HomeMy WebLinkAbout10/16/98 B A K E R S F I E L D
CITY MANAGER'S OFFICE
MEMORANDUM
October 16, 1998
TO: HONORABLE MAYOR AND CITY COUNCIL
FROM: ALAN TAND , C~I~'~AANAGER
SUBJECT: GENERAL INFORMATION
1. The latest progress report on the Wastewater Treatment Plant #3 Expansion is
enclosed for your information.
2. The paving of Truxtun Avenue and the associated traffic congestion problems has
been delayed until October 22nd and 23r~ according to the enclosed note from the
Public Works Director.
3. Attached is a memo from the Public Works Department detailing responses to the
Council referral concerning improvements surrounding Centennial Garden.
4. We have had a cycle of pretty easy agendas I believe, including the one scheduled
for October 21st. Beginning in November, we have the General Plan cycle and it is
likely to get more difficult.
AT:rs
cc: Department Heads
Pamela McCarthy, City Clerk
Trudy Slater, Administrative Analyst
BAKERSFIELD
PUBLIC WORKS DEPARTMENT
MEMORANDUM
TO: ALAN TANDY, City Manager
FROM: RAUL M. ROJAS, Public Works Director ~-;~--v ~/.~/~..~'
DATE: October 14, 1998
SUBJECT: WASTEWATERTREATMENT PLANT#2
Attached are eleven copies of Progress Report No. 7 of the Wastewater Treatment Plant
# 2 - Expansion Project, prepared by Black & Veatch.
Attachments
G:\GROUPDAT~Memo\1998\wwtp2report7.wpd
~tl~er~f [e~) ~~te4~ater ~re~ttment
TEEL COP~OIU]~ON ' Sachs.Ele.ctr c=
DYK'
A P~rt~er~lPr~~t
CONSTRUCTION PROGRESS SUMMARY NUMBER SEVEN
September 1, 1998 through September 30, 1998
CONSTRUCTION PROGRESS
I. Major construction quantities to date include:
· Man Hours To Date: 87,500 mh
Plus Electrical Workers and Ironworkers
· Square Feet of Concrete Formwork: 378,000 sf
· Concrete-Steel Reinforcing Installed: 900 tons
· Cubic Yards of Concrete Placed: 12,000 c.y.
· Cubic Yards of Structure Excavation: 25,500 c.y.
· Cubic Yards of Site Excavation: 61,500 c.y.
· Cubic Yards of Trench Excavation: 34,200 c.y.
· Cubic Yards of Bedding and Backfill 26,000 c.y.
· Linear Feet of 42-inch, 48-inch and 60-inch
Diameter Cement Mortar lined Steel Pipe: 3900/4500
· Linear Feet of S/10" Sludge Bed Piping 5372/I0,369
I. Kiewit Pacific Co., performed the following work:
Site: Completed excavation and berms for 90% of the
sludge drying beds, and started placing aggregate
base roads. Completed the area fill for the
secondary clarifier area. Installed the electrical
ductbank between the Recirculation Pump Station
and the Secondary Clarifier Splitter Box. Set the
54" pipe f~om the Distribution Box to the Storage
Reservoir.
Primary Clarifier: Started sand blasting and painting the clarifier
equipment prior to installation.
Trickling Filters: Finished placing concrete for the three trickling
filters. Completed placing 50% of the filter media.
Installed the access stairs to filters No. 1 and No. 2.
Recirculation Pump Station: Started finish work on the concrete surfaces.
Installed sluice gates and weirs.
Secondary Clarifiers: Completed leak tests of all basins. Started
formwork for Secondary Clarifier No. 3 launder
slab. Continued concrete corrective work on basin
walls.
P~el
Digesters: Completed prestressing Digester No. 4 wall.
Started prestressing Digester No. 3 wall. Finished
placing the upper walls on the Digester Control
Building. Installing process pipe in the Digester
Control Building basement.
Mass Site Fill in Secondary Clarifier Area
SIGNIFICANT ACCOMPLISHMENTS
· There have been no claims, but Change Order No. 2 is being prepared.
· Kiewit has had only one recordable accident to date on the project.
· The supplemental partnering session is scheduled for October 14, 1998.
