HomeMy WebLinkAbout10/05/1994 BAKERSFIELD
Randy Rowles, Chair
Kevin McDermott
Patricia M. Smith
Sta~ Gail E. Waiters
AGENDA
URBAN DEVELOPMENT COMMI'I-rEE
Wednesday, October 5, 1994
12:15 p.m.
City Manager's Conference Room
Second Floor - City Hall
1501 Truxtun Avenue
Bakersfield, CA
1. ROLL CALL
2. APPROVAL OF SEPTEMBER 14, 1994 MINUTES
3. PRESENTATIONS
4. PUBLIC STATEMENTS
5. DEFERRED BUSINESS
A. ADVERTISING ON SIDEWALKS - Hardisty
B. TRANSPORTATION IMPACT FEES UPDATE - Kloepper
C. STATUS REPORT ON FREEWAYS - Kloepper
D. WASTEWATER TREATMENT PLANT - Kloepper
6. NEW BUSINESS
A. TREE FOUNDATION - Andersen
B. POSTED STREET SWEEPING PROGRAM - Rojas
7. ADJOURNMENT
GEW:Jp
FILE COPY
MEMORANDUM
September 20, 1994
TO: ALAN TANDY, CITY MANAGER
GENE BOGART, WATER& SANITATION MANAGE~~ ~
FROM: LELAND J. ANDERSEN, COMMUNITY SERVICES M~AGER~
SUBJECT: TREE FOUNDATION - KERN RIVER PLANTING PROJECT
(Council Referral No. 13753)
At the August 24, 1994, Council meeting Rick Hewett, representing
the Tree Foundation, spoke and submitted a request asking the City
Council to direct staff to supervise the tree planting project. In
addition Councilmember Rowles requested that this item be reviewed
by the Urban Development Committee who will then report back to
Council.
On September 20, 1994, City staff met with representatives from the
Tree Foundation and the Kern River Foundation to discuss this
issue. During the course of the meeting discussion centered around
the development of plans and specifications for the installation of
irrigation'as well as the'planting of materials. A time frame was
established that would help facilitate this plan. Plans are to be
prepared and submitted to Parks Division for review during the week
of September 26. Upon approval of plans, the Tree Foundation will
solicit bids.
It is anticipated that the bid process and installation of
irrigation will be completed by the end of November, with planting
to be completed by the first week of December.
The Tree Foundation requested the removal of some non-native trees.
A walk-through with City staff will be coordinated by the
Foundation to determine which ones may be removed.
All funding for construction and installation of irrigation and
planting of trees will be funded by Texaco~ The Tree Foundation
will be coordinating volunteers to oversee the actual installation
and planting of trees in early December. In order to meet the
schedule it will be necessary to place this on a fast track. The
Urban Development Committee will review this issue on October 5th
and submit a recommendation to full Council at the earliest
possible date.
On going, long term, maintenance was also discussed. Typically,
maintenance will be absorbed within the Parks and Water Divisions.
Because of increased responsibilities, additional funding will be
necessary beginning in FY 1995-96.
Mr. Alan~Tandy
September 20, 1994
Page Two
In summarY, this project appears to be well coordinated and is the
type of development outlined in the Kern River Parkway Master Plan
for this area.
If you should have any questions or need additional information,
please contact either Lee Andersen or Gene Bogart at your
convenience.
LJA/lg
cc: Rick Hewett, Tree Foundation
Rich O'Neil, Kern River Foundation
Raul Rojas, Public Works Director
Frank Fabbri, Parks Superintendent
REC'D & PLACED ON FILE
~ COUNCIL MEETING OF
TREE .FOUNDATION OF KERN ,~ :-9 ~/- 9 c~ ~-. c,_
Kern River Tree Planting
Fail, 1994
Kev Features;
1. Stream Restoration as well as beautification
2. Enhancement of Bike Path
3. Enhancement of Jogging Trail
4. Enhancement of Adjacent Group Picnic Area
5. Caiifornia native plant theme will be used
6. Annuai grass meadowland to be seeded with wildflowers for spring display. Dry grass
to be mowed for fire control. High volume turf sprinkler heads will be available for
additionai fire prevention
7. Trees will be irrigated with drip system
8. Irrigation system will be "Maxicom" ready
9. Four inch main will extend "end to end" of project site so that existing trees can be
incorporated, aiso into "Maxicom"
10. Design and construction will be accomplished by licensed professionals
11. Tree placement will respect oilfield maintenance road as well as existing jogging trail and
bike path
12. Actuai tree planting will be done by Tree Foundation, Texaco volunteers and community
volunteers
13. Funding will be provided by Texaco via the Kern River Foundation
14. Tree Foundation and Kern River Parkway goais met by project
15. Non-native "invader" trees will be removed
16. Select group of existing snag trees (i.e., dead cottonwoods) will be retained for wildlife
vaiues.
REC'D & PLACED ON FILE
AT COUNCIL MEETING OF
KERN !~I VI,:R --
ADMINIST T1VE REPORT
TO: Honorable Mayor and City Council APPROVED
FROM: Raul M. Rojas, OEP~TM~~~
Public Works Director
C~TY A~rORN~ N/A
DATE: September 16, 1994
'~' CITY MANAGER ~
SUBJECT: Posted Street Sweeping Program report from the Public Works Department, dated
July 1994. (Response to Council Referral Record #13515)
RECOMMENDATION: Staff recommends to refer the matter to the Urban Development Committee
for review and recommendation.
BACKGROUND: The attached report presents four options to be considered regarding a posted
street sweeping program. These include: 1) Limited Expansion of the Current Pilot Program; 2)
Full City Wide Posted Program; 3) Ten-Year City Wide Posted Program;
4) Non-Posted Voluntary Compliance Program.
