HomeMy WebLinkAbout01/09/2009 .Afr 4F
vW
B A K E R S F I E L D
CITY MANAGER'S OFFICE
MEMORANDUM
TO: Honorable Mayor and City Council January 9, 2009
FROM: Alan Tandy, City Manager
SUBJECT: General Information 0 /ems
1. We are continuing to assess the damage caused by the State and the freeze on funds by
the Pooled Money Investment Account board. Their actions have created delays for
Mohawk, the Westside Parkway, Mesa Marin Park, the Kern River Restoration, and three
housing projects. The total damage to us is near $138,793,070! In addition, the "freeze"
is even in effect for contracts where work is already underway. It is unclear when or even
if we will be reimbursed for those expenses. Our only choice is to use Traffic Impact
Fees to pay the contracts, thus reducing our balance and flexibility from that source.
Exact numbers are still being analyzed. Other contracts which should have been
approved to get the projects ready have been put on hold. As a result, the startup time
will be greater to activate these projects whenever the State finally gets its act together.
2. Construction on the Allen Rd. Bridge is progressing well. The first quarter of the bridge
deck has been poured and the next quarter of the bridge deck is scheduled to be poured
on Wednesday, January 14th. Roadway and sound wall work will continue in conjunction
with the bridge work. Paving will start as soon as the temperatures are favorable for this
operation. This project is scheduled to be complete on May 22"d. Photos of the progress
are enclosed.
3. We are about 70% of the way through with the SR-178/Fairfax project and the contractor
is about two months ahead of schedule. The sound wall and retaining walls along the
north side of SR-178 are currently being constructed. The bridge superstructure is
complete, with the barrier rails and lighting still to be completed. Initial paving of the
freeway lanes and the on- and off-ramps has taken place east of the bridge, and
additional paving west of the bridge is still to be done. Three quadrants of the
interchange have the irrigation system installed and a majority of the landscape planted.
To date the City has made progress payments in the amount of $17.2 million out of the
original contract amount of$28.9 million.
4. Below is a progress update for each of our major park construction projects:
Mill Creek: The Central Park (Phase 1) construction is nearing completion. The
pedestrian bridge roof is roughly 80% completed with full completion expected by the end
of January. The decorative lights and bollards are installed and functioning. Irrigation
work is 95% complete and hydro-seeding is scheduled to take place at the end of March,
which is necessitated by the weather. The remaining canal modification work for Phases
2, 4 & 5 was recently completed on December 31St and the canal is flowing once again.
Everyone involved with this work deserves congratulations as completing the required
Honorable Mayor and City Council
January 9, 2009
Page 2
modification was challenging due to the compressed schedule we had to work with.
Work will continue to complete the pedestrian crossings and install the park amenities for
these phases. Photos of the progress are enclosed.
Aera Park: Construction of Aera Park is underway with irrigation work ongoing and
construction of the backstops taking place. In addition, construction of the restrooms and
concession stand has begun and is scheduled to be complete in April of 2009.
Sports Village: The Sports Village project is currently progressing with design and
construction documents under development for the Phase 1 soccer complex. Bid
advertisement is scheduled to take place in February or March of 2009, and the opening
is still on schedule for 2010
Mesa Marin Sports Complex: The Mesa Marin Sports Complex was scheduled to have a
Bid Opening on December 19, 2008. However, due to the recent freezing of bond funds
contained in the State Pooled Money Investment Account (PMIA), the Bid Opening has
been cancelled until we have greater clarity of when these funds will be available again.
Kern River Upland and River Edge Restoration Project: This project is currently in the
design phase but progress has stalled as the major funding source for this project is also
held captive in the PMIA freeze.
5. 1 am pleased to announce the promotion of Ryan Starbuck to Public Works Traffic
Engineer. Mr. Starbuck brings 14 years of experience to the job which includes over 10
years as a Civil Engineer III supervising traffic operations in the City's Traffic Engineering
section.
6. The 4th Annual Polar Bear Plunge, which took place on New Year's Day at McMurtrey,
had an increase of 62 participants this year. The total attendance for the event, including
spectators, was 349.
7. The Economic and Community Development Department Activity Report from October 1,
2008 through December 31, 2008 is enclosed
8. The Streets Division work schedule for the week of January 12th is enclosed.
9. Responses to Council requests are enclosed, as follows:
Councilmember Benham
• Clean up/Graffiti concerns at Bessie Owens School, and
Councilmember Couch
• Bright House Networks — Cable Service Problems.
AT:rs:rk
cc: Department Heads
Pamela McCarthy, City Clerk
Roberta Gafford,Assistant City Clerk
General Information Memo — January 9, 2009
Progress of Construction at Allen Rd. Bridge
n
1
1
I
u --
General Information - • January • 2009
Progress of Construction at Allen • Bridge
r
i 01 /06i 2009.
t?l3t12t�06 t3-21
e 4 1r
tr
lit lit
bkmcie�albi7f�alilAi �l ���.
" —•
ke k k' 1i kf� M i ut{�i i�0" flint
r
t.?Pi iAfil Pri��lt� _f' ��t.rl,s.
11
n a
r
•tom
o
a
4F
�>-Ali
wow
r..
r
General Information _ • "
Progress of Construction Creek
•" r
i
y
m
i
101�.�7 , 0 110�
B A K E R S F I E L D
PUBLIC WORKS DEPARTMENT
MEMORANDUM
TO: Alan Tandy, City Manager
FROM: Raul M. Rojas, Public Works Director
DATE: January 5, 2009
SUBJECT: Recent Promotion — Public Works Department
I am pleased to announce the promotion of Ryan Starbuck to Public Works Traffic
Engineer.
