� JUNE 8, 2016 COUNCIL MEETING
I�',' -;a REGULAR MEETING - 3:30 p.m.
NOTE: A separate meeting will be called to order at 3:30 p.m., followed by Public Statements
that will encourage comments pertaining to the Workshop and Closed Session matters only.
The Council will then recess into Closed Session. Upon conclusion of the Closed Session, any
Closed Session action will be announced prior to adjournment of the meeting. At 5:15 p.m.,
the Regular Meeting will be called to order to address the remainder of the agenda items.
CLOSED SESSION
There will be a conference with legal counsel regarding two items of pending litigation.
WORKSHOPS
Item 5a. Pavement Management System. Representatives from the City's consultant NCE
and Public Works staff will provide an overview of the Pavement Management System.
Item 5b. Updated State Water Conservation Regulations. Water Resources staff will provide
an overview and recommendations associated with new water conservation regulations
recently approved by the State.
REGULAR MEETING - 5:15 p.m.
APPOINTMENTS
There will be one appointment to the Keep Bakersfield Beautiful Committee.
CONSENT CALENDAR
Bids
Item 8ab & 8ac. Phase III Sports Village Construction. Phase III of the State Farm Sports
Village is designed to include amenities including a principal soccer, field sports lighting,
roadway lighting, parking lot lighting, playground equipment, restroom facilities, picnic
pavilions, landscape and irrigation improvements, and expansion of the existing lake. Phase
III originally went to bid in Fall 2015; however, the bids received exceeded available funding.
After rejection of those bids, the Phase III elements were redesigned and repackaged into
five distinct construction packages as a method to reduce the overall costs. Bids for two of
these five packages (Electrical Improvements and the Structures /Building Improvements)
have come in under the engineer's estimate and within available budget. Staff is
recommending the City Council award these two packages to begin construction of Phase
III.
M
Miscellaneous
Item 8aj. Updates to Mayor and City Council Reimbursement Policy. The Mayor and
City Council have an established policy which allows for advance reimbursement of certain
expenses associated with specific events. The specific events are listed in an exhibit that
accompanies the policy. Since the policy was approved by the City Council in 2006, there
have been additional events that City Councilmembers attended on a regular basis which
involve issues affecting the City. As such, Councilmembers Rivera and Parlier have requested
three new events be added to the list. These events include: All League of California Cities -
established Board, Committee and Caucus meetings and events; formal State legislative
testimony opportunities on legislation affecting the City in which the City Council has taken a
formal position; and the Kern Economic Development Corporation Kern County Economic
Summit. If approved, it would allow for the Mayor or Councilmember(s) to receive advance
reimbursement for certain travel expenses for these aforementioned events. No other
components of the policy are proposed to be modified or changed.
DEFERRED BUSINESS
Item 9a. 24th Street 2016 Final Environmental Impact Report. The 24th Street Improvement
Project is part of the Thomas Roads improvement Program (TRIP) for which the City is the lead
agency in accordance with the California Environmental Quality Act. The project proposes
to widen 24th Street and make other improvements to enhance traffic flow. In February 2014
the City certified the original Final Environmental Impact Report (EIR) for the project. Shortly
after this occurred, a group challenged the adequacy and completeness of the original EIR.
In July 2015, the Court ruled that the original EIR did not fully address two items, the additional
cul -de -sacs requested by local residents and eight potentially feasible alternatives to the
project. As a result of this finding, the Court ordered the City decertify the original EIR and
issued an injunction, which stopped all work on the project. To satisfy the Court's concerns
regarding the original EIR, the City prepared a Recirculated Draft Environmental Impact
Report (R -DEIR) that comprehensively addresses the additional cul -de -sacs requested by
local residents and eight potentially feasible alternatives to the project. In January 2016, the
R -DEIR was released for public review and comment. Throughout the public review period,
the City received written comments, oral testimony and signed petitions from a total of 120
persons. Approximately 70 percent of persons responding were in support of the project, 12
percent were opposed, and 18 percent were neutral. Staff is requesting the City Council
approve a resolution certifying the new EIR and approving the project. This item was
continued from the Council's May 18th meeting to allow for responses to comments that
arose during the public hearing, as well as comments made by Councilmembers after the
hearing was closed. Staff is requesting the Council certify the EIR and approve the project.
CONSENT CALENDAR PUBLIC HEARINGS
Items 10d & 10e. Refuse and Sewer Rates. Staff is proposing to increase refuse rates by 3
percent and sewer rates by 2.4 percent beginning July 1, 2016. Sewer and garbage services
provided by the City operate as standalone, business -like activities. The operations,
maintenance, capital projects and debt service (if applicable) of each service is accounted
for separately from all other City operations. Staff continuously evaluates the cost to provide
Agenda Highlights - June 8, 2016 Council Meeting
Page 2
M
each service, which in turn determines whether an annual rate increase is necessary to cover
all anticipated costs to provide each service. Over the past five years, staff has only
proposed two rate increases for sewer and garbage services. Under staff's proposal, a single -
family residence would see an increase of $5.70 annually for tan trash container, green
waste container, blue recycling container, bulky item collection, curbside motor oil
collection, a free greenwaste drop off and street sweeping services. Additionally,
commercial rates are proposed to increase 3 percent. For sewer rates, staff is proposing a
rate increase of $5 annually for a single - family residence. Commercial sewer rates are
proposed to increase by 5.8 %. Sewer connection fees are not proposed to increase in FY
2016 -17.
HEARINGS
Item 1 La. FY 2016 -17 Budget Hearing. This item provides for an opportunity for the Council to
receive public comment on the City's proposed budget prior to its adoption. Final adoption
of the budget is scheduled for June 29, 2016.
Item 11.b. Domestic Water Rates. Staff is proposing a rate increase for domestic water users
for the first time in over 5 years. Staff is proposing to increase quantity rates, readiness to serve
charge and the private fire protection service charge by 3.5 percent. The specific dollar
increase to each user is variable depending on the size of water meter installed at a specific
property and actual water usage. The proposed increase will help meet the costs of new
water supply programs, meeting water quality standards, and funding for capital costs. Due
to a delay in mailing required notices to some affected customers, staff is proposing the City
Council open the public hearing, take testimony and continue to the hearing until June 29,
2016 to allow for additional testimony.