1. Limited Expansion of the Current Pilot Program
This option explores two possible schedules in expanding our current pilot program.
A Two-Week Schedule would be the most desirable, but also the most expensive. Additional
sweeper operators would have to be employed after posting 50 miles of streets and after
every 110 mile increment thereafter. For enforcement, police service technicians would
have to be hired after posting every 55 mile increment of streets.
A Once Per Month Schedule, while not as effective as the previous schedule, it would
double the posted street miles prior to employing additional personnel. Equipment costs
for employees and signing expenses would remain the same with either schedule.
Our current 1994-95 budget has approximately $6,000 for a limited expansion of our current
pilot program. This would provide funding to sign up to one mile of street.
Page I of 3
16, 1994, 2:04pm
ADMINISTRATIVE REPORT
Honorable Mayor and City Council
Meeting Date: September 28, 1994
Consent Calendar
2. Full City Wide Posted Program
Again, this program also looks at two possible schedules.
A Two-Week Schedule would require the employment of 4 additional operators and 5
additional police service technicians along with their related equipment. Over 47,000 signs
would be required City wide. Initial implementation cost would be approximately
$4,650,000.00 with subsequent annual maintenance costs of approximately $846,000.00.
A Once Per Month Schedule would reduce costs somewhat. Implementation would cost
approximately $4,100,000.00 and subsequent annual maintenance would be approximately
$508,000.00. A major portion of these costs would be signing which would be the same with
either schedule.
3. Ten-Year City Wide 'Posted Program
For this program we looked at both a two-week schedule and once per month schedule over a
10-year period of adding approximately 53 miles of posted streets each year.
On a Two-Week Schedule we would need to add an additional sweeper operator on our 1st,
3rd, 5th and 7th years. Additional police service technicians would be required on years 1,
3, 5, 7, and 9. Once fully implemented, the additional annual maintenance of this program
would be approximately $846,000.00.
The Once Per Month Schedule would require an additional sweeper operator on the 3rd
and 7th years of the program. Additional police service technicians would be needed on
the 2nd, 4th, 6th and 8th years. Upon full implementation, the additional annual cost of
this program would be approximately $508,000.00.
4. Non-Posted Voluntary Compliance Program
The key to this program would be a public information notice published each week in the local
newspaper. A program of this nature would be very popular with most City residents and would
not lock us into a rigid schedule. This would be a major advantage in flexibility when dealing with
varying budgets.
Page 2 of 3 ,
16, 1994, 2:04pm
ADMINISTRATWE REPORT
Honorable Mayor and City Council
Meeting Date: September 25, 1994
Consent Calendar
Conc/us/on
Based on some of my past experiences in the previous cities, posted street sweeping throughout
the city is very costly and difficult to maintain because of equipment failures, manpower
requirements and very little flexibility in scheduling. The posting requirements are such that it
requires signs to be put up throughout the city; consequently, the citizens disapprove the posting
of signs in front of their residences.
In addition, the requirement to have the parking enforcement follow the sweepers around
throughout the City is the only way to enforce it. Once parking restrictions are enforced, there is
quite a bit of resistance from the residents because they get a ticket for being parked out there for
just a few minutes, or maybe their vehicle is temporarily disabled i.e, battery dead; but whatever
the reason, they get cited.
in conclusion, it is our recommendation that consideration be given to option 4, which is a
Non-Voluntary Compliance Program and option 1, Limited Expansion of the Current Proeram. which
is budgeted at $6,000. We could also take a look at the high non-compliance areas, such as areas
where we have apartment buildings, where there are quite a bit of vehicles that are parked out into
the street.
SE28PW3.CC
.~, Page 3 of 3
September 16, 1994, 2:09pm
CITY OF BAKERSFIELD
EXPANSION, OPTIONS AND COST ANALysIs
POSTED STREET SWEEPING PROGRAM
COUNCIL REFERRAL RECORD % 13515
PREPARED BY:
MARK LEAL
STREET SUPERINTENDENT
PUBLIC WORKS DEPARTMENT
JULY, 1994
HISTORY
Currently, in the City of Bakersfield, there are 671 miles of
streets. Based on our 1993-94 Street Cleaning Analysis
(Attachment 'A'), there are 529 residential street miles swept by
our 6 daytime operators. With the exception of the 2 miles in our
posted areas, the average sweeping frequency is once every 15
working days. There are two additional operators on our night
shift who sweep many of our arterial and commercial routes. The
sweeping frequency on these routes will vary from approximately
once every 15 working day on the arterials to twice a week on some
of the commercial routes.
Our pilOt program for posted sweeping.in designated areas has
been in implementation since November of 1991. Two areas
comprising 2.2 street miles have continued permanently with .this
program:
1. The apartment complex bordered by Marsha Street, Belle
Terrace, New Stine and Montclair Street. (1.4 miles
Ward 5).
2. The apartment and commercial complex consisting of Noel
Place, Dana Street north of University Avenue and Bishop
Drive (.8 miles Ward 3).
The program seems to be working well with an established
schedule of sweeping every 2 weeks, on the first and third Tuesday
of each month. 'As the program now exists, there are virtually no
complaints from residents in either of these neighborhoods.
We may consider several different options in the expansion of
our Posted Street Sweeping Program. These include:
1. Limited phased expansion of the current p~lot program.
2. Full city wide posted program.
3. Ten year phased city wide program.
4. Non-posted voluntary compliance program.
For simplicity, all discourse in this reDort will assume a no
growth scenario of maintaining a constant 529 residential street
miles. The following is a concise look into each of these plans.
