HomeMy WebLinkAbout05/01/2000 B. AKER S F IEL D
· Jacquie Sullivan, Chair
AlOft Tandy, City Manager Patricia J. ·DeMond
Staff: Alan Christensen Randy Rowles
AGENDA SUMMARY REPORT
COMMUNITY SERVICES COMMITTEE MEETING
Monday, May 1, 2000
4:00 p.m.
City Manager's Conference Room
1. ROLL CALL
Call to Order at 4:00 p.m.
Present: Councilmembers Jacquie Sullivan, Chair; Patricia J. DeMond; and Randy Rowles
2. ADOPT APRIL 4, 2000 AGENDA SUMMARY REPORT
Adopted as submitted.
3. PUBLIC STATEMENTS
None
4. DEFERRED BUSINESS
A. ICE SKATING FACILITY
Alan Tandy stated that after the Committee meeting with the large turnout from the community on
April 4th, besides the generous offer at that meeting by Bolthouse Farms to put up $250,000 in
funds to match community fund-raising donations, others have come forward offering possible land
donations for the facility. The County metro park site is still a possibility. Mesa Marin has a site by
the Raceway, although it would have higher development costs due to the topography of the area.
Another, at this time still only a possibility, is a site at an undeveloped 23 acre NOR park adjacent
to Centennial High School off Coffee Road. The downtown location is still a possibility at the
proposed City Center project due south of the arena on "M" Street.
With the matching funds and the land donation options, staff recommend to the Committee that
Council authorize $50,000 from Council Contingency for a feasibility study. One of the
requirements in order to sell non-recourse bonds, so liability does not fall back to the City's General
Fund, is that an investor would want an independed expert, one not connected with the operation
and maintenance of the facility to do a feasibility study to analyze our market and demographics
and come up with a pro forma for the business. We could geta study that is refined so that it is
applicable to more that one site with only little incremental differences that would exist. The bonds
would be secured by the land, the building, and revenues from the facility to get the capital
investment down to what would make a pro forma work so that a knowledgeable investor would buy
o, : ooo FILE COPY
AGENDA SUMMARY REPORT
COMMUNITY SERVICES COMMITTEE
Monday, May 1,2000
Page -2-
the bonds. Staff also recommended that the City commit $200,000 from one-time monies toward
building a facility, to be expended dependent on the $500,000 being raised by the community.
Alan Christensen stated that staff has received input from a number of individuals interested in
fund-raising and the Bakersfield Foundation has been offered for donations. Staff is proposing that
we assist by having some initial organizational meetings, maintain a list of interested parties and
offer support anyway we can to help that process get started. The community should then be able
to do the fund-raising on their own to promote the private donations that are needed for their
matching funds.
The Committee discussed the $30,000 financial assistance that was given to the Garden this year
to provide ice and would like that to continue for another season or until an ice facility can come
to fruition.
The Committee unanimously recommended forwarding an Administrative Report to the full Council
recommending: 1) $250,000 of matching funi:ls be reserved toward construction of an ice facility
from one-time monies in the budget, dependent on the community raising the matching $500,000;
2) $50,000 from Council Contingency be used to pay for a feasibility study; and. 3) City staff to
provide assistance to help promote initial fund-raising efforts using the Bakersfield Foundation for
donations, and that a link be set up on the City's website for interested parties to obtain information.
B. DISCUSSION AND POSSIBLE COMMITTEE RECOMMENDATION REGARDING TRAFFIC
MEDIAN STANDARDS THROUGHOUT THE CITY
Raul Rojas gave an update on two median test sites that were done, one on California Avenue
across from Martin Luther King, Jr. Park and the other on H Street just south of VVhite Lane.
These sites were chosen because curbing was already in place. Public Works and Recreation.
and Parks departments did the work with the exception of the concrete which was contracted out.
The cost was approximately $3 per square foot. If the median work is contracted out and new
curbing is required, it will cost closer to $4 per square foot.
When a new base standard is approved, then each year depending on availability of resources
and any grant money that can be applied for, money can be budgeted to convert the old asphalt
medians in the older parts of the City over to the new standard. In next year's proposed budget
there is $150,000 in gas tax monies and $150,000 in block grants that will convert about one mile
depending on the width of the median.
The Committee liked the test median on California Avenue, especially the round planters, and
recommend that it be the new base standard to be used when upgrading medians. The
Committee directed staff to compile a list of medians that will have the most visual impact, are
heavily traveled and in most need of repair, keeping in mind any pavement/construction projects
that need to be done first. Having a plan adopted by the City Council will enhance the City's
chances of getting any State funds or TE (Transportation Enhancement) federal funding that could
be applied for if funds are made available.
The Committee unanimously recommended forwarding the plan to the full Council for approval and
adoption.
AGENDA SUMMARY REPORT
COMMUNITY SERVICES COMMITTEE
Monday, May 1, 2000
Page -3-
5. NEW BUSINESS
A. ROCKIN' BY THE RIVER CONCERT SERIES
Stan Ford explained that the Recreation and Parks Department would like to expand the Rockin'
by the River concert series for the Fall of 2000 and instead of using local talent as they did in
1999, provide some nationally known name bands. The proposal is for a series of three concerts,
freeto the public, on consecutive Tuesdays in the evening at Yokuts Park featuring classic rock
from the late 60's and early 70's. The proposed bands would be the type of entertainment that
perform at night club level in the range of $5,000 per performance, so they would not be
competing with events at concert theaters or the Kern County Fair. This series would be in
addition to the concerts scheduled to be held in City parks in the different wards. The bigger name
bands would not be suitable for neighborhood parks due to noise and large crowds. Yokuts Park
was chosen because of its central location, it is unique and set apart from residential areas so
sound would not create a problem, and large enough with a lovely setting of grass, trees and the
river.
Staff is recommending contracting with an established entertainment promoter to provide the
bands, coordinate staging, provide equipment and related event support. The cost is not to
exceed $31,000 and funds are available in the current year's budget and included in the proposed
2000-01 budget. After the first event, it may be possible to get soft drink companies or local radio
stations as sponsors, which would help defray the cost.
The Committee unanimously approved of the concert series and directed staff to forward the
agreement to the City Council for approval.
6. ADJOURNMENT
The meeting was adjourned at 5:30 p.m.
Attendance: Staff: City Manager Alan Tandy; Assistant City Manager Alan Christensen; City Attorney
Bart Thiltgen;' Public Works Director Raul Rojas; Public Works Engineering Services Manager Jack
LaRochelle; Public Works Civil Engineer Ted Wright; Recreation and Parks Director Stan Ford; and
Assistant Recreation 'and Parks Director Allen Abe.
Public: Matthew Riley; Andre Radandt, Bolthouse Farms; Ralph Harrison; Barbara Grimes, Tanya
Andrews; Scott Grundhofer and Linda Grundhofer.
cc: Honorable Mayor and City Council
S:~AC\CSCommittee\cs00may01summary.wpd