Mr. Starbuck brings 14 years of experience to the job which includes over 10 years as a
Civil Engineer III supervising traffic operations in the City's Traffic Engineering section.
Mr. Starbuck has a Bachelor's Degree in Civil Engineering from California Polytechnic
State University San Luis Obispo and is both a Registered Professional Civil Engineer
and a Registered Professional Traffic Engineer.
During his tenure with the City, Mr. Starbuck has worked on a variety of traffic
engineering projects including project management for the Traffic Operations Center,
Signal Communication System, and Safe Route to School projects.
His unique combination of education and extensive traffic operations experience make
him well-qualified to assume the responsibilities of Traffic Engineer for the City of
Bakersfield.
,°�N U
B A K E R S F I E L D U
Economic and Community Development Department
M E M O R A N D U M
January 9, 2009
TO: Alan Tandy, City Manager-
FROM: Donna Kunz, Economic Development Director
SUBJECT: Economic and Community Development Department Activity Report from
October 1, 2008 through December 31, 2008
CAPITAL IMPROVEMENT PROJECTS
1. 34th Street Streetscape — Phase I
The city portion of this project has been completed and a maintenance district has been
formed. Streetscape improvements between Union Avenue and "Q" Street include the
installation of trees, shrubs, automatic irrigation and lights. In addition, special design
features in the median will be installed by Memorial Hospital. The completion of the city's
portion was completed to coincide with dedication of Memorial Hospital's new tower in
January 2009.
2. Lowell Park Restroom Construction Project
CDBG funds of $350,000 (FY 07-08) are available for design and construction of the
restroom facilities to replace the existing deteriorated restrooms at Lowell Park located at
4th and "P" streets. Federal environmental review was completed in October 2007. The
Recreation and parks Department is the lead department, and is working with PW in
preparing the bid package by early 2009 and expect to begin the bidding process by
February 2009. Project completion is anticipated by the end of the fiscal year.
NON-PROFIT/PUBLIC FACILITY PUBLIC SERVICE PROJECTS
The following various non-profit organizations are being financially assisted to improve the
level of service for operating their public facilities.
1. Bakersfield Senior Center
CDBG funds are used by this agency to maintain its current level of services, such as a
hot lunch program, recreational programs, and entertainment to seniors in southeast and
central Bakersfield. An agreement for 2008-2009 funding was approved by Council on
November 5 for $65,000. The agency has expended 53% of that allocation. An
amendment was approved by Council on December 17 to provide an additional $20,000
due to increased costs associated with operating the facility.
SADEBBIE'S\EDCD Activity Reports\2nd Quarter Update 2008-09.doc
1
2. Bakersfield Homeless Center
Emergency Shelter Grant (ESG) funds are used by this agency for operational expenses
such as staff, postage, telephone, utilities, insurance, equipment rental, and maintenance
costs. An agreement for 2008-2009 funding was approved by Council on November 5 for
$62,000. To date 0% of the funding has been requested by the agency.
3. Bakersfield Rescue Mission
Emergency Shelter Grant (ESG) funds are used by this agency for essential services and
operation and maintenance expenses including staff costs. An agreement for 2008-2009
funding was approved by Council on November 5 for$62,000. The agency has submitted
requests for 41% of the funding.
4. Alliance Against Family Violence and Sexual Assault
Emergency Shelter Grant (ESG) funds are used by this agency for operation and
maintenance expenses. An agreement for 2008-2009 funding was approved by Council on
November 5 for $15,200. To date 0% of the funding has been requested by the agency.
5. Martin Luther King Jr Center Roof Replacement
This project involves repairing the wooden deck if needed and replacing leaking roof
sections A,B,C, and D at the Martin Luther King, Jr. Community Center with a new R-19
multi-ply "cool" roof system to preserve the integrity of the interior of the center. Work is
scheduled to begin on the project in February 2009 and estimated completion is in April
2009.
HOUSING, ECONOMIC AND NEIGHBORHOOD REVITALIZATION PROJECTS
The following private and non-profit organizations are being assisted by staff to acquire,
develop or improve their housing and neighborhood/commercial facilities.
1. Southeast Bakersfield Infill Housing Project
The City was awarded a $500, 000 CalHFA loan to build affordable housing on scattered
lots in southeast Bakersfield. The RDA assumed all rights and obligations of the loan on
February 26, 2003. Round four of the infill housing project began in Fall of 2006. The
agreement period will be in place for two years and the contractor will be obligated to
complete at least four homes within the two-year period. To date, seventeen new homes
have been constructed.
Hybrid has completed the construction of a home at 226 East 6th Street and has begun
construction their third home located at 1213 Murdock Street. The anticipated completion
date is March 2009.
2. Bakersfield College Foundation Construction Alliance for Student
Achievement (CASA) Program
The Redevelopment Agency approved the donation of three residential lots to Bakersfield
College Foundation (BCF) to build infill affordable homes in the Southeast. The CASA
program enhances job opportunities among low-income residents while assuring
developers and construction firms have an adequate skilled labor pool to meet market
demands for affordable housing. This activity addresses the demand for skilled
S:\DEBBIE'S\EDCD Activity Reports\2nd Quarter Update 2008-09.doc
2
craftsmen/women in the construction field, and provides job training skills among minority
populations of Bakersfield.
The CASA program is participating in the Southeast Bakersfield Infill Housing Project.