1. %IMITED EXPANSION OF T~ CUR~WNT_ PILOT PROGRAM
As in our current regular sweeping program, a three week
schedule would be ideal. However, such a program would be
virtually impossible to sign without confusion. Consequently, for
future expansion, we should consider either continuing the two
week program or changing to a once per month schedule.
2 ~ sc~Dur.~
Increas£ng out posted program on a 2 week schedule would be
the most desirable to the public but obviously, almost twice as
expensive as a once per month schedule. There are, however,
factors that reduce costs on a 2 .week schedule. Often, fewer
passes may be required to clean a given area. Also, if there is
less debris to clean, there will be less wear and tear on the
equipment. Probably, the most important factor is that our
streets will be cleaner for a longer period of time.
Using this 2 week schedule, we have estimated that we would
need to employ our first additional Motor Sweeper Operator after
posting.50 miles of streets. Thereafter, an. additicnal operator
would be required after approximately every 110 miles of posted
streets. The first Police Service Technician would also be
required after the first 50 miles of posted streets. An
additional technician would be' require~ after each additional 55
miles of posted streets. In addition to these costs, a motor
sweeping machine would have to be purchased for each operator.
Also, our current policy is to provide a 50% back up of sweeping
machines. Therefore, a back up machine would be required for
every 2 operators. This is a Very important requirement in
meeting a rigid schedule since sweeping machines are typically a
high maintenance item. Each Police Service Technician would also
require the purchase of a parking control vehicle. Finally, every
mile of posted streets will require 90 signs. Attachment 'B'
.illustrates cost'of salaries, overhead, equipment and signs.
ONCE PER MONTH SCHEDULE
The most cost effective program would be to lengthen the
sweeping frequency to once per month. Even though the actual
street cleaning efficiency may not be as good as a 2 week
schedule, many areas that are currently not swept at all, due to
parked vehicles, would now get service. It is our experience in
discussion with the public, that many people would prefer a
schedule. Under this proposal, the first MotOr Sweeper Operator
would be employed after posting approximately 120 miles of streets
and subsequent operators would be needed after every additional
240 miles of posted streets. The first Police Service Technician
would be needed after posting 120 miles of streets and subsequent
technicians would be required after each additional 120 miles.
With either schedule, the most efficient operation would be
to expand into adjacent or nearby neighborhoods. This would
reduce travel time, maintain continuity, and minimize scheduling
problems. The most effective method of expansion would be to
target neighborhoods identified by Resolution No. 206-91
(Attachment 'C'). However, if any of the parameters are changed,
such as sweeping days, hours or streets, a new resolution would be
required.
Our current 1994-95 budget has approximately $6,000.00 for a
l~m~ted expansion of our pilot program. This would provide
funding to sign up to one mile of street. E~ther one of the
following two identified areas or portions of each could be
selected.
AREA % 1 (WARD 1, .91 MILES)
Forrest Street From Oleander to 'H' Street
Cherry Street From Oleander to 'H' Street
Dracena Street From Oleander to 'H' Street
'F' Street From Palm to Dracena
'G' Street From Palm to Dracena
AREA ~ 2 (WARD-3, .95 MILES)
Christmas Tree From Dana to Wenatchee
Crest Drive From Dana to Wenatchee
Church Avenue From Dana to Eton'
As in our initial pilot program, public awareness would be one
of our foremost concerns. We would start with a small article in
the Bakersfield Californian newspaper. This is then followed with
explanatory letters mailed directly to the residents. Several
issues will be made clear in this mailer: 1) There will be strict
enforcement of the policy by the Police Department~ 2) A tentative
sweeping schedule will be enclosed and; 3) A high percentage of
the residents must support the program. To determine Item ~3, the
mailer will include a self-addressed card on which 'residents can
vote to support or oppose the program.
Implementation of this expanded program could be completed
within 120 days after approval.
2. FULL CITY W~DE POSTED PROGRAM
2 WEEK SCHED~.~
A full city wide program would be a major commitment in funds
and resources. We estimate that in order to meet the sweeping
requirements of a fixed 2 week schedule, 4 additional operators
would be needed bringing our total number of daytime residential
routes and operators to 10. This would require as per our present
policy, 6 more motor sweeping machines, including 2 back up units.
Police enforcement will be required for a successful program.
Lieutenant Cleo Blackburn of the Bakersfield Police Department has
estimated that they would require a minimum of 5 full time Police
Service Technicians and their related equipment to keep up with 10
sweeping routes. There would., of course, be revenue income from
the citations issued but this number is unknown.
Proper signing is one of the major items to be considered.
At 90 signs per mile, 47,600 signs would be required to post our
529 miles of streets. General Services has estimated that a 2 man
crew installing 20 signs per day would require 9 years for
ins=alia=ion. In addition, there is the cos= of the signs and
equipment involved. Consequently, it seems the mos= reasonable
solution would be to con=tact this operation. The General
Services estimate is a contracted, installed price, including all
labor and material of $70 per sign.
Attachmen~ 'D' reflects the additional costs of approximately
$4,651,000.00 required in the Street Cleaning Section to implement
a full city wide posted sweeping program based on a 2 week cycle
time. Attac~n~ 'E' represents the annual additional, cost ef
approximately $846,000.00 required to maintain the program.
ONCE PER MONTH SCBEDUT. R
Reverting to a once per month schedule would reduce costs.
while still costly in both funds and resources, there would, a~
least, be .an absolute schedule that the public could rely on. In
order to meet this schedule we have estimated that we could reduce
the required additional street cleaning personnel and equipment by
approximately one half. With this program, 2 more Mo=or Sweeper
Operators would be needed along with 3 more motor sweeping
machines including i back up machine. This would bring our total
number of daytime routes and operators to 8. The Police
Department's estimate of 1 Police Service Technician for every 2
sweeping routes would translate into 4 more Police Service
Technicians since we would now have a total of 8 routes. In
addition, 4 police service vehicles would also be required.
