bakersfield
APPROVED MAR 3
HARVEY L. HALL
Mayor of the City of Bakersfield
APPROVED as to form
VIRGINIA GENNARO
City Attorney
Attachments:
Exhibit "A" Boundary Area
Exhibit "B" Fee Schedule
Exhibit "C" Cost Estimate
- Page 2 of 2 Pages -
S/PROJECTS~PSA,PDA/Estab\Go~den ValleyPDA Adopt of Res DOC
X iN
NOINn 'OS
133~{1S
'~0 NONN
EXHIBIT "B"
GOLDEN VALLEY PLANNED DRAINAGE AREA
FEE SCHEDULE
PDA
ZONE ACREAGE COST/ACRE ALLOCATION
R-1 93.19 $2,742 $255,527
COMMERCIAL 17.49 $5,868 $102,631
HIGH SCHOOL 59.77 EXEMPT $0
TOTAL 170.45 $358,158
TOTAL PRICE $358,158
*In each subsequent year, annual cost per acre may increase by the
Construction Cost Index.
EXHIBIT "C"
GOLDEN VALLEY PLANNED DRAINAGE AREA
COST ESTIMATE
REIMBURSEMENT TO KERN HIGH SCHOOL DISTRICT FOR PORTION BUILT
*THIS ESTIMATE IS FOR THE DIFFERENCE IN COST BETWEEN SIZE REQUIRED FOR THE
SCHOOL AND THE REQUIRED SIZE FOR THE PDA
ORIGINAL ESTIMATE WAS DONE BY PORTER-ROBERTSON ENGINEERING AND SURVEYING, INC., SEPTEMBER 30, 2004
Item Estimated Unit ITEM Unit Extension Price
No. Quantity Price
DRAINAGE PIPELINES
I 131 LF 36" pipe in place of no pipe $72.04 - $0.00= $72.04 $9,437
2 215 LF 36" pipe in place of 18" pipe $72.04 - $37.26= $34.78 $7,478
3 1219 LF 36" pipe in place of 24" pipe $72.04 - $47.94= $24.10 $29,378
4 1027 LF 42" pipe in place of 36" pipe $85.71 - $72.04= $13.67 $14,039
SUBTOTAl $60,332
DRAINAGE BASIN IMPROVEMENTS
5 65 % FENCING AND GATE $33,090 $21,422
6 61 % EXCAVATION $70,680 $43,313
SUBTOTAl $64,735
CONSTRUCTION TOTAL $125,067
12 % ENGINEERING AND ADMINISTRATION $125,067 $15,008
LAND ACQUISITION AND FEES
8 65 % *BASIN LAND ACQUISITION
65 % *BASIN HCP FEES
$57,000 $36,902
$3,720 $2,408
SUBTOTAL $39,310
TOTAL $179,385
TO COMPLETE
Item Estimated
No. Quantity
THE PDA THE FOLLOWING ITEMS ARE STILL NEEDED
Unit
Unit Item Price
Extension Price
1
2
3
4
5
6
1566 LF 24" STORM DRAIN
181 LF 30" STORM DRAIN
15 LF 36" STORM DRAIN
7 LF MANHOLES
100 LF ROAD BORED FOR 24" PIPE
2100 CY EXCAVATION
20 % CONTINGENCY
12 % ENGINEERING AND ADMINISTRATION
$48 $75,168
$60 $10,860
$72 $1,080
$2,500 $17,500
$2OO $20,000
$4 $8,400
SUBTOTAl $133,008
$133,008 $26,602
$159,610 $19,153
TOTAL $178,763
GRAND TOTAL ~ $358,148