BCF took title to the lots located at 339 Brown, 124 Hayes and 301 Owens Streets in
November, 2005. The 1 st home located at 339 Brown Street has been completed and sold
to a low-income family. The 2nd home located at 124 Hayes Street was recently completed
and is currently listed for sale.
3. Southeast Neighborhood Revitalization Project— (SE)
Staff has developed a three-year comprehensive targeted neighborhood revitalization
program. This program includes the addition of one dedicated Code Enforcement position,
partial clerical support, equipment, and supplies to provide various code enforcement
activities such as removal of junk cars and the demolition of substandard structures. The
program focuses on a five-block area bounded by Brook Street to the south, Hale Street to
the east, E. Planz Road to the north and Cottonwood Road to the west.
Housing Programs currently available for low income residents not exceeding 120% of the
area median income include a targeted owner-occupied housing, no interest-deferred
rehabilitation loan to $40,000 per unit. Qualifying homeowners occupying substandard
homes with clear title to their property may be eligible for down payment assistance up to
$35,000 to purchase or construct a new home on their existing lot or purchase a
manufactured home. A front porch grant program is also available to improve the
appearance of the exterior of a residence. The maximum project cost cannot exceed
$5,000 and the program requires a matching contribution of 10% of the total project cost
from the applicant. In addition, the Redevelopment Agency approved a sewer grant
program not to exceed $10,000 and a demolition grant up to $8,000. The program is
funded with Southeast Tax Increment funds.
Over the past year staff worked diligently with the property owner at 1818 Lewis Street to
guide him through the application process in an effort to replace a dilapidated residence
with numerous building code violations, health hazards and safety issues. The residence
was scheduled to be condemned had staff not intervened. As of today the residence was
demolished and the property owner qualified to purchase a new 1,240 square foot three
bedroom two bath manufactured home that is scheduled to be installed within the next 10
days. Working with this property owner was one of the most difficult cases in the entire
Filson Area Targeted Revitalization program. Another applicant recently closed escrow on
the purchase of an existing property on Filson Street. Staff plans to send out flyers within
the next month reminding the residents of the Housing Programs currently available for low
income residents not exceeding 120% of the area median income.
4. Home Accessibility (HAI Grant Program
The program offers grants of up to $3,500 for constructing accessibility improvements in
privately or publicly owned structures for those clients who are physically challenged. This
program aids low income physically challenged people who live within Bakersfield's city
limits. Since March 2008, thirteen physically challenged households have been provided
improvements such as wheelchair ramps, handicap toilets and grab bars. The Agreement
S:\DEBBIE'S\EDCD Activity Reports\2nd Quarter Update 2008-09.doc
3
for 2007-2008 expired in September 2008. A new agreement for 2008-2009 went before
Council on December 17, 2008 which includes a budget not exceeding $50,000.
5. West Columbus Affordable Housing Project - Residences at West Columbus
On April 9t", 2008, staff sent out a Request for Proposal & Qualifications to four
development Firm/Agencies to acquire and develop the 3.5 +/-acre residentially zoned site
located at 500 West Columbus Avenue in Bakersfield, California. GEAHI-II was chosen by
the City through an in-depth proposal evaluation and a follow-up developer interview. The
current owner of the property (LINC Housing Corp.) is working closely with the City to
transfer ownership of the property to the new tentative affordable housing developerwhich
will be composed of the new LP with GEAHI-II as the managing partner (owner).
Underwriting review of the proposed project is being conducted by city staff. A three party
assignment, and HOME-CHDO project Agreement is scheduled for approval at the January
14th City Council meeting. The LP will be applying for low income tax credit financing and
state financing to assist them with the design and project construction.
The project name has recently been changed to the "Residences at West Columbus."
Construction of the 56 unit project is expected to begin sometime in March 2009 and when
complete, will primarily serve emancipated foster youth.
6. Tax Defaulted Properties
Each year the County of Kern compiles a list of real properties for which property taxes
have not been paid for a minimum of five years. Pursuant to the County selling these
properties at auction, the City or Bakersfield Redevelopment Agency can object to the sale
of the properties and purchase them for future public use. EDCD staff has been
successful in gaining the right to purchase 23 properties over the past few years. The next
tax sale should be held in February 2009.
7. The Parkview Cottages Housinq Project
The City was awarded a $1.2 million HELP loan, which was used to acquire a portion of the
old foundry site located at 21St and "R" streets. The project consists of 74 single-family
housing units, ranging from 1,280 to 1,820 square feet. Each unit will be two stories and
have a two/three car garage. One home is in escrow, twelve homes are ready for sale,
home buyers currently occupy 30 units, and two units are models.
Current market conditions and lack of mortgage financing options for low and moderate-
income families have affected the ability to sell the homes. Staff increased the
downpayment limits and the developer lowered the prices. A new local broker is
aggressively marketing the homes on television and in the local pages. These efforts have
increased sales activity to approximately 2-3 units per month.
8. Fair Housing
During this quarter, 217 calls were received: 15 were substantial service calls dealing with
fair housing issues and five complaints were filed; these are under review by both the
Department of Fair Employment and Housing and city staff. Fair housing discrimination
complaints and inquiries during this period were categorized by Race 20%, Familial Status
20%, Disability 20%, Religion 20%, and Other 20%.
S:\DEBBIE'S\EDCD Activity Reports\2nd Quarter Update 2008-09.doc
4
9. Baker Street Revitalization Project (Old Town Kern Mixed Use Project)
Foundation work and grading has been completed for Phase I of the project on the half
block east of Baker Street south of Lake Street. When finished, this phase will include 24
three-story town homes, 13 residential lofts and 9,000 square feet of commercial space on
Baker Street. The residential and commercial developments are for-sale units.