Again, revenue from citations is unknown. However, it is assumed
that the large number issued initially would drop off as the
public became accustomed to the schedule. The required signing
would obviously, remain the same as in the 2 week program.
Attachment 'F' reflects the additional cost., above our regular
street cleaning budget of $4,100,000.00 to implement this program.
The annual maintenance cost of $508,000.00 is shown in Attachment
'G'. In addition ~o the costs shown in these and previous charts,
there would be additional expense that would be difficul~ to
compute a= ~his time. This would include, but no= limited to,
mechanics and service personnel to maintain the equipment and also
General Service personnel to maintain over 47,000 signs.
3. PHASED CITY WIDE POSTED PROGRAM
A planned city wide program may also be considered.
Obviously, funding could be used as available or distributed over
any time increment such as 10 or 15 years. However, the cost of
signing in any proposal would remain fixed at approximately
$6,000.00 per mile. Some estimates of anticipated costs for
either 2 weeks or once per month schedules follow. For the
purpose of illustration, these are based on a 10 year plan and do
not reflect any additional growth or inflation.
This plan would be very similar to the 2 week schedule of
Proposal ti, the limited expansion of the current program, since
we would be adding approximately 53 miles of posted streets each
year. The first additional Motor Sweeper Operator would be
employed during the first year. Subsequent operators would be
hired on years 3, 5 and 7. The first Police Service Technician
would also be required during the first year and additional
technicians would need-to be employed on years 3, 5, 7 and 9.
upon complete ~mplementation of this proposal, the annual
maintenance cost would be approximately $846,000.00 as _shown in
Attachm~ut 'E'.
ONCE PER MONTH SCHEDULE
The once per month schedule of Proposal %1 would be very
similar to this plan. It is anticipated, under this proposal,
that the first Motor Sweeper OPerator would be needed during the
third year and a second operator would be required on about the
seventh year. The first Police Service Technician would need to
be employed during the second year and additional technicians
hired during years 4, 6, and 8. As in the 2 weeks schedule, this
plan would also add approximately 53 miles of posted streets per
year and once fully implemented,, would cost approximately
$508,000.00 per year to maintain as shown in Attachment 'G'.
4. NON POSTED VOLUNTARY COMPLIANCE PROGRAM
The key to this program would be a public information notice'
published each week in the local newspaper. Our discussions with
Mr. Mike Triney, Metro Editor of the Bakersfield Californian, have
been very favorable. If requested, he has agreed to publish a
weekly public service announcement of street sweeping routes for
the following week. This announcement would list bordering
streets of neighborhoods scheduled for that week and would also
ask the residents to remove parked cars. Their Circulation Manager
states that their weekend coverage reaches almost 70% of all
households within the City of Bakersfield. Mr~ Wayne Wedgeworth,
their Advertising Manager, claims 100% coverage with the use of
their Cal Direct supplement delivered to all non subscribers once
a week. The latter would have a small fee of approximately $50
per week.
A major advantage of this program is that, for now, we would
be able to keep our current 3 week sweeping schedule. It is our
experience, that this is an excellent compromise between the 2
week schedule and the once per month schedule. Obviously, there
will be a number of vehicles that are not moved, however, we feel
that residents who are indeed concerned with the cleanliness of
their streets will make every effort to comply just as they have
for their refuse collection schedule. Another factor contributing
to the neighborhood cleanliness of this program would be. the lack
of offensive signs that would otherwise be required.
This proposal is, by far, the most requested by the public.
While many people say they would welcome the schedule, they would
prefer the flexibility of the voluntary program in instances such
as; visitors, unusual working hours, unavailable off-street
parking, or other temporary inconvenient situations.
CONCLUSION
It is the recommendation of Staff that primary consideration
be given to option ~4 "Non Posted Voluntary Compliance Program."
This could be implemented on a trial basis and results studied as
to the success. Secondary consideration should be given to Option
#1 "Limited Expansion of the current Program" on the once per
month schedule.
A~I'A~ 'A'
s'razET ~(; ~ALYS~S
1993 - 94
TOTAL STREET MILES 661
BIKE PATH MILES 9.$
.AIRPORT MILES
STATE ROUTE MILES 6.$
ALLEY MILES 1.2
PARKING LOT MILES 20
TOTAL MILES SWEPT 703.2
DAY ROU'I~S
RESIDENTIAL MILES
BIKE PATH MILES 9.5
AIRPORT MILES 5
TOTAL DAY ROUTE MILES 543.5
ARTERIAL ROLrTES (NIGHT}
ARTERIAL MILES 132
PARKING LOT MILES 20
STATE ROUTE MILES 6.5
TOTAL ARTERIAL MILES 158.5
NIGHT COMMERCIAL ROUTES
COMMERCIAL AREA MILES
ALLEY MILES 1.2
TOTAL COMMERCIAL MILES 19.2
PERSONNEL
* MOTOR SWEEPER OPERATOR $ 34,908.00
** OVERHEAD $ 30,549.00
TOTAL $ 65,457.00
* POLICE SERVICE TECHNICIAN $ 29,130.00
** OVERHEAD $ 23,233.00
TOTAL $ 52,363.00
PURCHASE ANNUAL RENTAL
MOTOR STREET SWEEPER $120,000.00 $ 50,184.00
PARKING CONTROL VEHICLE $15,000.00 $ 4,200.00
MATERIAL (SIGNS)
1 MILE 90 SIGNS AT $70.00 $ 6,300.00
INSTA! .I.I~D BY CONTRACT
'NOTE: ' Direct labor cost only.
*' Overhead includes fringe benefits, operating costs, departmental
overhead, and any applicable support services cost.