· Major participation from Bakersfield construction firms and material suppliers
include:
· Granite Construction- Paving
· Crown Fence - Fencing
· Tri-Steel Corporation: - Concrete Reinforcing Steel
· BSK- Materials Testing
· American Transit - Concrete
Page 2
Electrical Ductbank to Digester Conlrol Building
AREAS OF CONCERN
None
PROPOSED CHANGE ORDERS
Proposed Change Order No. 2 - Addresses minor engineering revisions, process
system improvemems and a significant Value Engineering credit.
REQUEST FOR INFORMATION
· 112 RFI's have been received/processed as of September 30, 1998.
· 6 Days on average turn around.
SHOP DRAWINGS
· 264 Shop Drawings have been received/processed as of September 30, 1998.
· 11 Days on average turn around.
Page 3
PLANNED ACTIVITIES FOR
OCTOBER 1998
Site: Complete the plant effluent piping
at the out£all distribution box. Start work
at the Headworks structure. Complete the
roads around the Sludge Beds.
Primary Clarifier: None
Trickling Filters: Continue installing
filter media. Patch and fmish the exposed
concrete walls.
Recirculation Pump Station: Start
Installing exposed electrical conduit.
Secondary Clarifiers: Install the 48" &
54" steel effluent piping. Place concrete
for the launders.
Distribution Box
Digesters: Place concrete for the roof slab on the Digester Control Building.
Continue installing process piping in the Digester Control Building
Basement. Complete prestressing Digester No. 3 and begin work for
the dome. Start painting the inside of Digester No. 4.
Primary Effluent Junction Box and Piping at Primary Clarifier No. 3
Page 4
CONSTRUCTION PROGRESS SUMMARY
DESCRIPTION STATUS
Notice to Proceed Dated February 9, 1998
Contract Time, Calendar Days 730
Original Completion Date February 8, 2000
Substantial Completion Date May 7, 1999
Time Extensions Approved 25 Days
Construction Revisions Delay Days 29
Revised Completion Date March 8, 2000
Original Contract Amount $29,239,800
Change Orders Approved (92,342.61)
Revised Contract Amount $29,147,457.39
Amount Earned This Period $3,501,442.24
Amount Earned to Date $15,324,797
Percent Complete, $ 52.41
Calendar Days Used 234
Percent Complete, Calendar Days 31.0
Forming Sludge Beds
98-098
Page 5
From: Raul Rojas
To: Alan Tandy
Date: 10/14/98 2:39PM
Subject: UPDATE on Truxtun Avenue Paving
Storm drain work on west bound Truxtun Avenue near Jastro Park has taken more time than expected. It
is now anticipated that Griffith Company has indicated that they will pave Truxtun Avenue Wednesday or
Thursday of next week, October 22nd & 23rd.
BAKERSFIELD
PUBLIC WORKS DEPARTMENT
MEMORANDUM ~
TO: ALAN TANDY, CITY MANAGER
FROM: RAUL ROJAS, PUBLIC WORKS DIRECTOR
DATE: OCTOBER 14, 1998
SUBJECT: IMPROVEMENTS SURROUNDING CENTENNIAL GARDEN
Council Referral WF0017987 1 001
Councilmember Smith requested staff look into improving the lighting on the streets surrounding
Centennial Garden. Also, resurfacing the alleys in the area and the possible installation of a mid-block
crosswalk at Truxtun Avenue & "P" Street.
1. Improving the l~hting on streets surrounding Centennial Garden.
Staff is reviewing the area north of Truxtun Avenue between "N" Street and "Q"
Street for additional street light requirements.
2. Resu~acing the alleys within the area of the Centennial Garden.
The Street Division will not finish resurfacing streets until late November 1998. The
weather during the month of December and January is not suited for resurfacing
projects. The Street Division will start resurfacing alleys in February 1999. The
alleys in the area of the Centennial Garden will be resurfaced at that time. In the
meantime, any potholes in these alleys will be patched.
3. Installation of a mid-block crosswalk at Truxtun Avenue & "P" Street.
The Traffic Engineer reviewed the location at Truxtun and P Streets, in front of the
Holiday Inn. A crosswalk cannot be placed at that intersection because of the left
turn median opening that was installed for the Holiday Inn. Crossing at that location
would conflict with the vehicles using the median opening to access the hotel.