Neighborhood type services are anticipated for the commercial space. Phase I should be
completed by Summer 2009. The next three phases will include more residential and
commercial units, and 41,000 square feet of new commercial space, such as a grocery
store and pharmacy as possible key anchors. Total project value is approximately $35
million.
10. Mill Creek Linear Park Project
Mill Creek Linear Park is a conceptual design of a 1.5 mile stretch of agricultural canal
which is being transformed into a major recreational linear park with a "natural creek" and
pedestrian corridor that will travel through the heart of downtown Bakersfield along the
Kern Island Canal from Golden State to California Avenues. The over all theme of the
project is focused on the late 1800's era with a historic flavor to include replicas of a
covered bridge and mill house.
The Redevelopment Agency received a $10,000,000 loan to provide financing for the project
brining the total budget to date to $12.7 that will cover the segments between Golden State
Avenue and 18th Street and from Truxtun to California adjacent to the South Millcreek
Mixed use Project. Construction of elevated street crossings at 19th and 21 St streets and
additional phase of the parkway have begun. At Central Park, the pond rail fence panels
are in place and the pedestrian bridge has been installed. The next phases of the
Millcreek Linear Park are currently underway.
11. Orphan Grant
This project has been completed ahead of schedule and under budget. A grant from the
State Water Resources Control Board paid for removing contaminated soil at the city-
owned site at 1433 Union Avenue and backfilling the area with clean soil.
12. BEGIN Down Payment Assistance Program
State grant funds of $1,560,000 were received from the Building Equity and Growth in
Neighborhoods (BEGIN) Program from the California Department of Housing and
Community Development(HCD). These funds will be used to provide mortgage assistance
to 52 low income first-time homebuyer families interested in purchasing a home within a
residential development near Ridgeview High School. Self-Help Enterprises (SHE) is the
affordable housing developerforthe 52 lots that will be receiving the BEGIN down payment
assistance. The down payment assistance will be a 30 year(silent second) loan (deferred)
at 1% simple interest up to $30,000.
SHE has had considerable delays in delivering the 52 units. The primary delay with the
program was the lack of administrative resources for SHE to deliver the mutual self-help
building program. Another delay has been SHE's outreach/marketing efforts for qualifying
families for this affordable housing project. SHE has completed nine of the 52 homes
located on McKee Road. The future of this project is unknown due to the "freeze" of funds
by the State of California.
SADEBBIE'S\EDCD Activity Reports\2nd Quarter Update 2008-09.doc
5
13. South Mill Creek Mixed-Use
The Mill Creek South Mixed-Use Project is a commercial and residential plan that will be
approximately 10 acres and include a minimum of 80 units of affordable mid rise garden
style affordable rental units, 35 market rate urban style upscale condominiums, and 65,000
square feet of commercial space for retail, restaurants, community events, and
neighborhood services. The proposed project is located in the Southeast Redevelopment
Project Area, alongside the southern tip of Mill Creek. The restaurants in the planned retail
development will have outdoor patio seating overlooking Mill Creek, a 1 .5-mile stretch of
agriculture canal, which is being redeveloped into a major recreational amenity with a white
water look and will travel through the heart of downtown Bakersfield. The planned $60
million, 10 acre mixed-use project will replace a contaminated metal recycling business and
auto repair and body shop. In addition, it will replace a dilapidated empty warehouse and a
predominantly vacant commercial dilapidated building with several abandoned partial
structures.
In January of 2008, two firms; Chelsea Investments Corporation and Southwest Consulting
Inc., were selected by the Redevelopment Agency for the development. Exclusive
negotiating agreements were approved as Chelsea was selected for the development of 70
mid rise garden style affordable rental units and Southwest Consulting, Inc., for the
development of 36 urban style upscale condominiums and 65,400 square feet of
commercial space. In September 2008, the City Council and Bakersfield Redevelopment
Agency approved the Disposition and Development Agreement with Chelsea Investment
Corporation for the construction of 70 mid-rise garden style affordable rental units.
Construction is anticipated to begin in July 2009 and be completed by August 2010.
14. South Millcreek Plaza Cinema Complex
South Mill Creek Plaza is a mixed-use lifestyle, ground-up development on approximately 7
acres. The site is designed to accommodate a total of 89,000 square feet of space,
featuring 28,000 sq. feet of entertainment related retail, restaurant space and a 61,000
square feet state of the art 16 screen, 2,600 seat multiplex cinema. Maya Cinemas North
America, the developer, plans to develop the project south of Rabobank Arena and
Convention Center, and south of the railroad tracks between California Avenue, "M" Street
and the Kern Island Canal. Maya Cinemas North America and D.W. Sivers have acquired
all the property necessary for the development of the $32 million dollar project and will take
24 months to construct and stabilize.
The South Mill Creek Plaza will be a major factor in reducing blight in the area and will
provide the Southeast Redevelopment Project Area with an anchor tenant that will be a
catalyst for additional development along California Avenue. The ground breaking
ceremony was held on July 29, 2008. Construction began on the Maya Cinema phase of
the project in September 2008, with completion anticipated in the fall of 2009. In addition,
construction on the 28,000 sq. feet of entertainment related retail, restaurant space is
estimated to begin in March 2009, with completion by December 2009.