RESOLUTION NO. 206.91
A RESOLUTION RESTRICTING PAIHClNG ON CERTAIN
PUBLIC STREE~ FOR THE PURPOSE OF STREET
SWEEPING
~lllRl~, the Council of the City of Bakersfield desires
to keep the public streets of the City of Bakersfield in a.clean,
aesthetically pleasing condition; and
~fll~lt~kS, the parking of motor vehicles along certain city
streets during all hours of the day and night effectively-prevents
the City street cleaning equipment from cleaning portions of the
street where cars are parked; and
i/glrHEAS, it is the desire of the Council to institute a
program in four different areas of the City of Bakersfield where
parking will be prohibited, as signed, between 8:00 a.m. and 12:00
noon on the first and third Tuesday of each month; and
WHEREAS, the four areas above referenced are described in
Exhibit "A" which is attached hereto and incorporated herein .by
reference; and
WHEREAS, California Vehicle Code, S 22507, allows cities,
by resolution, to restrict the parking of vehicles along any street
or portion thereof during all or certain hours of a day.
NON, THEREFORE, BE IT RESOLVEDby the Council of the City
of. Bakersfield as follows:
1. All the foregoing recitals are true and correct.
2. Parking shall be prohibited, as Signed, along City
streets set forth in Exhibit "A" between the hours of 8:00 a.m. and
12:00 noon on the first and third Tuesdays beginning in November
1991.
ooo ..........
MEMORANDUM
NO PARKZ~IG FROM 8..00 A.H. TO 12 :O0 NOON OH EVERY FIRST & TIIIRD
TUESDAY OF EACH MONTI!
AREA ~! - MARSllA STREET from Palmer Street to City Limits
PALMER STREET from Mareha Co Demeter
TAYLOR STREET from Demeter Co Belle Terrace
CO~IAH WAY from Taylor to New Seine
IILINTER AVENUE from. Taylor Co Lansing
LANSING DRIVE from llunCer Co So. Honcclatr
: SO. MONTCLAIR from Lansing Co Stockdale lfwy.
AREA ~2 - BELLE TERRACE from New Stine to Old Stine
NORDIC DRIVE from New Stine to Valhalla
RoBERTA WAY from Valhalla to Nimrod
PA~KWOOD CT. from Nimrod to HcDonald
NORSEMAN ST. from Valhalla to McDonald
FJORD STREET from New Stine to Valhalla
A}~RICAN AVE. from Valhalla to McDonald
VALIIALLA DR. from }ling to Belle Terrace
McDONALD WAY from Ming to Belle Terrace
GEMINI CT.
VIRGO CT,
LIBRA CT.
SCOP~IO CT.
TAURUS CT.
AQUARIUS CT.
EXJIIBIT "A"
(Page I of 2)
NO PARKING FROM 8500 A,M,. TO 12..00 NOON ON EVERY FIRST & THIRD
TUESDAY OF EACH MONTIIo
AREA ~3 - BLANCHE ST. from Oleander to "H" St.
ORANCE ST. from Oleander to "II" St.
HAPLE AVENUE from Oleander Co "fl" SC.
FOREST ST. from Oleander Co "Il" SC.
C/fERRY ST. from Oleander Co "Il" SC.
DRACENA ST. From Oleander Co '*Il" St.
"F'* STREET from Palm co Dracena
'*C,** STREET from Palm Co Dracena
AREA ~4 - DANA STREET from University Co Churctt
NOEL PLACE from Christmas Tree Ln. to Church
BIS[lOP DRIVE from Dana Co Church
CIIRIST~S TREE LN, from Dana to Wenatchee
CREST DRIVE from Dana to Wenacchee
CIIURCIi AVENUE from Dana to ECon
ETON STREET from Christmas Tree to Panorama
SUMMIT CIRCLE
EXillB IT "A"
(PaBe 2 of 2)
A~'rACHMENT 'D'
2 WEEK SCHEDULE
ANNUAL ADDITIONAL COST. CFI'YWIDE POSTED PROGRAM
PERSONNEL
4 EA - * MOTOR SWEEPER OPERATOR $139,632.00
· ' OVERHEAD $122,196.00
5 FAt * POLICE SERVICE TECHNICIANS $145,650.00
· * OVERHEAD $116.165.00
TOTAL LABOR $523,643.00
EQUIPMENT ANNI.Ia.L RENTAL
6 EA MOTOR STREET SWEEPER $720,000.00
5 EA. PARKING CON'I~OL VEHICLE $ 75,000.00
TOTAL LABOR $795,000.00
MATERIAL (SIGNS)
47,600 SIGNS $70.00 EACH INSTAI.!.FD $ 3,332~000.00
BY CONTRACT
TOTAL COST $ 4~650~643.00
*NOTE: * Direct labor cost only.
** Overhead inciudea Lringc benefita, operating costa, departmental
overhead, and any appllcabie support scrvicea coat.
PEI~ONNEL
4 EA * MOTOR SWEEPER OPERATOR $139,632.00
· *' OVERHEAD $122,196.00
5 EA - * POLICE SERVICE TECHNICIANS $145,~0.00
· * OVERHEAD $116,165.00
TOTAL LABOR $523,643.00
EQUII~MENT ANNUAL RENTAL
6 EA MOTOR STREET SWEEPER $301,104.00
5 EA PARKING CONTROL VEHICLE $ 21,000.00
TOTAL EQUIPMENT $322,104.00
TOTAL COST $845,747.00
*NO'FE: * Direct labor cost oniy.
** Overhead includes fringe benefits, operating costs, departmental
overhead, and any appilcable support services cost.
