Loading...
HomeMy WebLinkAboutAGRMT NO KRGSA 16-001(2) CCO1KRGSA 16=001(2) CC01 CHANGE ORDER Kern River Groundwater Sustainability Agency "KRGSA" Date: March 5, 2020 Project: KRGSA Groundwater Sustainability Plan Change Order #: 01 Owner: KRGSA Contractor: HORIZON WATER AND ENVIRONMENT Contract #: KRGSA 16-001(2) CONTRACT CHANGE ORDER See attached memorandum for specific details for Proposed Change Orders. The following Proposed Change Order(s) are incorporated into the Contract by reference: Summary Description: Amount: 1. Basin coordination, community outreach, and public meetings $5,733.32 Amount of this Change Order: $5,733.32 The adjustment in the contract sum set out in this Change Order shall constitute the entire compensation due Contractor arising out of the change in the work covered by this Change Order. No additions or deletions to this Change Order shall be allowed, except with written permission of the KRGSA. This Change Order is hereby agreed to, accepted and approved by: Horizon Water and Environment, LLC: Kenneth M. Sch , Principal KRGSA: Rodney Palla, Chairman Date: '09:�''C 2?1 2 o Z D Date: ��5-Z-d Horizon WATER and ENVIRONMENT Memorandum Subject: Request for Budget Augmentation Date: February 19, 2020 To: Art Chianello, City of Bakersfield From: Ken Schwarz, Horizon Water and Environment This memorandum summarizes Horizon's request for a budget augmentation from the KRGSA for services provided by Horizon in support of developing the KRGSA's Groundwater Sustainability Plan (GSP). Horizon's contract amount to support the GSP ($193,733.32) was used to support or develop several aspects of the GSP. Horizon had key roles in providing basin coordination, developing the GSP community outreach and engagement plan, conducting several community outreach and engagement activities, and assisting to assemble and complete the GSP document in coordination with Todd Groundwater and the KRGSA management team. At this time, Horizon is requesting a budget augmentation to cover the out -of -contract amount of our December/January billing, $5,733.32 During the contract period (June 2016 to date),. Horizon's efforts to support the GSP development process exceeded the anticipated level of effort provided in our original scope of work, including: ■ Task 2 — Basin Coordination: Over the contract period, Horizon coordinated extensively with other GSAs in the Kern County Subbasin; attended meetings and workshops hosted by Subbasin GSAs; attended workshops and webinars organized by DWR on GSP- and SGMA- related topics. We have also monitored, tracked, and recorded coordination efforts throughout the Basin for inclusion in the GSP as part of the Communication and Engagement Plan appendix. Several of these tasks were conducted to a greater level of effort than originally scoped. ■ Task 4 — Draft Communication Plan and Initial Community Outreach: Under this task, Horizon was scoped to provide a draft and final Communication and Engagement Plan, participate in one meeting to review the plan, and participate in up to two stakeholder meetings. Development of the plan extended well beyond the anticipated July to November 2016 timeframe, with the draft plan posted to KRGSA's website in November 2017. The plan was updated for inclusion in the draft GSP in July -August 2019, and then again for the submittal draft in December 2019/January 2020. Rather than two stakeholder meetings, Horizon and Self Help Enterprises (SHE) conducted four meetings —two introductory meetings to familiarize stakeholders with SGMA in summer 2018 and two additional meetings to summarize the contents of the draft GSP in fall 2019. SHE's assistance was not scoped or included in Horizon's original work plan. SHE helped facilitate these additional meetings at a cost to Horizon of $13,975.71. ■ Task 8 — Program Communications and Meetings: Horizon was scoped to participate in team conference calls and meetings from June 2016 through January 2020, as well as 1 MHorizon HER and ENVIRONMENT coordinating directly with Todd Groundwater on GSP schedule development. Our scope included "up to 5 additional meetings" not covered in other tasks; that number was exceeded early in the contract period, with Quad Knopf attending five board meetings by November 2017 and Horizon attending several additional meetings. We also engaged in several periods of extensive coordination with KRGSA staff related to various milestones in the GSP development and review process, including key participation at the following Board meetings: June 2018; August and October -November 2018, leading up to public workshops; February 2019; and September -October 2019, during the GSP public review period. In sum, Horizon spent additional effort on this task beyond what was originally scoped. As a result of these additional activities in support of KRGSA's GSP, Horizon is requesting complete payment for our latest invoice, which included $5,733.32 of charges over the contract amount. We greatly appreciate our working relationship with KRGSA, and we look forward to assisting with implementation of the GSP and the other important activities the agency is conducting on behalf of the City and the Kern County Subbasin. Feel free to contact me for additional information as needed.