15. Village Park Senior Housing
The Housing Authority of the County of Kern (HACK)through its non-profit Golden Empire
Affordable housing Inc. (GEAHI) received $2 million in HOME New Construction monies
S:\DEBBIE'S\EDCD Activity Reports\2nd Quarter Update 2008-09.doc
6
from the City of Bakersfield for the construction of affordable senior housing. The
proposed project is the development of 60 units (56 one-bedroom units and 4 two-
bedroom units) or senior housing in the Downtown Redevelopment Project Area, at the
corner of 24th and R Streets. This is GEAHI's second low-income housing tax credit project
downtown near 24th and R Streets and will be rented to persons at or below 60% of the
area median income.
The funds will be used for the construction of the senior housing units as HACK already
owns the project property. The total cost for the project is approximately $12 million and
will be built adjacent to the Park Place Senior Housing Project, 80 units of senior housing.
The City's assistance will be in the form of a loan — 3% simple interest (residual receipts
loan rate)over a 55 year period. The remainder of funds for the senior housing project will
come from various other state and private funding sources. Project is underway and
completion is estimated by no later than spring of 2009.
16. King Square Family Apartments
KSA Partners received $850,000 in HOME funds to construct a $14M ± 72-unit family
apartment complex at 1601 Lotus Lane. This is a low-income housing tax credit project. The
Developer expects to receive$9.3 ± million in tax credit funding, $2.3± million in private long
term financing, and $1.5 ± million deferred developer's fee in addition to the $850,000 in
HOME funding.
A Council action approving the HOME project agreement with KSA Partners occurred
February 7, 2007. Construction started in March of 2007. Project was completed late
2008.
17. McDonald Way Sewer Connection Project
A construction contract was awarded in May 2007 to HPS Mechanical for septic tank
abandonment and hook-ups. Staff has been receiving and processing applications from
qualified residents. To date, 31 applications ± have been awarded SCG funds with 1
application being awarded during this reporting period. Additionally another 20
applications are in various stages of approval.
Low-income families in the area may qualify for CDBG assistance to connect to the sewer,
once it is completed. It is anticipated that this grant amount can be as much as
$20,000/connection for eligible applicants. The grant will only be available to low income
homeowner occupants. This program will be phased over two fiscal years and will end on
April 1, 2009. Total funding for the project consists of $450,000 FY 05-06 CDBG funds
with an additional allocation of $400,000 for FY08-09.
18. Graffiti Removal Program - Citywide
CDBG funds are used to assist in graffiti removal in low- and moderate-income areas
throughout the city, primarily in wards 1, 2, 3, 6, and 7. Graffiti removal has been budgeted
for the funding year 2008/2009 the amount of $200,000. To date 0% of the funding has
been used.
S:\DEBBIE'S\EDCD Activity Reports\2nd Quarter Update 2008-09.doc
7
19. Quantico/Madison Affordable Housing Rehab Project
The apartments are located at 1885 Madison Street and owned and operated by Mercy
Housing California. HUD(HOME) and TI Funds will be used to benefit about 56 units. City
funds in the amount of$450,000 will be used for exterior renovation, on—site improvements
and tenant based rental assistance. About$350,000 (TI funds)will be used for exterior and
interior rehabilitation and $100,000 (HOME funds)for Tenant Based Rental Assistance to
benefit five households(at risk homeless families). A draft Owners Participation Agreement
(OPA) using TI funds ($350,000) has been drafted and is under review by Mercy Housing.
Construction of the project is anticipated to start by spring of 2009.
20. _Casa Loma Park — Wet Play Area Project
Improvements to include wet playground equipment consisting of a circulation pump,
filtration system, and concrete base for a county-owned park located at 493 East Casa
Loma Drive within the City. The total budget for this project is $500,000.The Council
approved an amendment activity to the FY 2007-08 Action Plan in the amount of$375,000
last fall and the remaining $125,000 the County will use park Bond money. The County's
Park and Recreation Department will construct the improvements and own and operate
them upon completion. The agreement will go before the County on January 6, 2009 and
will go before the City Council on January 28, 2009. Construction is expected to start in
mid March 2009. Construction should be completed by mid June 2009.
21. Bakersfield Association of Retarded Citizens
CDBG funds of$300,000 (FY 07-08)are available for a social entrepreneurial non-profit to
acquire, construct, or rehabilitate a commercial/industrial training facility for a special
economic development activity. The proposed multi-million $ project is to be located at the
Bakersfield Association of Retarded Citizens(BARC)training facility on 2240 South Union
Avenue it will be a 30,800 ± sq. ft., pre-fabricated steel frame metal building with about
40,000 sq.ft. asphalt paving to be used as a: 1) recycling facility, or 2) internet orderfacility,
or a 3) pallet manufacturing facility. The County also has about$300,000 of CDBG funds
earmarked for this activity. A minimum of 40 jobs to be created with the total ($600,000)
HUD assistance with at least 22 positions or 51% of the jobs to be created earmarked for
low income job seeking residents. The project agreement between the City, County and the
non-profit has been executed by all parties. EDCD staff in conjunction with the County and
BARC have met to discuss the project management and a Notice to Proceed was jointly
issued by November. BARC will be the lead agency for this activity and started
construction December 2008. Project completion is anticipated by no later than the end of
the fiscal year.
22. 19th Street Plaza
This proposed mixed use project adjacent to the Mill Creek Linear Park would include
office, commercial, and residential space. The developer envisions approximately 35,000
square feet of office and commercial space with a restaurant in a four level building
adjacent to the canal; 67 one and two-bedroom units of affordable senior rental housing in
a three story structure; a 3,000 square foot food court; and an 80 space parking garage.