ATTACHMENT ,!~
ONCE PER MONTH SCHEDULE
INITIAL COST . CTrY WIDE POSTED PROGRAM
PERSONNEL
2 EA - ' MOTOR SWEEPER OPERATOR $ 69,816.00
*° OVERHEAD $ 61,098.00
4 EA * POLICE SERVICE TECHNICIAN $116,520.00
** OVERHEAD ~ 92,932.00
TOTAL LABOR $340,366.00
Egun'~mNT
3 EA MOTOR STREET SWEEPER $360,000.00
4 EA PARKING CONTROL VEHICLE ~ 60,000.00
TOTAL EOUIPMENT $420,000.00
.MATERIAL (SIGNS)
47,600 SIGNS $70.00 EACH INSTAI_t ED BY $3~332~000.00
CONTRACT
TOTAL COST $4,092,366.00
*NOTE: * Direct labor cost only.
'* Overhead includes t'ringe benefits, operating costs, departmental
overhead, and any applicable support services cost.
ATTACHMENT 'G'
ONCE PER MONTH SCHEDULE
ANNUAL ADDITIONAL COST - CITYWIDE POS'gED PROGRAM
PERSONNEL
2 Eat * MOTOR SWEEPER OPERATOR $ 69,816.00
" OVERHEAD $ 61,098.00
4 EA * POLICE SERVICE TECHNICIANS $116,$20.00
· * OVERHEAD ~ 92,932.00
TOTAL LABOR $340,366.00
EQUIPMENT ANNUAL RENTAL
3 EA MOTOR STREET SWEEPER $150,552.00 .
4 EA PARKING CONTROL VEHICLE $ 16,800.00
TOTAL EQUIPMENT $167,352.00
TOTAL COST $507,718.00
· NOTE: * Direct labor cost only.
· ' Overhead includes gringe benefits, operating costs, departmental
overhead, and any applicable support services cost.
D4~YI~.KpT
BAKERSFIELD
PUBLiC WORKS DEPARTMENT
MEMORANDUM
TO: ALAN TANDY, CTTY NAHAGER
FROM: RAUL ROJAS PUBLIC WORKS DIRECTOR
DATE: JULY 6, 1~94
SUBJECT: Council Referral Record #13515
STREET SWEEPING PROGRAM (Smith)
At the Council meeting of June 15, 1994, Councilmember Smith
requested staff look into the feasibility of expanding the street
sweeping program and notiflca=lon to the residents.
Attached for Council distribution is the Street Division's
preliminar~ report regarding the Po~d
Staff will continue to further study the Street Sweeping Program.
Additional information will follow.
Attachment
B A K E R $ F I E L D:
PUBLIC WORKS DEPARTMENT
MEMORANDUM
Ba~d on our 1992-93 Street Cleaning Analysis, there are 525 residential
street miles. (See Attactunem
Although we currently have 2 miles of residential streets posted in two parts
of the City, we plan to review other neighborhoods that would lend
themselves to a scheduled sweeping program. However, before we propose
expansion of the Posted Street Sweeping Program, there are two important
items we must determine:
I. Personnel and Equipment.
It is absolutely necessary to have adequate sweepers and sweeper
operators to mamtmn a sweeping schedule if parking is controlled by
signs. The General Services Division will aJso have to review their
availability to install the signs.
2. Enforcement Policy.
We will consult with the Police Department as to their availability to
enforce the posted policy. A program requiring posting of streets
would be ineffective without strict enforcement.
Once we determi-e the feasibility of expanding the Street Sweeping Program,
we will submit a list of areas for Council or Committee review. The list will
include the cost and needs to implement the program within a designated
area. As in our imtial program, public awareness is our foremost concern.
We would start by mailing letters directly to residents. There will be a self-
addressed card on which residents can vote in favor or oppose posted s~eet
sweeping in their neighborhood.
July 1, 1994
RAni Rojas, Pubflc Works Director
C3ty Council RererrM Record #L3S1S
STREg~ SWEEPING PROGRAM (Smith)
Two important issues will be made clear to residents: 1) There w/Il be strict
enforcement of the posted street sweeping poi/cT by the Police Department,
,. and; 2) at least 90% of the res/dents must support the program. ALso, the
residents will be informed about the sweeping schedule. Thh phase of the
program will be the last step implemented.
Review of items 1. and 2. will be completed within two weeks. We already
have a l/st of areas that would benefit from a posted street sweeping program.
However, we w/ii keep you informed as to our progress.
NOTE: At this rime we are provid/ng you with an estimated cost to
provide posted street sweeping in ail res/denfiai streets. (See
Attachment
Attachments
A~:f. ac. hmen~:' "A" '
STREET CLEANING ANALYS IS
1992 - 93
TOTAL STREET MILES 657
BIKE PATH MILES 9.5
AIRPORT MILES 5
STATE ROUTE MILES 6.5
AT.nEY MILES 1.2
PARKING LOT MILES 20
TOTAL MILES SWEPT 699.2
DAY ROUTES
RESIDENTIAL MILES 525
BIKE PATH MILES 9.5
AIRPORT.MILES 5
TOTAL DAY ROUTE MILES' 539.5
THOROUGHFARE ROUTES INIGHT~
THOROUGHFARE MILES 132(APP~OX. 20~OFS~7~
PARKING LOT MILES 20
STATE ROUTE MILES 6.5
TOTAL THOROUGHFARE MILES 158.5
NIGHT COMMERCIAL ROUTES
COMMERCIAL AREA MILES 18
ALLEY MILES 1.2
TOTAL COMMERCIAL MILES 19.2
Atmehnmm
Estimated cost to implement Posted Street Sweeping on $2~ miles of residential streets:
Posting would require six (6) signs per block or approximately ninety (90) Si..~ms per
.mile for a total of 47,2.50 signs. Si~, post and installation would be $70 per sign.