G:\GROUPDA~Referrals\CentennialGarden.wpd
City of Bakersfield *REPRINT*
WORK REQUEST PAGE 1
REQ/JOB: WF0017987 / 001 PROJECT: DATE PRINTED: 10~12~98
REQUEST DATE: 10/08/98
CREW: SCHEDULE DATES
START: ±U~08~98
LOCATION: COMPLETION: 10/19/98
GEN. LOC: FACILITY NODES
FROM:
FACILITY ID: TO:
REF NBR:
REQ DEPT: CITY COUNCIL REFERRAL PRIORITY: HIGH
REQUESTOR: REFERRAL - SMITH ORIGIN: CITY COUNCIL REFERRAL
USER ID: RBARNHAR WORK TYPE: REFERRAL
DESCRIPTION: IMPROVEMENTS SURROUNDING CENTENNIAL GARDEN
REQUEST COMMENTS
***REFERRAL TO PUBLIC WORKS***
SMITH REQUESTED STAFF LOOK INTO IMPROVING THE
LIGHTING ON THE STREETS SURROUNDING CENTENNIAL
GARDEN. ALSO, RESURFACING THE ALLEYS IN THE AREA
AND THE POSSIBLE INSTALLATION OF A MID-BLOCK
CROSSWALK AT TRUXTUNAND "P" STREETS.
Job Order Description: IMPROVEMENTS SURROUNDING CENTENNIAL GARDEN Category: PUBLIC WORKS
Task: RESPONSE TO REFERRAL
Assigned Department: PUBLIC WORKS
START DATE / / COMPLETION DATE / /
BAKERSFIELD C/kLIFORIqlAIq
Editorials
Projects can upgrade 2 city areas
S ometimes neglected sections of Banks, stores and supermarkets have
Bakersfidd at least now can see some moved from the areas in the last few
· light at the end of the tunnel - even if years. Designating the territory as rede-
ithat brightness is not rmv- Velopment projects will
.ding at warp speed. Proposed redevelopment areas help reveme this trend.
The city is going ~ ~ ~ ~ .~ The designation caa
ahead with two redevel- : '~ :~'-'~'.~ help attract businesses
opment projects to help "<~- ~'-~ ~ ~$t. through incentives,
:fight blight over about ~!:~ ~um including a return of a
Pioneer, Old Town Kern ,~'.· ,-~,- business is constructed
~ e~-y~;,_-,,,and the owner agrees
· Change is not going .Tr.q~? ~~2.~. to keep it open for at
to happen immediately, r i :,.-';~ ............ least 10 years.
~999)~ ! lif 'rnia ~ 'e' 7' ' ~ The next key date in
Economic
Development
'u~ dagel a. ~',~ the revitalizati'on
Director Jake Wager -.'~ ...... ;~ ~., .~,.--
'told The Californian. ._../ I .~ ! process is Oct. 26 when
"In redevelopment, the ~ ~ i,. Ave.. _._, ; K L. a public hearing will be
key is not to affect c~ d.~,~ ~L,~ heldat4p.ltL in City
every parcel. It's meant ; Plan;:R Hall on the issue of
to act as a catalyst for i [ Wh't' Ln. ~ ~ 8 ' eminent domain fights.
private invesUnent." ~ .[ This would allow the
A redevelopment $, ~ -. city to acquire private
area allows businesses ~ t ? m~!o, property for public pro-
within the area's bound- · ~anarrun. jects, something that is
aries to borrow public r,~ c^c~ma~^~ rarely used, Wager said.
money for improvements. The money As required by law, project area corn-
comes from property taxes collected mittees will be elected in November
from the businesses in the area. from among project area residents, busi-
The mount to be collected in a rede- ness and community organization repre-
velopment area is detenuined by estab- sentatives.
lishing a base tax year. Then, a small per- They will advise the six-member
.centage of taxes above the base year are Central District Development Agency
put into the redevelopment area's that administers the city's first redevel-
account. Collection of tax money in the opment area - the downtown vicinity.
:two areas probably will not occur until The council and Planning Commission
'2000. Growth in the areas is the key to also must set public hearings on the new
generate continued funding, redevelopment plans with final approval
That should be no problem, according expected by next June:
'to Councilwoman Irma Carson, whose The Downtown Redevelopment pro-
.district includes the two projects, ject took about eight years to take off
Carson, who admirably has pushed with new businesses that sparked a
long and hard for the new redevelop- rebirth of the area.
ment areas, cogently observed: "This These two new redevelopment pro-
will put a new face on both areas and I jects should be approved to allow blight-
think the citizens of those areas will be ed areas in the city a chance to rebound
'pleased... it's a beginning." in the same fashion.