The RDA has entered into a Disposition and Development Agreement with Southwest
Consulting, Inc., to build the project on approximately 2.5 acres of vacant land east of the
canal between 18th Street and 19th Street, 501 -19th Street. Engineering and architectural
plans have been developed and are in review.
S:\DEBBIE'S\EDCD Activity Reports\2nd Quarter Update 2008-09.doc
8
23. Boys and Girls Club of Kern County
Renovation of this existing facility at 801 Niles Street will involve improvements to the roof,
ceiling panels, air conditioning, and gym floor. The target date for completion is December
2009. Staff is currently working on an agreement for this agency's request of$40,000 and
is awaiting reply from the agency to complete the agreement.
24. Acquisition & Relocation — Catholic Charities
This project will involve acquiring the parcel located at 525 - 18th Street and relocating the
tenant, Catholic Charities. $400,000 of CDBG funds were approved in the FY08/09 Action
Plan. An amendment to the Action Plan for an additional $281,578 was approved by the
City Council at their July 30, 2008 meeting. The site then will be converted into park space
in connection with the Mill Creek Linear Park Project. Target date for completion is Winter
2009.
25. Habitat for Humanity— 1812 Filson
On May 5, 2008, the Bakersfield Redevelopment Agency approved an agreement to sell a
vacant parcel located at 1812 Filson Street to Habitat. This parcel was purchased by the
Agency through a tax default sale. Habitat for Humanity volunteers and the prospective
new homeowner will begin construction on the home in September. The completed home
will then be relocated to the Filson Street address. This parcel is also located within the 5-
block Southeast Targeted Neighborhood program area. The home is expected to be
completed by March 2009 and a family should be occupying the home by April 2009.
26. E. California Avenue Property
On May 7th, 2008 The City of Bakersfield Economic and Community Development
Department posted a Request for Proposal & Qualifications on The City of Bakersfield's
EDCD webpage to acquire and develop the 2.69 +/- acre commercially zoned parcel on
East California Ave. between S. Owens Street and S. Robinson Street. Postcards were
sent to potential participants for notification of the City's Request for Proposal and
Qualifications. The RFP/Q was circulated for a 45 day period and the deadline for
submittals was June 20, 2008.
One proposal was received from Becker Commercial Properties in conjunction with Grubb
& Ellis ASU & Associates. However, Becker Commercial was unsuccessful in procuring
tenants for the development and decided to withdraw their proposal.
The Kern County Black Chamber of Commerce has shown interest in the property and is
currently reviewing the RFP/Q. The Chamber's President along with a partnering
developer will evaluate the feasibility of a potential development and will consider
submitting a proposal to the department by March 2009.
27. Green Gardens II
Golden Empire Affordable Housing, Inc., II (GEAHI-II) is requesting $600,000 in HOME
funds from the City of Bakersfield and the Bakersfield Redevelopment Agency. The funds
would be used for the development of a new 24 unit permanent supportive housing
complex designated for chronically homeless individuals. The housing will consist of 24 -
412 sq. ft. one-bedroom units. Total project cost is estimated at approximately$4.4 million
and will utilize various funding sources.
S:\DEBBIE'S\EDCD Activity Reports\2nd Quarter Update 2008-09.doc
9
The project is located at 2300 S. Union Ave., approximately at the northeast corner of the
intersection of Union Avenue and White Lane. The project encompasses approximately
2.01 acres and is located in the Southeast Bakersfield Redevelopment Area. The City is
currently reviewing the application from the Housing Authority of The County of Kern and
the NEPA review for the project is nearing completion. Project construction is tentatively
scheduled to begin in March 2009.
28. Friendship House — Community Action Partnership of Kern
Community Action Partnership of Kern requested $247,342 for improving the outdoor
sports complex located on the Friendship House Community Center property at 2424
Cottonwood Road while $3,039,000 has been secured from the State of California,
Department of Parks and Recreation. This project was reconsidered and funding identified
from year end closings and savings. This project was included in Amendment # 3 FY
07/08 Action Plan. The NEPA (National Environmental Policy Act) review is underway.
The agreement is expected to go before Council in early 2009, with construction
completion by end of the 2009 calendar year.
S:\DEBBIE'S\EDCD Activity Reports\2nd Quarter Update 2008-09.doc
10
Page 1 of 2
STREETS DIVISION — WORK SCHEDULE
WEEK OF JANUARY 12, 2009 — JANUARY 16, 2009
Resurfacing/Reconstructing streets in the following areas:
Reconstructing streets in the area between Club View Drive and Sanders Lane,
east of Ashe Road.
Miscellaneous Streets Division projects:
Working on the Mill Creek project.
Working on the Aera Park project.
THIS SPACE INTENTIONALLY LEFT BLANK
Week of January 12-2009—Work Schedule
Page 2 of 2
STREET SWEEPING SCHEDULE
Monday, January 12, 2009
Between So. "H" Street and Union Avenue — Pacheco Road to Hosking Road.
Between Stockdale Highway and Truxtun Avenue Extension — Coffee Road to Partridge
Avenue.
Tuesday, January 13, 2009
Between Highway 99 and So. "H" Street — Ming Avenue to Panama Lane.
All cul-de-sacs on the north side of Magdalena Avenue, west of So. "H" Street.
Wednesday, January 14, 2009
Streets within the City Limits in the area between Brundage Lane and Ming Avenue — So. "H"
Street to Union Avenue.
Streets within the City Limits in the area between Wilson Road and Pacheco Road — So. "H"
Street to Union Avenue.
Between Casa Loma Drive and Planz Road — Madison Avenue to Cottonwood Drive.