Total cost would be $3,307,500 or $6,300 per mile.
2. Personnt/& ~___uip_ment.
Four additional sweepers would be needed at a cost of $120,000 per unit. Two of
these sweepers would be used as back-up units. Two additional Sweeper Operators
would be needed at a cost of 570,440 per year.
Total cost of additional Personnel and Equipment $$$0,400.
Estimate does not include the General Services Division and Police Department's
cost or needs.
CITY COUNCIL REFERRAL '-'"~'~"'"'~ ~-'"?'~~
MEET'.NG OF:. 05/~5/94
TO: PUBLIC ~ORKS R- ROJAS
~:~:RRED *O' 9OLIO[ OE~T S ~RU~MER
]TEH' RECORD~ 12515
S~ree~ Sweeo~n9 gr~gram, Sml~h~
ACT:CH TAKEN BY COUNCIL:
SMITH REQUESTED STAFF LOCK !NT-_ THE =EASi=_,',LIT'¢·
OF EXPANDING THE STREET SNEE.="?iG ~ROGRAM AND
;~OTIFICAT~ON C: RESIDENTS,
~ACKUP HATERiAL ATTACHED- NO
DATE =ORWARDED BY CITY
A_lan T~, City Mana~ef-'~' ' / Randy Rowles, Chair
Staff: Gail E. Waiters ~ Kevin McDermott
/
Patdcia M. Smith
AGENDA SUMMARY REPORT
URBAN DEVELOPMENT
Wednesday, September 14, 1994
12:15 p.m.
City Manager's Conference Room
1. ROLL CALL
Call to Order 12:35 p.m.
Present: Councilmember Randy Rowles, Chair; Vice Mayor Kevin McDermott,
and Councilmember Patricia Smith
2. APPROVAL OF AUGUST 17, 1994 MINUTES
Item 5B amended to read ¥idening of Route 178" instead of Route 58.
Approved as amended.
3. PRESENTATIONS
None
4. PUBLIC STATEMENTS
None
5. DEFERRED BUSINESS
A. TRANSPORTATION IMPACT FEES
A written status report was submitted to the Committee. The County is awaiting the
judgement on the Jamison case before they proceed with implementing a policy that is
Urban Development Committee
Agenda Summary Report
September 14, 1994
Page 2
consistent with the City's. That information should be back to the Committee sometime
in December. The Committee asked for a list of all regional facilities and the total costs
projected, which will become the basis for the transportation impact fee per unit. The
list will be brought back to committee after discussion and review with the County and
the technical committee.
B. STATUS REPORT ON FREL~,~AYS
The Committee thanked staff for work thus far on the Kern River Freeway. The Chair
reminded staff to provide the Committee with a wdtten time line on the status of the
South Beltway project. Staff indicated that there were no significant updates to report
on freeway projects.
C. WASTEWATER TREATMENT PLANT
Staff has directed Brown and Caldwell, the consultants, to provide more specific detail
for cost comparison of the two sites that are in the final consideration for the treatment
plant. The City came in second on the local OEDP list (list for economic development
projects), for a development grant for Plant #2. This designation is a direct result of E.
Del Smith's lobbying efforts in Washington. It will then go to the national level for pdority
selection of the grant.
6. NEW BUSINESS
A. ORDINANCE REGARDING TEMPORARY PROMOTIONAL ACTIVITIES
Staff presented information on this item as a result of a carnival coming to town and
applying for a temporary promotional activity permit. The magnitude of the event was
not known until a caravan of trucks ardved in the proposed neighborhood. Carnivals are
regulated under a different section of the ordinance. Staff has suggested developing a
new application 'or enhancing the current one to cover the range of information
necessary to determine the magnitude of the temporary activity being requested.
Currently, the part of the ordinance that relates to carnivals is very weak, and gives quite
a bit of discretion to the City Manager as to what is allowed. Staff suggests
strengthening and bringing more clarification to the ordinance. Chapter 5.36 of the
Municipal Code will be amended and an application to address carnivals, open air and
tent shows will be developed.
Urban Development Committee
Agenda Summary Report
September 14, 1994
Page 3
B. ADVERTISING ON SIDEWALKS
This item was referred to the Committee to discuss "A frame" signs that obstruct
sidewalks. The Committee voted to continue this item to the October 5, 1994 meeting,
and asked that citizen, Bob Clerico be invited to attend the meeting.
7. ADJOURNMENT
Adjourned 1:15 p.m.
cc: Honorable Mayor and City Council
GEW:jp
BAKERSFIELD
PUBLIC WORKS DEPARTMENT
MEMORANDUM
TO: Alan Tandy, City Manager
FROM: Raul M. Rojas, Public Works Director ~Xvr~/~.~.d~-
DATE: September 14, 1994
SUBJECT: STATUS OF FREEWAY AND STATE HIGHWAY PROJECTS
METROPOLITAN BAKERSFIELD AREA
For your information and Council distribution, attached is the September report prepared
by this department regarding the status of the various freeway and State highway projects
in the metropolitan area. The previous reports also provide additional background on the
various projects.
September 14, 1994
STATUS OF FREEWAY
AND STATE HIGHWAY PROJECTS
METROPOLITAN BAKERSFIELD AREA
Public Works Department
Marian P. Shaw, CE III
This report is intended to update the members of the City Council on the progress of various freeway and
State Highway projects in the metropolitan area since the August. status report.
Kern River Corridor (Kern River Freeway)
On August 31, 1994, a public meeting was held at the Harvey Auditorium to help inform the residents of West
Park of the status of the State Route 58 Adoption Study. This meeting was sponsored by the County of Kern
and the City of Bakersfield; CalTrans made the presentation and answered questions presented by the public.