Between Planz Road and Brook Street — Madison Avenue to Hale Street.
Thursday, January 15, 2009
Streets within the City Limits in the area between Stockdale Highway and Ming Avenue — Ashe
Road to Gosford Road.
Between El Portal/Laurelglen Blvd. and Ashe Road — Ming Avenue to So. Halfmoon/Olympia
Drive.
Between Ashe Road and Stine Road — Ming Avenue to So. Half moon/Edge mount Drive.
Between Coffee Road and Wilson Road extension — White Lane to So. Halfmoon/Olympia Dr.
Friday, January 16, 2009
Between Stockdale Highway and Ming Avenue — Allen Road to Old River Road.
Between Old River Road and Coffee Road — Ming Avenue to Ridge Oak/NVestwold Drive.
Between Ridge Oak/Westwold Drive and White Lane — Old River Road, east to the PG&E
easement.
Between White Lane and Asperata Drive — Gosford Road, west to the PG&E easement.
Between White Lane and Cedarwood Drive — Stine Road to Wilson Road extension.
Week of January 12_2009_Work Schedule
0
S A K E R S F I E L D
CITY OF BAKERSFIELD
PUBLIC WORKS DEPARTMENT —
MEMORANDUM
Al", Q
TO: Alan Tandy, City Manager
FROM: Raul Rojas, Public Works Director
DATE: January 6, 2009
SUBJECT: CLEAN UP/GRAFFITI CONCERNS AT BESSIE OWENS SCHOOL
Referral No. 48
COUNCILMEMBER BENHAM REFERRED CORRESPONDENCE FROM RAMON
CAMACHO REGARDNG CONCERNS OF GRAFFITI AND SIDEWALKS/STORMDRAINS
NEEDED TO BE CLEANED TO STAFF AND REQUESTED STAFF PREPARE A LETTER
FOR HER SIGNATURE EXPLAINING WHAT ACTION THE CITY IS TAKING AND
THANK HIM FOR NOTIFYING HER.
Traffic Engineering will contact the school to determine whether or not the signs in question
are still in use. If they are no longer needed, the signs will be removed. If they are still in
use, they will be replaced with new signs.
Staff will look at the storm line that goes from the catch basin to the main storm line to
determine if the main line can handle more capacity
Since the flooding caused dirt to accumulate on the sidewalk, the sidewalk will be cleaned by
City staff.
The School District is responsible for planting and maintaining trees in the park way. As a
courtesy, staff will forward Mr. Camacho's concerns to them.
Attached is a letter from Councilmember Benham to Mr. Camacho in response to his
concerns.
G:\GROUPDAT\Refen-als\2008\12-17\#48 Graffiti Bessie Owens.doc
z 0
X00100-Z..-
B A K E R S F I E L.
T
C A L I F O R N I A
F �"£ January 6, 2009
I
Mr. Ramon Camacho
815 Chico Street
CITYCOUNCIL I Bakersfield, Ca 93305
J
Harvey L.Hall
Mayor Dear Mr. Camacho:
Harold W.Hanson Thank you for bringing your concerns to my attention. City staff has reviewed
Vice-Mayor them and will be addressin
Wards g your concerns as follows.
Irma Carson Traffic Engineering will contact the school and if the signs are no longer needed
Ward] they will be removed. If the signs are still needed, they will be replaced with
new ones.
Susan M.Benham
Ward When Curb
gutter and sidewalks were installed the storm line was not replaced.
Ken Weir However, the Streets Division will be looking at the storm line on the two catch
Ward basins on Beale Avenue to determine if the main storm line can handle more
capacity.
David Couch
Ward 4 It is the responsibility of a property owner to maintain the sidewalk in a safe
Jacquie Sullivan condition, as per sections #5610 to #5614.1 of the State of California Street and
Ward 6 Highways Code. But, since the dirt on the sidewalk was caused by the recent
flooding, the Streets Division will be assigning a crew to clean the sidewalk. In
Zack Scrivner the future it would be up to the school or the school district to maintain the
Ward 7 sidewalk.
It is the School District's responsibility to plant and maintain trees along the
parkway in front of the school. As a courtesy, City staff will forward your
concerns to them on this issue.
I hope your concerns have been addressed. If you have any questions please
do not hesitate to contact me.
Yours Truly,
Sue Benham
Councilmember, Ward 2
1501 Truxtun Avenue•Bakersfield,California 93301 •(661)326-3767•Fax(661)323-3780
s
B A K E R S F I E L D
CITY MANAGER'S OFFICE
MEMORANDUM
January 8, 2009
TO: Alan TandyyCity, Manager
FROM: � Rhonda Srtrfl"ey, Assistant to the City Manager
SUBJECT: Bright House Networks — Cable Service Problems
Council Referral #45
Councilmember Couch requested staff look into the complaints of cable service
problems with Bright House Networks.
At the December 17th, 2008 City Council meeting, Councilmember Couch requested
that staff investigate various problems being experienced by Bright House Networks
cable television customers, as a result of the concerns described by their customers,
Jayme R. Seeger.
Attached is a detailed report from Bright House explaining the reasons for the technical
issues and the efforts they are making to correct the various problems that have been
reported by their subscribers, including those described by Ms. Seeger.
The division president of Bright House indicates they are making significant progress in
resolving the technical issues, but he acknowledges that there are still problems which
they are diligently working on, and he encourages all customers who are having
problems to please report them, as each case is unique and needs to be addressed
individually.
With regard to the particular complaints brought forward by Ms. Seeger, Bright House's
Vice President of Engineering and several technicians visited her residence to
troubleshoot her issues in December. They did find a loose connection that appeared
to be a significant contributor to the problem. It was repaired, and the latest software
was applied to her converter box. In addition, they left her with a DVR, so she could
record any issues if she saw them. Bright House staff contacted Ms. Seeger this week,
and she indicated that she is still experiencing problems and will get back to them with
further details. The division president has indicated that his staff will continue to work
with her to correct the source of the problems.
Referral Response#45
Bright House Networks—Cable Service Problems
January 8, 2009
Page 2
Staff will continue to communicate with Bright House management regarding Ms.
Seeger's problems, as well as the broader technical problems that many customers are
experiencing throughout Bright House's service area. We will update you as we receive
more information from them on the results of their efforts to solve the problems.
:rks
Attachment
3701 North Sillect Avenue Joseph R. Schoenstein
Bakersfield, CA 93308 Division President
Tel (661) 634-2260 Bakersfield Division
Fax (661) 395-3378
bright
house
NETWORKS
January 5, 2009
Rhonda Smiley
Public Information Officer
City of Bakersfield
1600 Truxtun Avenue, Fifth Floor
Bakersfield, CA 93301
Dear Ms. Smiley:
Over the course of the past few months, Bright House Networks has experienced some unusual technical
issues that have impacted some of our customers. I appreciate the opportunity to provide both yourself
and the City Council some background information about these issues.
Our priority at Bright House Networks is to provide outstanding customer service. Unfortunately, the issues
that have been bedeviling us recently have left many customers disappointed.The issues fall into three
categories:
Terrestrial Interference
Bright House Networks has invested millions of dollars in upgrading our plant and infrastructure over the
past several years. Recently we have experienced some issues with terrestrial interference with the
reception of our signals from one particular satellite. The channels impacted included Fox News Channel,
Lifetime, Speed, Golf, the Encore Movie channels, HGTV, Food and the California Channel.This external
interference has been random in nature and, unfortunately, out of our control. I can report that it has
affected more cable systems than just Bright House Networks.
In an effort to isolate the root cause, we have been in contact with four cable systems in the area:Time
Warner Cable in Barstow; Charter in Porterville; Comcast in Coalinga; and Suddenlink in Bishop.These cable
systems, along with our stand-alone system in Avenal, all experienced this same kind of terrestrial
interference on the same channels during the same time frame.The FCC was engaged in mid-November to
help us isolate the problem, as it appears someone is using a frequency they should not be on. Further, a
firm that specializes in tracking this type of issue has also been engaged. The interference typically started
around 5 PM and stopped around 8 PM. It went on for several weeks, and then stopped. It has reappeared
only intermittently recently.
We will continue to work with the FCC and the other cable operators to locate the source of this
interference and get it stopped once and for all.
Converter Box Related Issues
Some of the issues we have had recently trace back to the converter boxes we have deployed in the
field. These issues include audio fade and/or no audio as well as freezing.
As you are aware, Bright House Networks partners with credible national vendors including Scientific
Atlanta (now owned by Cisco).As soon as these problems began emerging, we engaged our vendors and
have been able to isolate several issues. The vendors developed software "patches" to resolve some of
these problems. We have seen a significant decrease in these issues, but continue to have constant
monitoring not only here with our local Bright House Network engineering team, but also in our vendor
laboratories.Additional "patches" are in testing now, and we are hopeful they will provide further relief.
Recently acquired Suddenlink system
As the City is aware, Bright House Networks completed the acquisition of the Suddenlink cable system in
July of 2007. We have been diligently working to upgrade the newly acquired cable plant to support all of
the advanced services Bright House Networks offers including Digital home phone service and On Demand
channels. The physical transition of this system has taken the better part of the year.There have been
significant improvements and upgrades made to the Suddenlink cable plant, fiber and overall infrastructure
to allow the launch of these popular interactive services including My Account on Demand, Movies on
Demand, popular new High Definition channels and upwards of 23 Free on Demand channels. Because of
the magnitude and thoroughness required of these efforts, this project has taken longer than we would
have liked and caused greater disruptions of service; however, we have proactively communicated with
customers including multiple automated informational calls. We are pleased to report that we are not only
coming to completion of this project, but also have been able to increase the availability of services to
customers and also increase our cable plant reliability going forward. Additionally, we are utilizing
frequencies in these homes that have not been used before, and this can expose problems with the wiring
in the home, including loose fittings and/or poor quality or cracked cables, which require a service call to
identify and repair.
In summary, we are aware that these technical issues exist and we have committed a significant amount of
both local and corporate resources to find resolution as quickly as possible.Those resources will continue
to be focused on these issues until they are fully resolved.We are confident that we are making good
progress toward that end. In the meantime, if customers have concerns they should be encouraged to
contact us so that we can troubleshoot their particular issues. As you can see from the above, there is no
single smoking gun or fix. Each case is different.
On a related note, you will be pleased to hear that we continue to make it easier for our customers to
interact with us. Over the last year, we have expanded our local customer service phone hours by an
additional 15 hours per week, extending our hours from 7:00 a.m.-10:00 p.m. Monday—Friday for customer
convenience. In addition, the appointment times for service calls have been narrowed down to as low as a
one-hour window. We continue to work diligently to schedule as many service calls in tighter windows as
possible.
Thank you for the opportunity to address these concerns. We remain committed to delivering the highest
quality service, and are confident we'll have these issues tackled shortly.
Please let me know if you have any questions.
Sincerely,
Joe Schoenstein
Division President