The main concern of the residents was to get the Southern Option dropped from further consideration in the
Route Adoption study. Although CalTrans was unable to drop the alignment that night, their representative
promised to take their concerns into consideration and to see what could be done in regards to the Southern
Option.
CalTrans has informed the City that the Background Socioeconomic study will be accelerated and will be
available by the end of September. A Project Development Team meeting will be.held sometime between
October 15 and November 1. The team members will review the data and make a recommendation regarding
the Southern Option at that time.
Prior to acquiring right-of-way, CalTrans will need to enter into a freeway agreement with both the City of
Bakersfield and the County of Kern agreeing to local access locations. With the City Council's opposition to
the Southern Option, CalTrans anticipates a very difficult time getting approval of any freeway agreement
involving the Southern Option.
The public hearing on the project will be held sometime in 1995, and a preferred alignment will be selected
after the hearing. The Environmental Impact Report will be completed in 1995. CalTrans hopes to have the
specific plan line process completed by the time the right-of-way money becomes available in July of 1996.
State Route 178 (Crosstown Freeway)
There has been no change in the status of the Crosstown Freeway from that last reported. The House has
authorized $4.5 million for this project. The project was not included in the recent appropriations bill and
may be considered for funding next year.
State Route 99
There are currently three major projects programmed for State Route 99: the Rosedale interchange
landscaping, the Golden State/Airport Drive interchange modification, and the widening of S.R. 99 to eight
lanes between Wilson Road and Golden State/Airport Drive.
Freeway Status Report
September 14, 1994
The City will be receiving an Encroachment Permit for the landscaping of the Rosedale interchange from
CalTrans this week and construction should be starting Monday, September 19, 1994. Changes to the
landscaping plans requested by the Kern River Parkway Committee and the California Native Plant Society
will be accommodated as much as possible, depending on plant availability.
Construction on the Golden State/Airport Drive interchange modification is ahead of schedule. CalTrans
expects to have the route open for traffic at the end of October. The resurfacing of Airport Drive is complete.
Southbound S.R. 99 traffic to eastbound S.R. 204 will be switched to use the new bridge soon. Northbound
S.R. 99 traffic to eastbound S.R. 204 will continue on the existing detour until the project is complete.
The funding for the widening of S.R. 99 between Wilson Road and Airport Drive has been restOred. The
project-will advertise on September 19, 1994. Construction should start by mid- to late-November. The
widening project will take approximately 2 years to construct. Work on this project will be closely coordinated
with the City's California Avenue Widening project, which will include redesign of both the eastbound
California/northbound 99 ramp and the westbound California/northbound 99 ramp.
South Beltway
Public Works and Planning staff are pursuing the SPecific Plan Line adoption for the South Beltway. The
Environmental Impact Report approved by Kern COG added three alternatives to the ones already proposed.
The City is completing an engineering evaluation of the additional routes and will be establishing a schedule
for the remaining work.
West Beitway
There is no change in the status of the West Bcltway from that last reported. It is still the County's intention
to pursue adoption of a specific plan linc for this bcltway through the General Plan amendment and zone
change process for the West Rosedale, Pacificana and McAllister Ranch specific plans. The County has held
some informational meetings for thc public, but they have not been well attended.
Coffee Road Grade Separation
The Separation of Grade District has solicited proposals for environmental evaluation of the project site
relative to risks and mitigation of contamination and has narrowed the selection to three proposals. These
proposals are currently being evaluated.
FS:\FREEWY13.STS
mps
BAKERSFIELD
PUBLIC WORKS DEPARTMENT
MEMORANDUM
TO: URBAN DEVELOPMENT COMMITFEE
Alan Tandy, City Manager
FROM: PUBLIC WORKS DEPARTMENT ~ ~
Fred L. Kloepper, Assistant Public Works Directo '
DATE: September 12, 1994
SUBJECT: Urban Development Committee MEETING OF SEPTEMBER 14, 1994
Item 54. - Transportation Impact Fees Update
Attached is a printout of Cumulative Status Report through
mid September 1994.
No reportable progress has been made relative to resolution of
City-County differences since the most recent committee
meeting.
Attach.
BAKERSFIELD
PUBLIC WORKS DEPARTMENT
MEMORANDUM
September 13, 1994
TO: FRED L. KLOEPPER, ASSISTANT PUBLIC WORKS DIRECTOR
FROM: DARNELL HAYNES, BUSINESS MANAGER ~
SUBJECT: CUMULATIVE STATUS REPORT - TRANSPORTATION IMPACT FEES
This memorandum is to report the current status of the revenues
collected and expenditures incurred from transportation impact fees.
Listed below is a summary of the fund activity since July 1, 1992.
July 1, 1992 - June 30, 1993
Interest on Investments $ 42,390.00
Traffic Impact Fees $ 3,477,320.00
'Contributions & Donations (Riverlakes) $ 200,000.00
Total Revenue Collected $ 3,719,710.00
Less: Transfer to Gas Tax Fund $ (885,400.00)
Less: Transfer to Gas Tax (Riverlakes) $ (400,000.00)
Less: 1992-93 C.I.P. Expenditures $ (211,934.00)
Revenue Remaining at June 30, 1993 $2,222,376.00
July 1, 1993 - June 30, 1994
Interest on Investments $ 51,390.00
Traffic Impact Fees $ 1,657,736.00
Contribution & Donations (Riverlakes) $ 200,000.00
Total Revenue Collected $ 1,909,126.00
Less: 1993-94 C.I.P. Expenditures $ (971,768.00)
Revenue Remaining at June 30, 1994 $ 937,358.00
July 1, 1994 - September 13, 1994
Traffic Impact Fees $ 343,837.00
Total Revenue Remaining For Fiscal Year 1994-95 $3.,503,571.00